25R1303 P614 Note16.pdf
PDF 364 KB Posted
- Attached to
- FY24 MCON P-614 JOINT CONSOLIDATED COMMUNICATIONS CENTER, US JOINT REGION MARIANAS, ANDERSEN, GUAM
- Solicitation number
- N6274225R1303
About this file
This document is a Pre-Proposal Questions & Answers (Notice No. 16) for RFP N62742-25-R-1303, related to the FY24 MCON Project P-614 Joint Consolidated Communications Center at Joint Region Marianas Andersen, Guam. The notice addresses three specific technical questions deferred from a previous notice: 1) clarification on the type of raised access flooring to be used (Cementitious-Filled Formed Steel Composite Panels), 2) request for seismic separation joint details for ceilings over 2,500 SF, and 3) inquiries about finish schedules for exterior structures.
The document indicates that the specification for access flooring (Spec 09 69 13) and Drawing Sheet A-511A will be revised in a forthcoming amendment to provide the requested details. For the exterior structures like the Electrical Yard, Fuel Tank Building, Mechanical Enclosure, Switchgear enclosure, and Trash Enclosure, the Navy clarified these are not intended to be in the Room Finish Schedule but will be included in an Exterior Finish Schedule on Sheet A-602A. These revisions will be made in a future amendment to the solicitation.
View the file
Other files
Show 40 more
Latest 50 of 89 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND PACIFIC
258 MAKALAPA DR STE 100
PEARL HARBOR HI 96860-3134
RFP N62742-25-R-1303
Notice No. 16
Notice No. 16 08 May 2025
PRE-PROPOSAL QUESTIONS & ANSWERS
RFP N62742-25-R-1303
FY24 MCON PROJECT P-614 JOINT CONSOLIDATED COMMUNICATIONS
CENTER JOINT REGION MARIANAS ANDERSEN, GUAM
NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.
RESPONSES DEFERRED FROM NOTICE NO. 14 DATED 06 MAY 2025
250. In Specification 09 69 13 Rigid Grid Access Flooring, there are two varieties of access flooring, the Hollow Formed Steel (section 2.2.3.1) and Cementitious-Filled Formed Steel (Composite Panels) (section 2.3.3.2). Please clarify what kind of raised access flooring will be used.
ANSWER: Use Cementitious-Filled Form Steel (Composite Panels). Spec 09 69 13 will be revised in forthcoming amendment
251. As per Drawing Sheet No A-511A, Ceiling Details, Seismic Separation Joint is required for a ceiling with area greater than 2500 SF, however there are no details provided.
Please provide details for seismic separation joints.
ANSWER: Sheet A-511A will be revised in forthcoming amendment to include seismic separation joint detail.
253. The following buildings/enclosures are not included in the Room Finish Schedule.
Please provide Wall, Floor, and other required finishes for this building.
1. Electrical Yard
2. Fuel Tank Building
3. Mechanical Enclosure
4. Switchgear enclosure
5. Trash Enclosure
ANSWER: These are exterior structures and not intended to be in the Room Finish Schedule.
Will clarify and include in Exterior Finish Schedule. Sheet A-602A will be revised in forthcoming amendment.