12_25R1303_26 24 13_Amd0008.pdf
PDF 106 KB Posted
- Attached to
- FY24 MCON P-614 JOINT CONSOLIDATED COMMUNICATIONS CENTER, US JOINT REGION MARIANAS, ANDERSEN, GUAM
- Solicitation number
- N6274225R1303
About this file
This document is a technical specification for switchboards (Section 26 24 13) for the FY24 MCON P-614 Joint Consolidated Communications Center project at Andersen Air Force Base in Guam. The specification provides detailed requirements for switchboard construction, including electrical ratings of 480 volts AC, three-phase, with specific provisions for bus bars, protective devices, circuit breakers, metering, and grounding systems. Key technical requirements include front-accessible circuit breakers, drawout breakers with four-position operation, electronic trip units with digital displays and communication capabilities, and digital meters with advanced monitoring and logging features.
The specification outlines comprehensive testing and quality assurance requirements, including visual and mechanical inspections, electrical tests, ground resistance measurements, and follow-up verification procedures. Switchboards must comply with multiple industry standards including NEMA PB 2, UL 891, and NFPA 70, and must include features such as arc flash warning labels, galvanized steel enclosures, and grounding systems with resistance not exceeding 5 ohms. The document provides extensive details on installation, foundation requirements, equipment mounting, and post-installation testing protocols to ensure proper functionality and safety of the electrical switchboard systems.
View the file
Other files
Show 40 more
Latest 50 of 89 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY24 MCON P-614 JOINT CONSOLIDATED COMMUNICATIONS CENTER 1737021
JOINT REGION MARIANAS, ANDERSEN AIR FORCE BASE
SECTION 26 24 13
SWITCHBOARDS
08/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI C12.1 (2014; Errata 2016) Electric Meters - Code for Electricity Metering
ASTM INTERNATIONAL (ASTM)
ASTM A123/A123M (2017) Standard Specification for Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
ASTM A153/A153M (2023) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware
ASTM A653/A653M (2023) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM A780/A780M (2020) Standard Practice for Repair of Damaged and Uncoated Areas of Hot-Dip Galvanized Coatings
ASTM D149 (2020) Dielectric Breakdown Voltage and Dielectric Strength of Solid Electrical Insulating Materials at Commercial Power Frequencies
ASTM D709 (2017) Standard Specification for Laminated Thermosetting Materials
ASTM D1535 (2014; R 2018) Standard Practice for Specifying Color by the Munsell System
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 81 (2012) Guide for Measuring Earth Resistivity, Ground Impedance, and Earth Surface Potentials of a Ground System
IEEE 100 (2000; Archived) The Authoritative Dictionary of IEEE Standards Terms
IEEE C2 (2023) National Electrical Safety Code
SECTION 26 24 13 Page 1
Amendment No. 0008 26 24 13 SWITCHBOARDS, dated April 14, 2025
IEEE C37.90.1 (2013) Standard for Surge Withstand Capability (SWC) Tests for Relays and Relay Systems Associated with Electric Power Apparatus
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2021) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems
NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)
ANSI/NEMA PB 2.1 (2013) General Instructions for Proper Handling, Installation, Operation and Maintenance of Deadfront Distribution Switchboards Rated 600 V or Less
NEMA ICS 6 (1993; R 2016) Industrial Control and Systems: Enclosures
NEMA PB 2 (2011) Deadfront Distribution Switchboards
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2023; ERTA 4 2023; ERTA 5 2023; ERTA 6
2023) National Electrical Code
UNDERWRITERS LABORATORIES (UL)
UL 467 (2022) UL Standard for Safety Grounding and Bonding Equipment
UL 489 (2016; Rev 2019) UL Standard for Safety Molded-Case Circuit Breakers, Molded-Case Switches and Circuit-Breaker Enclosures
UL 891 (2019) UL Standard for Safety Switchboards
1.2 RELATED REQUIREMENTS
Section 26 08 00 APPARATUS INSPECTION AND TESTING applies to this section, with the additions and modifications specified herein.
1.3 DEFINITIONS
Unless otherwise specified or indicated, electrical and electronics terms used in these specifications, and on the drawings, are as defined in
IEEE 100 .
1.4 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval.Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
SECTION 26 24 13 Page 2
Switchboard Drawings; G
SD-03 Product Data
Switchboard; G
SD-06 Test Reports
Switchboard Design Tests; G
Switchboard Production Tests; G
Acceptance Checks and Tests; G
SD-10 Operation and Maintenance Data
Switchboard Operation and Maintenance, Data Package 5; G
SD-11 Closeout Submittals
Assembled Operation and Maintenance Manuals; G
Equipment Test Schedule; G
1.5 QUALITY ASSURANCE
1.5.1 Product Data
Include manufacturer's information on each submittal for each component, device and accessory provided with the switchboard including:
a. Circuit breaker type, interrupting rating, and trip devices, including available settings.
b. Manufacturer's instruction manuals and published time-current curves (in electronic format) of the main secondary breaker and largest secondary feeder device.
1.5.2 Switchboard Drawings
Include wiring diagrams and installation details of equipment indicating proposed location, layout and arrangement, control panels, accessories, piping, ductwork, and other items that must be shown to ensure a coordinated installation. Identify circuit terminals on wiring diagrams and indicate the internal wiring for each item of equipment and the interconnection between each item of equipment. Indicate on the drawings adequate clearance for operation, maintenance, and replacement of operating equipment devices. Include the nameplate data, size, and capacity on submittal. Also include applicable federal, military, industry, and technical society publication references on submittals.
Include the following:
a. One-line diagram including breakers, current transformers,potential transformers, and meters.
b. Outline drawings including front elevation, section views, footprint, and overall dimensions.
SECTION 26 24 13 Page 3
c. Bus configuration including dimensions and ampere ratings of bus bars.
d. Markings and NEMA nameplate data.
e. Circuit breaker type, interrupting rating, and trip devices, including available settings.
f. Wiring diagrams and elementary diagrams with terminals identified, and indicating prewired interconnections between items of equipment and the interconnection between the items.
g. Manufacturer's instruction manuals and published time-current curves (in electronic format) of the main secondary breaker and largest secondary feeder device. Use this information (designer of record) to provide breaker settings that ensures protection and coordination are achieved.
1.5.3 Regulatory Requirements
In each of the publications referred to herein, consider the advisory provisions to be mandatory, as though the word, "shall" or "must" had been substituted for "should" wherever it appears. Interpret references in these publications to the "authority having jurisdiction," or words of similar meaning, to mean the Contracting Officer. Provide equipment, materials, installation, and workmanship in accordance with the mandatory and advisory provisions of NFPA 70 unless more stringent requirements are specified or indicated.
1.5.4 Standard Products
Provide materials and equipment that are products of manufacturers regularly engaged in the production of such products which are of equal material, design and workmanship, and:
a. Have been in satisfactory commercial or industrial use for 2 years prior to bid opening including applications of equipment and materials under similar circumstances and of similar size.
b. Have been on sale on the commercial market through advertisements, manufacturers' catalogs, or brochures during the 2-year period.
c. Where two or more items of the same class of equipment are required, provide products of a single manufacturer; however, the component parts of the item need not be the products of the same manufacturer unless stated in this section.
1.5.4.1 Alternative Qualifications
Products having less than a 2-year field service record will be acceptable if a certified record of satisfactory field operation for not less than 6000 hours, exclusive of the manufacturers' factory or laboratory tests, is furnished.
1.5.4.2 Material and Equipment Manufacturing Date
Products manufactured more than one year prior to date of delivery to site are not acceptable.
SECTION 26 24 13 Page 4
1.6 MAINTENANCE
1.6.1 Switchboard Operation and Maintenance Data
Submit Operation and Maintenance Manuals in accordance with Section
01 78 23 OPERATION AND MAINTENANCE DATA.
1.6.2 Assembled Operation and Maintenance Manuals
Assemble and securely bind manuals in durable, hard covered, water resistant binders. Assemble and index the manuals in the following order with a table of contents:
a. Manufacturer's O&M information required by the paragraph SD-10, OPERATION AND MAINTENANCE DATA.
b. Catalog data required by the paragraph SD-03, PRODUCT DATA.
c. Drawings required by the paragraph SD-02, SHOP DRAWINGS.
d. Prices for spare parts and supply list.
e. Information on metering.
f. Design test reports.
g. Production test reports.
1.7 WARRANTY
Provide equipment items that are supported by service organizations reasonably convenient to the equipment installation in order to render satisfactory service to the equipment on a regular and emergency basis during the warranty period of the contract.
PART 2 PRODUCTS
2.1 PRODUCT COORDINATION
Products and materials not considered to be switchboards and related accessories are specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION, and Section 26 20 00 INTERIOR DISTRIBUTION SYSTEM.
2.2 SWITCHBOARD
NEMA PB 2 and UL 891 .
2.2.1 Ratings
Provide equipment with the following ratings:
a. Voltage rating: 480 volts AC, three-phase, 3-wire.
b. Continuous current rating of the main bus: as indicated.
c. Short-circuit current rating: as indicated.
d. UL listed and labeled.
SECTION 26 24 13 Page 5
2.2.2 Construction
Provide the following:
a. Switchboard: consisting of one or more vertical sections bolted together to form a rigid assembly and front and rear aligned as indicated.
b. All circuit breakers: front accessible.
c. Front accessible, front and rear aligned switchboards: front accessible load connections.
d. Where indicated, "space for future" or "space" means to include a vertical bus provided behind a blank front cover. Where indicated, "provision for future" means full hardware provided to mount a breaker suitable for the location.
e. Completely factory engineered and assembled, including protective devices and equipment indicated with necessary interconnections, instrumentation, and control wiring.
2.2.2.1 Enclosure
Provide the following:
a. Enclosure: NEMA ICS 6 Type 1.
b. Enclosure: bolted together with removable bolt-on side and rear covers.
c. Bases, frames and channels of enclosure: corrosion resistant and fabricated of galvanized steel.
d. Base: includes any part of enclosure that is within 3 inches of concrete pad.
e. Galvanized steel: ASTM A123/A123M , ASTM A653/A653M G90 coating, and ASTM A153/A153M , as applicable. Galvanize after fabrication where practicable.
f. Paint color: ASTM D1535 light gray No. 61 or No. 49 over rust inhibitor.
2.2.2.2 Bus Bars
Provide the following:
a. Bus bars: copper with silver-plated contact surfaces or aluminum with tin-plated contact surfaces.
(1) Phase bus bars: insulated with a tape wrap or insulating sleeve providing a minimum breakdown voltage of 16,000 volts per ASTM D149.
b. Make bus connections and joints with hardened steel bolts.
c. Main-bus (through bus): rated at the full ampacity of the main throughout the switchboard.
d. Minimum one-quarter by 2 inch copper ground bus secured to each
SECTION 26 24 13 Page 6 vertical section along the entire length of the switchboard.
2.2.2.3 Main Section and Bus Tie Sections
Provide the main section and bus tie sections consisting of an individually mounted drawout air power circuit breaker and utility transformer compartment.
2.2.2.4 Distribution Sections
Provide the distribution sections consisting ofdrawout,molded case air power circuit breakers as indicated.
2.2.2.5 Miscellaneous Devices
a. Provide kirk key interlocks as indicated.
b. Provide control power transformers with primary and secondary protection for proper operation of equipment. Control power transformers must have a secondary voltage of 120VAC.
2.2.2.6 Handles
Provide handles for individually mounted devices of the same design and method of external operation. Label handles prominently to indicate device ampere rating, color coded for device type. Identify ON-OFF indication by handle position and by prominent marking.
2.2.3 Protective Device
Provide main and branch protective devices as indicated.
2.2.3.1 Molded-Case Circuit Breaker
Provide the following:
a. UL 489 . UL listed and labeled, standard rated branch breakers manually operated, drawout,low voltage molded-case circuit breaker, with a short-circuit current rating of 100kA rms symmetrical amperes at 480 volts.
b. Breaker frame size: as indicated.
c. Series rated circuit breakers are unacceptable.
d. Molded case circuit breaker load connections must be front accessible to ensure that switchboard can be wall mounted.
2.2.3.2 Insulated-Case Breaker
Provide the following for Main and Tie Breakers:
a. UL listed and labeled, 100 percent rated main breaker, electrically operated, low voltage, insulated-case circuit breaker, with a short-circuit rating as indicated at 480 volts.
b. Breaker frame size as indicated.
c. Series rated circuit breakers are unacceptable.
SECTION 26 24 13 Page 7
2.2.4 Drawout Breakers
Provide drawout breakers as indicated. Main and tie breakers must be designed for continuous operations at 100 percent of the current rating.
Equip drawout breakers with disconnecting contacts, wheels, and interlocks for drawout application. Provide main, auxiliary, and control disconnecting contacts with silver-plated, multifinger, positive pressure, self-aligning type. Provide each drawout breaker with four-position operation with each position clearly identified by an indicator on the circuit breaker front panel as follows.
a. Connected Position: Primary and secondary contacts are fully engaged. Breaker must be tripped before racking into or out of position.
b. Test Position: Primary contacts are disconnected but secondary contacts remain fully engaged. This position allows complete test and operation of the breaker without energizing the primary circuit.
c. Disconnected Position: Primary and secondary contacts are disconnected.
d. Withdrawn (Removed) Position: Places breaker completely out of compartment, ready for removal. Removal of the breaker actuates assembly that isolates the primary stabs.
2.2.5 Electronic Trip Units
Equip main and distribution breakers with a solid-state tripping system consisting of three current sensors and a microprocessor-based trip unit that provides true rms sensing adjustable time-current circuit protection. Include the following:
a. Current sensors ampere rating: as indicated.
b. Trip unit ampere rating: as indicated.
c. Ground fault protection: as indicated.
(1) Indicated Breakers: include long delay pick-up and time settings, and LED indication of cause of circuit breaker trip.
(2) Main breakers: include short delay pick-up and time settings and, instantaneous settings and ground fault settings as indicated.
(3) Distribution breakers: include short delay pick-up and time settings, instantaneous settings, and ground fault settings as indicated.
(4) Main and Tie Breakers: include a digital display for phase and ground current.
(5) Main Breakers: include a digital display for watts, vars, VA, kWh, kvarh, and kVAh.
(6) Main Breakers: include provisions for communication via a network twisted pair cable for remote monitoring and control. Provide the following communications protocol:Modbus.
SECTION 26 24 13 Page 8
(7) For electronic trip units that are rated for or can be adjusted to 1,200 amperes or higher, provide arc energy reduction capability with an energy-reducing maintenance switch with local status indicator.
2.2.6 Metering
2.2.6.1 Digital Meters
IEEE C37.90.1 for surge withstand. Provide true rms, plus/minus one percent accuracy, programmable, microprocessor-based meter enclosed in a sealed case with the following features.
a. Display capability:
(1) Multi-Function Meter: Display a selected phase to phase voltage, percent phase to phase voltage THD; a selected phase current, neutral current, percent phase current THD, selected total PF, kW, KVA, kVAR, FREQ, kVAh, kWh. Detected alarm conditions include over/under current, over/under voltage, over/under KVA, over/under frequency, over/under selected PF/kVAR, voltage phase reversal, voltage imbalance, reverse power, over percent THD. Include a Form C KYZ pulse output relay on the meter.
b. Design meters to accept input from standard 5A secondary instrument transformers direct voltage monitoring range to 600 volts, phase to phase.
c. Provide programming via a front panel display and a communication interface accessible by a computer.
d. Provide password secured programming stored in non-volatile EEPROM memory.
e. Provide digital communications using fiber optic multimode medium with a preferrred Modbus RTU protocol and an independently addressable communications port.
f. Provide meter that calculates and stores average max/min demand values with time and date for all readings based on a user selectable sliding window averaging period.
g. Provide meter with programmable hi/low set limits with two Form C dry contact relays when exceeding alarm conditions.
h. Include historical trend logging capability with the ability to store up to 100,000 data points with intervals of 1 second to 180 minutes.
Provide a unit that can store and time stamp up to 1000 programmable triggered conditions.
2.2.6.2 Submetering
Provide CTs for branch circuit breakers as indicated on the drawings.
Include UL listed microprocessor-based submetering system as indicated on the drawings.
a. The system must have the capability to monitor all branch circuits indicated on drawings by use of current sensors.
SECTION 26 24 13 Page 9
b. The system must automatically sense the rating of any connected current sensor.
c. The system must be capable of supporting communications via Modbus TCP, BACnet/IP, RS-485 Modbus RTU, Ethernet TCP/IP.
2.2.7 Terminal Boards
Provide with engraved plastic terminal strips and screw type terminals for external wiring between components and for internal wiring between removable assemblies. Provide short-circuiting type terminal boards associated with current transformer. Terminate conductors for current transformers with ring-tongue lugs. Provide terminal board identification that is identical in similar units. Provide color coded external wiring that is color coded consistently for similar terminal boards.
2.2.8 Wire Marking
Mark control and metering conductors at each end. Provide factory installed, white, plastic tubing, heat stamped with black block type letters on factory-installed wiring. On field-installed wiring, provide white, preprinted, polyvinyl chloride (PVC) sleeves, heat stamped with black block type letters. Provide a single letter or number on each sleeve, elliptically shaped to securely grip the wire, and keyed in such a manner to ensure alignment with adjacent sleeves. Provide specific wire markings using the appropriate combination of individual sleeves.
Indicate on each wire marker the device or equipment, including specific terminal number to which the remote end of the wire is attached.
2.3 MANUFACTURER'S NAMEPLATE
Provide a nameplate on each item of equipment bearing the manufacturer's name, address, model number, and serial number securely affixed in a conspicuous place; the nameplate of the distributing agent is not acceptable. This nameplate and method of attachment may be the manufacturer's standard if it contains the required information.
2.4 FIELD FABRICATED NAMEPLATES
ASTM D709. Provide laminated plastic nameplates for each switchboard, equipment enclosure, relay, switch, and device; as specified in this section or as indicated on the drawings. Identify on each nameplate inscription the function and, when applicable, the position. Provide nameplates of melamine plastic, 0.125 inch thick, white with blackcenter core.Provide matte finish surface. Provide square corners. Accurately align lettering and engrave into the core. Provide nameplates with minimum size of one by 2.5 inches. Provide lettering that is a minimum of
0.25 inchhigh normal block style.
2.5 SOURCE QUALITY CONTROL
2.5.1 Equipment Test Schedule
The Government reserves the right to witness tests. Provide equipment test schedules for tests to be performed at the manufacturer's test facility. Submit required test schedule and location, and notify the Contracting Officer 30 calendar days before scheduled test date. Notify Contracting Officer 15 calendar days in advance of changes to scheduled
SECTION 26 24 13 Page 10 date.
Provide the following as part of test equipment calibration:
a. Provide a calibration program which assures that all applicable test instruments are maintained within rated accuracy.
b. Accuracy: Traceable to the National Institute of Standards and Technology.
c. Instrument calibration frequency schedule: less than or equal to 12 months for both test floor instruments and leased specialty equipment.
d. Dated calibration labels: visible on all test equipment.
e. Calibrating standard: higher accuracy than that of the instrument tested.
f. Keep up-to-date records that indicate dates and test results of instruments calibrated or tested. For instruments calibrated by the manufacturer on a routine basis, in lieu of third party calibration, include the following:
(1) Maintain up-to-date instrument calibration instructions and procedures for each test instrument.
(2) Identify the third party/laboratory calibrated instrument to verify that calibrating standard is met.
2.5.2 Switchboard Design Tests
NEMA PB 2 and UL 891 .
2.5.2.1 Design Tests
Furnish documentation showing the results of design tests on a product of the same series and rating as that provided by this specification.
a. Short-circuit current test.
b. Enclosure tests.
c. Dielectric test.
2.5.3 Switchboard Production Tests
NEMA PB 2 and UL 891 . Furnish reports which include results of production tests performed on the actual equipment for this project. These tests include:
a. 60-hertz dielectric tests.
b. Mechanical operation tests.
c. Electrical operation and control wiring tests.
d. Ground fault sensing equipment test.
SECTION 26 24 13 Page 11
2.6 ARC FLASH WARNING LABEL
Provide warning label for switchboards. Locate this self-adhesive warning label on the outside of the enclosure warning of potential electrical arc flash hazards and appropriate PPE required. Provide label format as indicated.
PART 3 EXECUTION
3.1 INSTALLATION
Conform to IEEE C2 , NFPA 70 , and to the requirements specified herein.
Provide new equipment and materials unless indicated or specified otherwise.
3.2 GROUNDING
NFPA 70 and IEEE C2 , except that grounds and grounding systems with a resistance to solid earth ground not exceeding 5 ohms.
3.2.1 Grounding Electrodes
Provide driven ground rods as specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION. Connect ground conductors to the upper end of the ground rods by exothermic weld or compression connector. Provide compression connectors at equipment end of ground conductors.
3.2.2 Equipment Grounding
Provide bare copper cable not smaller than No. 4/0 AWG not less than 24 inches below grade connecting to the indicated ground rods. When work in addition to that indicated or specified is directed to obtain the specified ground resistance, the provision of the contract covering "Changes" applies.
3.2.3 Connections
Make joints in grounding conductors and loops by exothermic weld or compression connector. Install exothermic welds and compression connectors as specified in Section 33 71 02 UNDERGROUND ELECTRICAL
DISTRIBUTION.
3.2.4 Grounding and Bonding Equipment
UL 467 , except as indicated or specified otherwise.
3.3 INSTALLATION OF EQUIPMENT AND ASSEMBLIES
Install and connect equipment furnished under this section as indicated on project drawings, the approved shop drawings, and as specified herein.
3.3.1 Switchboard
ANSI/NEMA PB 2.1 .
3.3.2 Meters and Instrument Transformers
ANSI C12.1 .
SECTION 26 24 13 Page 12
3.3.3 Field Applied Painting
Where field painting of enclosures is required to correct damage to the manufacturer's factory applied coatings, provide manufacturer's recommended coatings and apply in accordance with manufacturer's instructions.
3.3.4 Galvanizing Repair
Repair damage to galvanized coatings using ASTM A780/A780M , zinc rich paint, for galvanizing damaged by handling, transporting, cutting, welding, or bolting. Do not heat surfaces that repair paint has been applied to.
3.3.5 Field Fabricated Nameplate Mounting
Provide number, location, and letter designation of nameplates as indicated. Fasten nameplates to the device with a minimum of two sheet-metal screws or two rivets.
3.4 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES
3.4.1 Exterior Location
Mount switchboard on concrete slab as follows:
a. Unless otherwise indicated, provide the slab with dimensions at least 8 inches thick, reinforced with a 6 by 6 inch No. 6 mesh placed uniformly 4 inches from the top of the slab.
b. Place slab on a 6 inch thick, well-compacted gravel base.
c. Install slab such that the top of the concrete slab is approximately 4 inches above the finished grade.
d. Provide edges above grade 1/2 inch chamfer.
e. Provide slab of adequate size to project at least 8 inches beyond the equipment.
f. Provide conduit turnups and cable entrance space required by the equipment to be mounted.
g. Seal voids around conduit openings in slab with water- and oil-resistant caulking or sealant.
h. Cut off and bush conduits 3 inches above slab surface.
i. Provide concrete work as specified in Section 03 30 00 CAST-IN-PLACE
CONCRETE.
3.4.2 Interior Location
Mount switchboard on concrete slab as follows:
a. Unless otherwise indicated, provide the slab with dimensions at least 4 inches thick.
b. Install slab such that the top of the concrete slab is approximately 4
SECTION 26 24 13 Page 13 inches above the finished grade.
c. Provide edges above grade 1/2 inch chamfer.
d. Provide slab of adequate size to project at least 8 inches beyond the equipment.
e. Provide conduit turnups and cable entrance space required by the equipment to be mounted.
f. Seal voids around conduit openings in slab with water- and oil-resistant caulking or sealant.
g. Cut off and bush conduits 3 inches above slab surface.
h. Provide concrete work as specified in Section 03 30 00 CAST-IN-PLACE
CONCRETE.
3.5 FIELD QUALITY CONTROL
Refer to Section 26 05 73 POWER SYSTEM STUDIES regarding submittal of breaker required settings.
3.5.1 Performance of Acceptance Checks and Tests
Perform in accordance with the manufacturer's recommendations and include the following visual and mechanical inspections and electrical tests, performed in accordance with NETA ATS.
3.5.1.1 Switchboard Assemblies
a. Visual and Mechanical Inspection
(1) Compare equipment nameplate data with specifications and approved shop drawings.
(2) Inspect physical, electrical, and mechanical condition.
(3) Verify appropriate anchorage, required area clearances, and correct alignment.
(4) Clean switchboard and verify shipping bracing, loose parts, and documentation shipped inside cubicles have been removed.
(5) Inspect all doors, panels, and sections for paint, dents, scratches, fit, and missing hardware.
(6) Verify that fuse and circuit breaker sizes and types correspond to approved shop drawings as well as to the circuit breaker’s address for microprocessor-communication packages.
(7) Verify that current transformer ratios correspond to approved shop drawings.
(8) Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, verifying tightness of accessible bolted electrical connections by calibrated torque-wrench method, or performing thermographic survey.
SECTION 26 24 13 Page 14
(9) Confirm correct operation and sequencing of electrical and mechanical interlock systems.
(10) Confirm correct application of manufacturer's recommended lubricants.
(11) Inspect insulators for evidence of physical damage or contaminated surfaces.
(12) Verify correct barrier installation and operation.
(13) Exercise all active components.
(14) Inspect all mechanical indicating devices for correct operation.
(15) Verify that filters are in place and vents are clear.
(16) Test operation, alignment, and penetration of instrument transformer withdrawal disconnects.
(17) Inspect control power transformers.
b. Electrical Tests
(1) Perform insulation-resistance tests on each bus section.
(2) Perform dielectric withstand voltage tests.
(3) Perform insulation-resistance test on control wiring; Do not perform this test on wiring connected to solid-state components.
(4) Perform control wiring performance test.
(5) Perform primary current injection tests on the entire current circuit in each section of assembly.
(6) Perform phasing check on double-ended switchboard to ensure correct bus phasing from each source.
3.5.1.2 Circuit Breakers - Low Voltage - Power and Low Voltage - Molded Case with Static Trips
a. Visual and Mechanical Inspection
(1) Compare nameplate data with specifications and approved shop drawings.
(2) Inspect physical and mechanical condition.
(3) Inspect anchorage, alignment, and grounding.
(4) Verify that all maintenance devices are available for servicing and operating the breaker.
(5) Inspect arc chutes.
(6) Inspect moving and stationary contacts for condition, wear, and alignment.
SECTION 26 24 13 Page 15
(7) Verify that primary and secondary contact wipe and other dimensions vital to satisfactory operation of the breaker are correct.
(8) Perform all mechanical operator and contact alignment tests on both the breaker and its operating mechanism.
(9) Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, verifying tightness of accessible bolted electrical connections by calibrated torque-wrench method, or performing thermographic survey.
(10) Verify cell fit and element alignment.
(11) Verify racking mechanism.
(12) Confirm correct application of manufacturer's recommended lubricants.
b. Electrical Tests
(1) Perform contact-resistance tests on each breaker.
(2) Perform insulation-resistance tests.
(3) Adjust Breaker(s) for final settings in accordance with Government provided settings.
(4) Determine long-time minimum pickup current by primary current injection.
(5) Determine long-time delay by primary current injection.
(6) Determine short-time pickup and delay by primary current injection.
(7) Determine ground-fault pickup and delay by primary current injection.
(8) Determine instantaneous pickup value by primary current injection.
(9) Activate auxiliary protective devices, such as ground-fault or undervoltage relays, to ensure operation of shunt trip devices;
Check the operation of electrically-operated breakers in their cubicle.
(10) Verify correct operation of any auxiliary features such as trip and pickup indicators, zone interlocking, electrical close and trip operation, trip-free, and antipump function.
(11) Verify operation of charging mechanism.
3.5.1.3 Current Transformers
a. Visual and Mechanical Inspection
(1) Compare equipment nameplate data with specifications and approved shop drawings.
(2) Inspect physical and mechanical condition.
SECTION 26 24 13 Page 16
(3) Verify correct connection.
(4) Verify that adequate clearances exist between primary and secondary circuit.
(5) Inspect all bolted electrical connections for high resistance using low-resistance ohmmeter, verifying tightness of accessible bolted electrical connections by calibrated torque-wrench method, or performing thermographic survey.
(6) Verify that all required grounding and shorting connections provide good contact.
b. Electrical Tests
(1) Perform resistance measurements through all bolted connections with low-resistance ohmmeter, if applicable.
(2) Perform insulation-resistance tests.
(3) Perform polarity tests.
(4) Perform ratio-verification tests.
3.5.1.4 Metering and Instrumentation
a. Visual and Mechanical Inspection
(1) Compare equipment nameplate data with specifications and approved shop drawings.
(2) Inspect physical and mechanical condition.
(3) Verify tightness of electrical connections.
b. Electrical Tests
(1) Determine accuracy of meters at 25, 50, 75, and 100 percent of full scale.
(2) Calibrate watthour meters according to manufacturer's published data.
(3) Verify all instrument multipliers.
(4) Electrically confirm that current transformer and voltage transformer secondary circuits are intact.
3.5.1.5 Grounding System
a. Visual and Mechanical Inspection
(1) Inspect ground system for compliance with contract plans and specifications.
b. Electrical Tests
(1) IEEE 81 . Perform ground-impedance measurements utilizing the
SECTION 26 24 13 Page 17 fall-of-potential method. On systems consisting of interconnected ground rods, perform tests after interconnections are complete.
On systems consisting of a single ground rod perform tests before any wire is connected. Take measurements in normally dry weather, not less than 48 hours after rainfall. Use a portable ground resistance tester in accordance with manufacturer's instructions to test each ground or group of grounds. Use an instrument equipped with a meter reading directly in ohms or fractions thereof to indicate the ground value of the ground rod or grounding systems under test.
(2) Submit the measured ground resistance of each ground rod and grounding system, indicating the location of the rod and grounding system. Include the test method and test setup (i.e., pin location) used to determine ground resistance and soil conditions at the time the measurements were made.
3.5.2 Follow-Up Verification
Upon completion of acceptance checks, settings, and tests, show by demonstration in service that circuits and devices are in good operating condition and properly performing the intended function. Trip circuit breakers by operation of each protective device. Test each item to perform its function not less than three times. As an exception to requirements stated elsewhere in the contract, provide the Contracting Officer five working days advance notice of the dates and times for checks, settings, and tests.
-- End of Section --
SECTION 26 24 13 Page 18
| 26 24 13 - SWITCHBOARDS |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 RELATED REQUIREMENTS |
| 1.3 DEFINITIONS |
| 1.4 SUBMITTALS |
| 1.5 QUALITY ASSURANCE |
| 1.5.1 Product Data |
| 1.5.2 Switchboard Drawings |
| 1.5.3 Regulatory Requirements |
| 1.5.4 Standard Products |
| 1.5.4.1 Alternative Qualifications |
| 1.5.4.2 Material and Equipment Manufacturing Date |
| 1.6 MAINTENANCE |
| 1.6.1 Switchboard Operation and Maintenance Data |
| 1.6.2 Assembled Operation and Maintenance Manuals |
1.7 WARRANTY
| PART 2 PRODUCTS |
| 2.1 PRODUCT COORDINATION |
| 2.2 SWITCHBOARD |
| 2.2.1 Ratings |
| 2.2.2 Construction |
| 2.2.2.1 Enclosure |
| 2.2.2.2 Bus Bars |
| 2.2.2.3 Main Section and Bus Tie Sections |
| 2.2.2.4 Distribution Sections |
| 2.2.2.5 Miscellaneous Devices |
| 2.2.2.6 Handles |
| 2.2.3 Protective Device |
| 2.2.3.1 Molded-Case Circuit Breaker |
| 2.2.3.2 Insulated-Case Breaker |
| 2.2.4 Drawout Breakers |
| 2.2.5 Electronic Trip Units |
| 2.2.6 Metering |
| 2.2.6.1 Digital Meters |
| 2.2.6.2 Submetering |
| 2.2.7 Terminal Boards |
| 2.2.8 Wire Marking |
| 2.3 MANUFACTURER'S NAMEPLATE |
| 2.4 FIELD FABRICATED NAMEPLATES |
| 2.5 SOURCE QUALITY CONTROL |
| 2.5.1 Equipment Test Schedule |
| 2.5.2 Switchboard Design Tests |
| 2.5.2.1 Design Tests |
2.5.3 Switchboard Production Tests
2.6 ARC FLASH WARNING LABEL
| PART 3 EXECUTION |
| 3.1 INSTALLATION |
| 3.2 GROUNDING |
| 3.2.1 Grounding Electrodes |
| 3.2.2 Equipment Grounding |
| 3.2.3 Connections |
| 3.2.4 Grounding and Bonding Equipment |
| 3.3 INSTALLATION OF EQUIPMENT AND ASSEMBLIES |
| 3.3.1 Switchboard |
| 3.3.2 Meters and Instrument Transformers |
| 3.3.3 Field Applied Painting |
| 3.3.4 Galvanizing Repair |
| 3.3.5 Field Fabricated Nameplate Mounting |
| 3.4 FOUNDATION FOR EQUIPMENT AND ASSEMBLIES |
| 3.4.1 Exterior Location |
| 3.4.2 Interior Location |
| 3.5 FIELD QUALITY CONTROL |
| 3.5.1 Performance of Acceptance Checks and Tests |
| 3.5.1.1 Switchboard Assemblies |
| 3.5.1.2 Circuit Breakers - Low Voltage - Power and Low Voltage - Molded |
| 3.5.1.3 Current Transformers |
| 3.5.1.4 Metering and Instrumentation |
| 3.5.1.5 Grounding System |
3.5.2 Follow-Up Verification
File details come from the government source that posted it. Updated .