02_25R1303_01 57 19.03 20_Amd0008.pdf
PDF 5 MB Posted
- Attached to
- FY24 MCON P-614 JOINT CONSOLIDATED COMMUNICATIONS CENTER, US JOINT REGION MARIANAS, ANDERSEN, GUAM
- Solicitation number
- N6274225R1303
About this file
This document is a Supplemental Temporary Environmental Controls specification (Section 01 57 19.03 20) for the FY24 MCON P-614 Joint Consolidated Communications Center project at Andersen Air Force Base, Guam. The specification provides detailed requirements for munitions response explosives safety submission (MRESS) and construction support, focusing on environmental controls and safety protocols for potential munitions and explosives of concern (MEC/MPPEH) encountered during the project.
Key requirements include comprehensive submittal procedures, personnel qualifications, and safety protocols for handling potential unexploded ordnance. Contractors must submit detailed work plans, documentation of training, community relations plans, and site health and safety plans. The specification mandates specific procedures for MEC/MPPEH encounter, including immediate notification protocols, spot reporting, and strict safety measures. Personnel must meet qualification standards defined in DDESB TP 18, with roles including Unexploded Ordnance Safety Officer (UXOSO), UXO Quality Control Specialist (UXOQCS), and Senior UXO Supervisor (SUXOS). The document emphasizes rigorous quality control, geographic information system (GIS) documentation, and comprehensive reporting requirements throughout the munitions response process.
View the file
Other files
Show 40 more
Latest 50 of 89 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY24 MCON P-614 JOINT CONSOLIDATED COMMUNICATIONS CENTER 1737021
JOINT REGION MARIANAS, ANDERSEN AIR FORCE BASE
SECTION 01 57 19.03 20
SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
Munitions Response Explosives Safety Submission (MRESS) Guam Construction
Support 08/22
PART 1 GENERAL
1.1 SUBMITTALS
Government acceptance is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Work Plan; G
Record of Training; G
Comprehensive Community Relations Plan; G (submitted concurrently with other preconstruction submittals)
Installation Commanding Officer (ICO) Notification; G (submitted concurrently with other preconstruction submittals)
Geographic Information System (GIS) Work Area Grid; G (submitted concurrently with other preconstruction submittals)
Personnel Qualifications and Duties; G
Site Health and Safety Plan (SHSP); G
Occupancy, Population and Vehicle Survey; G
SD-06 Test Reports
QC Report (req'd as part of the daily construction QC reports); G
Munitions and Explosives of Concern (MEC)/Material Potentially Presenting an Explosive Hazard (MPPEH) Spot Reports; G
Munitions and Explosives of Concern MEC/ MPPEH Close-Out Report; G
Bedrock Determinations G
In Situ Native Stratified Soil Determinations; G
Instrument Verification Strip IVS Results; G
SD-11 Closeout Submittals
GIS Data; G
After Action Reports; G
SECTION 01 57 19.03 20 Page 1
Amendment No. 0008 01 57 19.03 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS, dated April 14, 2025
1.1.1 SUBMITTAL SCHEDULE
Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated.
Except as specified otherwise, allow review period, beginning with receipt by accepting authority, to include 30 working days for submittals for Contracting Officer, which may include Installation Commanding Officer approval. Period of review for submittals requiring Government approval begins when the Government receives the submittal from the QC organization.
The review period for each resubmittal is the same as for the initial submittal.
1.2 DOCUMENTATION
Maintain a copy of the following documents on site and available to Government representatives upon request:
a. Latest version of the Guam Construction Support Munitions Response Explosives Safety MRESS, including the project-specific annex
b. Work Plan
c. NOSSA ltr 8020 Ser N45G/080 of 17 Jan 20 (WebESS ID# 547/ESS 19-24)
d. DDESB memo DDESB-PE of 24 Aug 18 (GG-052MOD)
e. NAVSEA OP 5
f. Other previous DDESB approvals
g. DDESB memo DDESB-PE of 24 Jan 20
h. Quality Control Log
i. Safety Meeting Attendance Log
j. Site Visitors Log
k. Safety Inspection Logs
l. Daily Report of MEC Operation
m. MPPEH Accountability Forms
1.3 ANOMALIES
An anomaly is defined as a metal item with any one dimension equal to the 20 mm projectile, project’s approved Target of Interest (TOI or larger.
Historic anomaly averages, which may be contained within various references incorporated into this contract, do not reflect conditions at the project site. Contractor assumes the risk that the number of anomalies encountered at the project site may differ from historic averages.
1.4 PERSONNEL QUALIFICATIONS AND DUTIES
Personnel shall meet the minimum qualification standards set forth in DDESB TP 18 and the Guam Construction Support MRESS, including training and experience requirements. Personnel requirements and duties are defined in DDESB TP 18 and the Guam Construction Support MRESS.
The team composition and size shall be in accordance with EM 385-1-97.
Skill and composition of the team(s) will be appropriate to the task being performed; this is to include Quality Control and Safety.
The contractor shall provide all personnel qualifications and duties at least seven business days prior to commencing intrusive activities. When submitting the qualifications, include a signed letter to the Contracting
SECTION 01 57 19.03 20 Page 2
Officer certifying that key personnel meet the training and experience requirements for the position(s) held. The letter shall list, by name and position, all key personnel. The letter shall contain the following statement: “I certify that the personnel listed meet or exceed the contract requirements for the function they will perform.”
1.4.1 UNEXPLODED ORDNANCE SAFETY OFFICER (UXOSO)
The UXOSO shall be responsible for submitting and implementing the Site Health and Safety Plan (SHSP) and the Accident Prevention Plan (APP).
UXOSO must be on site,within the Exclusion Zone(s) or transiting between different teams, during anomaly investigation or any activity covered under the SHSP and APP.
The UXOSO may also perform duties of the UXOQCS. This position may be combined with the UXOQCS when there are fewer than fifteen (15) personnel on site. If this is done, it shall be designated in writing in the work plan.
In the work plan, designate a primary UXOSO. The contractor shall not deviate from the identified UXOSO without government notification and acceptance.
1.4.2 UXO QUALITY CONTROL SPECIALIST (UXOQCS)
The UXOQCS shall be responsible for implementing the approved Quality Control Plan. The UXOQCS may also perform duties of the UXOSO when there are fifteen (15) or fewer people on site. If this is done, it shall be designated in writing in the work plan. The UXOQCS shall not report to the SUXOS. The UXOQCS is responsible to ensure that the three phases of quality control (preparatory, initial, and follow-up) are properly implemented and shall inspect each definable feature of work by phase.
The UXOQCS is responsible for insuring proper implementation of the Geophysical System Verification process, installing an Instrument Verification Strip (IVS), and emplacing blind seeds. IVS shall be installed on a site-specific basis taking into account such factors such as;
proximity to powerlines, roads, electromagnetic emitting towers and soil conditions
Include space (s) as part of the the project to accomodate the placement of the IVS. The following idealized IVS ISO seed items will be buried ten feet apart in a horizontal orientation at the depths indiciated:
a. 1 each 20mm surrogate 5/8" - 11 x 2" fully threaded bolt buried at 6 inches
b. 1 each medium ISO (2-inch x 8-inch pipe nipple) buried at 13 inches
c. 1 each large ISO (4-inch x 12-inch pipe nipple) buried at 20 inches
In the work plan, designate a primary UXOQCS. The contractor shall not deviate from the identified UXOQCS without government notification and acceptance
1.4.3 SENIOR UXO SUPERVISOR (SUXOS)
The SUXOS is responsible to oversee all munitions response work. The SUXOS shall not operationally manage MEC/MPPEH efforts as part of another project while the UXO team is mobilized for this project. The SUXOS shall not perform any other role.
SECTION 01 57 19.03 20 Page 3
In the work plan, designate a primary SUXOS. The contractor shall not deviate from the identified SUXOS without government notification and acceptance.
Prior to initiating any work on site, meet with the Contracting Officer and installation Environmental Office to discuss the proposed Environmental Protection Plan (EPP) or equipment local requirement.
Develop a mutual understanding relative to the details of environmental protection, including measures for protecting natural and cultural resources, required reports, required permits, permit requirements (such as mitigation measures), and other measures to be taken.
1.4.4 UXO TECHNICIANS
UXO Technicians shall be provided by the contractor as needed based on site and project conditions. Training and experience shall be in accordance with DDESB TP 18 and Guam Construction Support MRESS and be commensurate with their assigned duties. A copy of the qualifications for all UXO Technicians shall be maintained on-site during all MEC/MPPEH-related work activities.
1.4.5 EXPLOSIVE SAFETY AWARENESS TRAINING
Explosive safety awareness training shall be performed in accordance with the requirements of DDESB TP-18 for all site workers/personnel working in areas identified by the JRM ESS designated as “likely” of encountering MEC regardless of whether they are engaged in intrusive activities or not.
Submit a Record of Training for all site workers to the Contracting Officer. The safety briefings shall be completed prior to site workers being allowed to enter the project site. Explosive safety awareness training must be renewed annually for all site workers.
1.5 WORK PLAN GENERAL REQUIREMENTS
Submit the Work Plan within 30 calendar days of Contract Award.
The Work Plan shall be project-specific and address any unusual or unique aspects of the project or activity for which it is written. The Work Plan shall interface with the Contractor’s overall safety, health, and quality control programs. The Government considers the Prime Contractor to be the “controlling authority” for all work site safety, health, and quality control implementation of the subcontractors. Contractors are responsible for informing their subcontractors of the safety and quality provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention and quality control responsibilities are being carried out. The contractor shall implement the three phases of quality control. The Work Plan shall be signed by the project superintendent,the project QC Manager, the project SSHO, the UXOSO, UXOQCS, and the SUXOS.
Once accepted by the Contracting Officer, the Work Plan and attachments will be enforced as part of the contract. Only when the Work Plan is accepted shall the contractor be permitted to begin remediation activities.
Contractor's failure to execute work in accordance with the approved Work Plan will be cause for non-compliance with the contract. Any costs or delays associated with full resolution will be the contractor's responsibility.
SECTION 01 57 19.03 20 Page 4
Once work begins, changes to the accepted Work Plan shall be made with the knowledge and concurrence of the Contracting Officer and Government MEC Quality Assurance Specialist (QA), project superintendent, QC Manager, SSHO,UXOSO, UXOQCS,and SUXOS.
Should imminent danger become evident, stop work in the area, secure the area,remove the exposure and control the hazard. In the event MEC/MPPEH is encountered, the contractor shall notify the Contracting Office and egional Operations Center immediately to begin response efforts. In the interim, take all necessary action to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public, and the environment. Written notification and initial MEC/MPPEH SPOT report within 24 hours (one business day).
1.6 INSTALLATION COMMANDING OFFICER (ICO) NOTIFICATION
MEC/MPPEH remediation work which impacts an installations operations (residents and tenant commands), traffic patterns or quality of life will require approval from the Installation Commanding Officer (ICO) prior to the start of remediation work. At a minimum the ICO will require 45 calendar days to review and approve the proposed plan that will cause disruptions to normal operations. Contractors shall submit ICO notifications to the assigned Contracting Officer for each contract. The submission shall contain, at a minimum, the following information;
location and details of the exclusion zone(s) (EZ), traffic control plan, and impacted buildings. Additionally,include; an aerial picture identifying the affected facilities and extents of EZ, identify the dates, times, and duration of anomaly investigation and identify the lead government and contractor point of contact for the on-site work.
1.7 GEOGRAPHIC INFORMATION SYSTEM (GIS) WORK AREA GRID
The contractor shall perform location recording and mapping using the WGS 1984 UTM Zone55 North coordinate system. The contractor shall determine the work area boundaries and use these coordinates and the GIS to determine the grid/sector distribution for the work area. Data must be provided in accordance with the GIS standards included as appendices to this specification section. Submit the GIS Work Area Grid to the Contracting Officer at least ten calendar days before commencing intrusive activities.
1.8 QC REPORT
Refer to specification section 01 45 00 QUALITY CONTROL for guidance on QC Reporting content.
1.8.1 DAILY QUALITY CONTROL (QC) REPORTS
The QC Report shall include the WGS 1984 UTM Zone55 North coordinate system used, elevation, description of grids/area included in the report, depth of clearance, number of anomalies investigated, weight in pounds of debris recovered, number of MEC found, number of MPPEH found, number of blind seeds placed, number of blind seeds recovered and IVS results. The report must indicate if the QC inspection passed/failed, schedule of requested Government MEC QA inspections and must be signed by the UXOQCS and the Prime Contractor QC Officer (if different). In map format, identify the area included in the QC Report relative to the entire project footprint, grids, anomalies Left in Place, MEC/MPPEH, and blind seeds. If MEC/MPPEH is found, include a tabular list of the grid, quantity, depth below the
SECTION 01 57 19.03 20 Page 5 original surface elevation, weight, type (MEC/MPPEH), disposition, mark/model, Military Grid Reference System (MGRS) coordinates, and any other applicable information. For blind seeds recovered, include a tabular list of the grid, MGRS coordinates, quantity,depth, size (S, M, L), description, and any other relevant information. For items Left in Place, include a tabular list of the grid, MGRS coordinates, and elevation. All locational information / map products shall be in the WGS 1984 UTM Zone 55N coordinate system. Each complete QC Report shall be in accordance with the format included as an appendix in this specification and submitted to the Government for review.
Upon government review of the QC Report and passing Government MEC QA inspection from the government, the footprint included within that QC Report may have construction activities proceed in the depicted area. It is anticipated that multiple QC Reports will be required and the number will vary based on project and site conditions. The contractor is responsible for maintaining oversight of intrusive activities to ensure that construction activities that disturb the earth stay within designated areas which have passed QC and Government MEC QA inspections.
1.8.2 DETECTION AND POSITIONING EQUIPMENT QC REPORTS
Detection and positioning equipment calibration shall be in accordance with Chapter 5.3.1 and 5.3.2 of the Guam Construction Support MRESS.
Periodic reports documenting Detection and positioning equipment calibration Quality Control shall be submitted to the Government in accordance with Chapter 5.3.1 of the Guam Construction Support MRESS. The QC Report shall include operational checks of equipment, compliance with the accepted DGM Work Plans, identify any non-compliant work and resulting re-work, and document the three phases of control.
The report must indicate if the QC inspection passed/failed, and must be signed by the UXOQCS and the Prime Contractor QC Officer (if different).
1.9 MEC/MPPEH SPOT REPORT
MEC/MPPEH Spot Reports are required in any situation where MEC/MPPEH is encountered and shall be in accordance with the format included as an appendix to this specification. In the event MEC/MPPEH is encountered, the contractor shall notify the Contracting Office and Regional Operations Center immediately to begin response efforts. An intermediate written report is due to the Contracting Officer, Government MEC QA and MEC Data Exchange by the next business day. A close-out report is due to the Contracting Officer, Government MEC QA and MEC Data Exchange 30 calendar days from the day when the MEC/MPPEH was encountered. The initial voice MEC/MMPPEH Spot report shall include a brief description of the positively identified MEC/MPPEH and its disposition. The intermediate written report shall include, but is not limited to, the description of the positively identified MEC/MPPEH item(s), photograph of item(s) (if possible next to an measuring device for reference), condition (e.g. fuzed, not fuzed, fired, not fired), depth from surface item(s) was found, map with MGRS coordinates indicating location of found MEC/MPPEH item(s) based on the WG1984 UTM Zone 55 North coordinate system, method used to isolate the hazard, description of work being performed when MEC/MPPEH item was encountered, name(s) of personnel who found the item and names of the certified personnel that made the MEC/MPPEH determination. The close-out report shall have all the same information as in the intermediate report and any additional subsequent information. If the MEC/MPPEH encountered
SECTION 01 57 19.03 20 Page 6 was not anticipated as part of intrusive investigation, MEC/ MPPEH close-out report shall also include a root cause analysis as to why a MEC/MPPEH item was encountered when it was not detected.
1.10 GIS DATA
GIS Data shall be submitted in accordance with the GIS standards included as appendices to this specification section.
1.11 AFTER ACTION REPORTS (AAR) GENERAL REQUIREMENTS
AARs shall be submitted to the Contracting Officer within 15 business days of the completion of clearance activities governed by this Specification.
AARs shall be provided in accordance with NOSSAINST 8020.15 (Series).
PART 2 PRODUCTS
2.1 DETECTION EQUIPMENT, METHODS AND STANDARDS
Detection equipment, methods and standards shall be in accordance with Chapter 5.1 of the Guam Construction Support MRESS. Detection equipment calibration shall be in accordance with Chapter 5.3.1 of the Guam Construction Support MRESS.
2.2 POSITIONING SYSTEMS, METHODS AND STANDARDS
Positioning systems, methods and standards shall be in accordance with Chapter 5.2 of the Guam Construction Support MRESS and the GIS standards included as appendices to this specification section. Positioning equipment calibration shall be in accordance with Chapter 5.3.2 of the Guam Construction Support MRESS.
2.3 STORAGE OF DATA COLLECTION
Initial data collection storage shall be a rugged Personal Digital Assistant (PDA), using pull-down menus, to include digital photos of recovered objects (e.g., MEC and MPPEH items are photographed specifically, while grid debris is photographed collectively by grid or lot of grids). As a back-up to PDA systems, a logbook shall also be kept.
Alternative storage methods may be authorized by the Contracting Officer.
PART 3 EXECUTION
3.1 COMMENCING OF INTRUSIVE ACTIVITIES
Submittals required by this specification shall not cause delay, limit, or halt the start or progression of the design work and shall be developed in parallel to the design work.
The Work Plan, Comprehensive Community Relations Plan, ICO notification,GIS Work Area Grid, qualifications for all personnel and Instrument Verification Strip IVS results shall be submitted by the contractor and accepted by the Government prior to the commencing of intrusive activities.
3.2 OCCUPANCY, POPULATION AND VEHICLE SURVEY
The contractor shall conduct the initial Occupancy, Population and Vehicle Survey between three months to two weeks prior to establishing EZs for
SECTION 01 57 19.03 20 Page 7 intrusive activities. Follow on survey counts shall be conducted on a monthly basis thereafter to estimate the vehicular and pedestrian traffic traversing the EZs. Provide the following as part of the Occupancy, Population and Vehicle Survey.
For vehicular and pedestrian traffic, the contractor shall conduct counts of vehicles and personnel travelling in and around the area of interest where EZs are planned. The counts shall be conducted during timeframes similar to the intended work periods by posting personnel on site to perform the counts. At a minimum, the counts of vehicular and pedestrian traffic shall be based on two-day counts of vehicles and personnel travelling in and around the planned EZs during high and low volume traffic periods. Unless recommended or approved otherwise, use 0700-0800 hours for the high volume traffic period and 1800-1900 for the low volume traffic period. Establish monthly estimated counts based on the average daily estimate of vehicular and pedestrian traffic.
For projects with EZs on Department of Defense (DOD) Property, the contractor shall request the occupancy and population for the area of interest from the Public Works Office. The contractor shall also request an access list of Government personnel authorized to remain within buildings inside EZs. Authorized Government personnel are subject to change.
3.3 WORK SCHEDULE FOR INTRUSIVE ACTIVITIES
Review the proposed work schedule and identify site specific issues and working hours of the EZ at the Post Award Kickoff Meeting.
The contractor shall schedule work appropriately to mitigate, to the greatest extent practicable, the impacts to base operations and the general public. Scheduling shall include phasing as well as night and weekend work as necessary.
Work outside of that approved in the Work Plan requires 3 day notice to ensure adequate QA oversight.
3.4 COMMUNITY OUTREACH
The contractor shall develop a thorough strategy for community outreach and engagement to ensure all entities impacted by EZs are effectively identified,notified, and informed of anticipated ESS activities and their impacts in a timely manner. Upon Government acceptance of the Contractor’s Comprehensive Community Relations Plan, the contractor shall coordinate regularly with the designated Government Project Team regarding the project-specific community engagement, outreach and public relations efforts.
The overall project community outreach and engagement strategy will be managed by the government. The contractor shall be responsible for drafting the development of documents to include, but not limited to, ICO notifications,written notices to property owners and businesses within EZs, design and implementation of traffic control, coordination with on base activities.
Written notice to property owners and businesses within the exclusion zone shall be produced and mailed by the contractor in advance of anomaly investigation that impacts those particular properties after approval by the Government. Written notice shall provide the name of the project and the contractor, give a general statement of work and explosives safety
SECTION 01 57 19.03 20 Page 8 concern,shall include the contractor’s website and the government contact number, and shall be approved by the government prior to issuance. The list of property owners will be provided by the contractor. The contractor shall maintain a complete list of the notices sent, detailing name and address of property,date of EZ impact, and date mailed. Should the contractor’s schedule of execution require that particular properties be impacted by EZ’s at separate times (i.e. in October and again in December), written notice shall be provided by the contractor for each occasion. Notice should also indicate the property owner’s responsibility to inform tenants, residents and/or employees as applicable.
The Contractor shall provide traffic control in the form of signs that shall be posted at least 7 calendar days prior to anomaly investigations to notify drivers of MEC/MPPEH investigative activities. These signs shall remain in place throughout the duration of the work activity.
All proposed Contractor written and oral communications must be approved by a designated Government representative prior to any and all communications with members of the public, stakeholders, etc.
3.5 ENFORCEMENT OF EXCLUSION ZONES ON DEPARTMENT OF DEFENSE (DOD) PROPERTY
The contractor shall be responsible for coordinating and issuing the notices of evacuation consistent with Section 3.4.
The contractor shall be responsible for providing reasonable levels of verification and enforcement of identified exclusion zones during ESS activities. Reasonable verification is defined as observations of the exclusion zone prior to commencing intrusive investigations.
Should unauthorized personnel be observed in the exclusion zone, the contractor shall verbally inform them of the scheduled work and request that they leave the EZ. Government MEC QA providing oversight of projects or enforcement of requirements are considered authorized personnel.
Verbal contact is intended to remind the impacted occupants of the evacuation requirements and the time and duration when intrusive activities will commence.
Reasonable enforcement is defined as verbal notification and request to evacuate to any unauthorized individual observed inside the EZ limits during anomaly investigation. The contractor is required to stop anomaly investigation while unauthorized personnel are within EZs. Should unauthorized personnel remain within the EZ after they have been verbally informed of the scheduled work and request to vacate, the contractor shall immediately notify the government point of contact in order of, Construction Management Engineer, Contracting Officer, Supervisory General Engineer, or FEAD/ROICC until positive contact with one or more is made.
The contractor has no authority to detain or escort people out of the EZ.
EZ control shall be implemented by using entry control points (ECPs) to block access to the EZ during intrusive operations. ECPs along roads and sidewalks shall be sufficiently barricaded (e.g., road barriers, security/construction fencing) to block unauthorized access to the site during MEC operations. Signs shall be posted at each ECP with the point of contact information for the MEC Contractor’s Senior UXO Supervisor (SUXOS) and UXOSO. If a roadway or waterway located within the EZ cannot be blocked, spotters shall be used to alert the UXOSO and SUXOS to cease MEC operations when non-essential personnel enter into the EZ. Operations
SECTION 01 57 19.03 20 Page 9 shall not be allowed to resume until nonessential personnel leave the EZ.
All personnel working within the EZ shall stop work in the event that an unauthorized individual encroaches into the EZ.
Upon completion of the anomaly investigation activities in the established EZ, the contractor shall notify the Government and evacuees as soon as possible that they may return. Notification may be made by phone, text, social media, or other appropriate notification.
3.6 SOIL EXCAVATION AND REMOVAL
Soil excavation and removal shall be in accordance with the Guam Construction Support MRESS and NAVSEA OP 5.
3.7 IMPORTED SOILS
The Contractor shall ensure that all imported soils are free of MEC/UXO/MPPEH items or metallic materials.
The Contractor shall afford Government representatives an opportunity to visit and view the source for any imported soils at the Government’s request.
3.8 BEDROCK DETERMINATIONS FOR UNLIKELY CONSIDERATION
Determinations of a solid rock formation shall be made by a licensed Professional Geologist or Civil Engineer with a Professional Engineer (PE) license. Before the licensed professional makes a determination, the contractor shall fully expose the entire top layer of the solid rock formation over which the determination is being made. The area shall be cleared of all anomalies using full clearance techniques in accordance with the Guam Construction Support MRESS and NAVSEA OP 5. The area shall be physically identifiable at the site with the use of construction markers based on the determined Global Position System (GPS) coordinates.
Determinations shall be made in writing and include the following:
certifying stamp from the licensed individual making the determination;
three dimensional GPS coordinates (grid and depth) outlining the area for which the determination is being made; methods and criteria used to make the determination; and photographs of the area showing the solid rock formation. A bedrock determination shall only be valid for the area defined. Anywhere outside of the area defined in the determination shall require a separate determination prior to being managed as unlikely.
Upon written acceptance by the Contracting Officer (KO), the defined area shall be considered low likelihood for encountering MEC/MPPEH. A written designation of low likelihood must be issued from the KO to the contractor that acknowledges the planned area to proceed as bedrock and then directs the contractor to utilize On-Call Construction Support until all excavation is complete.
In the event of a MEC/MPPEH discovery in an area previously classified as low likelihood due to a solid rock formation determination, the provisions of Guam Construction Support MRESS with respect to a MEC/MPPEH discovery in an unlikely area shall immediately apply.
SECTION 01 57 19.03 20 Page 10
3.9 IN SITU NATIVE STRATIFIED SOIL DETERMINATIONS FOR LOW LIKELIHOOD
CONSIDERATION
Determinations of in situ native stratified soil horizons shall be made by a licensed Professional Geologist, Civil Engineer with a Professional Engineer (PE) license, or cultural resource subject matter expert (e.g.
Archiologist) with Secretary of Interior qualifications. Before the competent authority makes a determination, the contractor shall fully expose the top layer of the entire area over which determination is being made, plus (6) additional inches. This area shall be scanned and determined to be anomaly free in accordance with the relevant ESS or ESS annex (e.g., MEC Contractor with MEC QA). If anomalies are detected, the anomalies must be investigated and removed, and the existence of the discovered anomaly during the determination process shall be documented.
The area shall be physically identifiable at the site with the use of construction markers based on the determined Global Position System (GPS) coordinates.
Determinations shall be made in writing and include the following:
certifying stamp from the competent authority making the determination;
three dimensional GPS coordinates (grid and depth) outlining the area for which the determination is being made; methods and criteria used to make the determination; and photographs of the area that is being determined as in situ native stratified soil horizon. An in situ native stratified soil horizons determination shall only be valid for the area defined. Anywhere outside of the area defined in the determination shall require a separate determination prior to being managed as low likelihood.
Upon written acceptance by the Contracting Officer (KO), the defined area shall be considered low likelihood for encountering MEC/MPPEH. A written designation of low likelihood must be issued from the KO to the contractor that acknowledges the planned area to proceed in situ native stratified soil formation and then directs the contractor to utilize On-Call Construction Support until all excavation is complete
In the event of a MEC/MPPEH discovery in an area previously classified as low likelihood due to an in in situ native stratified soil horizons determination, work shall be stopped and the Project Management Team will notify the NAVFAC Marianas MEC Program Manager and the JRM Explosive Safety Office and request guidance on how to proceed.
3.10 REQUIREMENTS WHEN MEC/MPPEH IS ENCOUNTERED
Stop all work immediately if any material or object believed to be MEC/MPPEH is encountered and execute first response protocols immediately.
Notify the UXO Technician III, UXOSO or SUXOS for a determination of MEC/MPPEH. Notify the Contracting Office and Regional Operations Center immediately to begin response efforts. Provide a written notification and initial Spot Report within 24 hours (one business day). Follow the safety reporting procedures of the Work Plan.
The Contractor shall not blow-in-place or counter-charge any MEC/MPPEH encountered.
Both the SUXOS and UXOSO shall make a joint decision on whether the item is safe to move.
If MEC/MPPEH encountered is determined by the SUXOS and UXOSO to be safe to move and does not pose a threat to human health or the environment, it may
SECTION 01 57 19.03 20 Page 11 be moved and temporarily stored on site in a secure location for the appropriate Government response team for further disposition. If MEC/MPPEH is not retrieved by the Government by the end of the same business day, the contractor shall provide services to guard the MEC/MPPEH, overnight if necessary, until retrieved.
If MEC/MPPEH encountered is determined by the SUXOS and UXOSO to be unsafe to move, poses a threat to human health and the environment or represents an imminent and substantial endangerment to human health and the environment, execute first response protocols immediately. The Contractor shall also coordinate as soon as possible with the appropriate Government Representative so that the appropriate EOD response team is dispatched by the Government for further disposition.
MEC and MPPEH storage, transportation and disposal will be accomplished by military EOD IAW Guam Construction Support MRESS. The Contractor shall notify the Government (Naval Base Guam Command Duty Officer/Andersen Air Force Base Command Post) until positive contact is made to dispatch EOD.
Immediately following this, the contractor shall notify the Government’s point of contact in the following order: Government MEC QA, Construction Manager Engineer, Contracting Officer, Supervisory General Engineer, FEAD/ROICC until positive contact with one or more is made.
Document transfer of MEC/MPPEH to EOD via the DD form 1348-1A.
3.10.1 REQUIREMENTS WHEN MEC/MPPEH IS ENCOUNTERED GREATER THAN THE LARGEST
APPROVED PRIMARY AND CONTINGENCY
If while executing a munitions response, the contractor identifies a MEC item which has a greater maximum fragment distance-horizontal (MFD-H), hazardous fragment distance (HFD), or K328 distance than the approved MGFD; the contractor shall cease all intrusive activities and notify the Contracting Officer. Intrusive work may recommence after putting in place either increased protection required by the item found or the contingency MGFD. If either represents a changed contract condition, the contractor shall immediately submit written notification to the Contracting Officer, include rationale and supporting documentation for the increase, and offer the most cost effective recommendation(s) to maintain the construction schedule. Contractors are advised against providing cost proposals without guidance from the Contracting Officer.
3.11 QUALITY CONTROL
The UXOQCS shall be responsible for Quality Control in accordance with section 7.1 of the Guam Construction Support MRESS.
3.12 GOVERNMENT MEC QUALITY ASSURANCE SPECIALIST (QA)
The Contractor shall afford the Government an opportunity to complete the required Government MEC QA inspection prior to the area or soil being used for any construction activity. The Contractor shall identify MEC QC intrusive and soil processing activities on the project schedule and allow for two full business days to complete the required Government MEC QA inspection. For unplanned MEC QC activities not identified on the project schedule, the Contractor shall notify the Contracting Officer two full business days in advance of intrusive and/or soil processing activities and allow an opportunity for Government MEC QA inspection.
All anomalies recovered that are not MEC/MPPEH shall be collected and
SECTION 01 57 19.03 20 Page 12 remain on-site for up to 10 business days or until the Government MEC QA has had an opportunity to perform a quality assurance check to ensure there is no MEC/MPPEH or MD/MDAS comingled with what would otherwise be considered scrap metal and/or debris.
-- End of Section --
SECTION 01 57 19.03 20 Page 13
Appendix A: MEC GIS Requirements
01 57 19.03 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS, dated April 14, 2025 thanna Text Box 1737021 thanna thanna thanna thanna
Appendix A: NAVFAC Standards for Geographic Information System (GIS)
1. Overview:
The GeoReadiness Center (GRC) is the single, authoritative source and distribution point for all geospatial shore installation data within the region. The GRC houses the most current geospatial information for the entire region and provides access to the comprehensive data set and analysis tools to Regional and DOD decision makers/managers, sponsored contractors, and other sponsored individuals via a secure government Internet site.
2. Basic Deliverable Requirements:
a. Submittals, Government Review and Acceptance:
i. All data used and developed under contract is intellectual property of the U.S. Government, and shall be turned over to the U.S. Navy upon completion of this amendment.
ii. All submittals shall be reviewed for accuracy, structure and completeness by a GeoReadiness representative before acceptance. Contractors shall submit data and documentation samples at 25% and 75% project completion to avoid the rejection of final deliverables.
iii. All source code (e.g. Python scripts, html files, etc.) and map files (ESRI ArcGIS .mpk) shall be provided to the government.
iv. Failure to adhere to any of the stated delivery specifications could result in rejection of deliverables and nonpayment.
b. GIS Data Format: NAVFAC’s GIS data is an ERSI Geodatabase format. Check for the Navy approved current version of ArcGIS.
i. All GIS/geospatial projects (i.e., MPK) shall be delivered containing all related source files in a specific project file, including extension, graphics, photos, CAD, source code (non-encrypted, Visual Basic) based on version of
ArcGIS Desktop specified for the task order. Submittal format shall be determined by the COR.
ii. Spatial Data (GIS Map Themes): Spatial data shall be delivered as an ArcGIS file geodatabase. File geodatabases are relational databases that contain geographic information. File geodatabases contain feature classes and tables. The names of these geodatabases should reflect the location of the geographic information it contains at the appropriate level of detail (region, special area, activity). The general format of personal geodatabase names is as follows:
Location yyyymmdd.gdb
Appendix B: NAVFAC Standards for Geographic Information System (GIS)
01 57 19.03 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS, dated April 14, 2025 thanna
iii. Location = Location of the geographic information, defined to the appropriate level of detail. Names begin at the regional level, using the 2-digit country code from iNFADS
(e.g. HI=Hawaii, GQ=Guam, JA=Japan, etc.) and may narrow into an area of interest within the region (e.g. Pearl
Harbor, Yokosuka, Apra Harbor, etc.). The location can be further narrowed down to the activity level where the geodatabase can be identified by the activity’s UIC
(N68032, N58003, etc.)
iv. yyyymmdd= Date that the geodatabase was created or amended, as expressed in year (yyyy), month (mm), and date
(dd)
C. Data Retention: all proprietary data (electronic and paper formats) must be removed from contractor equipment and possession and returned to the government at the end of the period of performance and before the final invoice is approved.
d. Data Structure:
IV. Unless specifically directed otherwise, all data shall be structured according to the current version of the Spatial Data
Standards (SDSFIE) in use by NAVFAC. This is the current version of the Navy Data Model (NDM). Information on the SDSFIE data model can be found at: https://sdsfie.org, and a copy of the current data model implementation shall be provided to the contractor. The data collection guide can be accessed at:
http://datacollectionadvisor.com/
i. If new data is being created and the corresponding SDSFIE data structure exists, the government shall provide unpopulated layers to the contractor structured per current
NAVFAC standards.
ii. If new data is being created and the corresponding data structure does NOT yet exist, the contractor shall provide the GRC with a data dictionary identifying all of the
SDSFIE Entity Types, attributes, and/or domain values associated with the new feature(s), the geographic area(s) covered by the data and Spatial extent information prior to the creation/editing of GIS data. Acceptable formats: MS
Excel or MS Word. (Adobe PDF is not an acceptable format.
New non-SDS compliant attributes (meeting SDSFIE criteria) will require precise schema definitions.
e. Government Source Data: The contractor will be provided access to any GIS data required for the project via a government computer, which will require Contractor Common Access Card (CAC).
Government GIS repository is in an ESRI format. All data shall be returned in this format and structure unless the government specifies otherwise. A completed NAVFAC GIS Data Release form is required prior to data being released to the Contractor if editing is required to be completed on Contractor equipment.
thanna
f. Attribute Population:
i. The contractor shall consult with the COR before populating attribute tables to ensure the results match the current
GeoReadiness interpretation of the SDSFIE.
ii. The contractor shall identify the classification, type, location, ID number, and any other necessary attributes
(specified by the Government) for all new/updated/edited features.
iii. For new field collected data, attribution must include the date collected in the following format.
1. Name: Date Description: Date that the feature was edited from its original or previous value.
Data Type: Date
Default Value: null
3. Data Integrity:
a. Data accuracy standards for all deliverables will be in accordance with those set forth in the section entitled ’Data
Collection Procedures’. All deliverables should include an accuracy report in the metadata.
b. The contractor shall employ appropriate QA/QC standards to ensure that data is topologically correct, accurate and complete (to include):
c. No erroneous overshoots, undershoots, dangles or intersections in the line work
d. Point and line features will be snapped together where appropriate to support networks. For example, do not break linear features for labeling or other aesthetic purposes.
e. Lines should be continuous and point features should be digitized as points. For example, point features, such as manholes, should not be drawn using only a circle (polygon) to represent its location. Preferably, use an attribute block symbol that has an insertion point in the center of the manhole.
f. No sliver polygons
g. Digital representation of the common boundaries for all graphic features must be coincident, regardless of feature layer
h. Geometric network connectivity must be maintained for utility networks.
Note: This excludes field collected “walked” survey transect data
A summary of the methods used to correct inconsistencies and any remaining errors by case should be included in the metadata under the ’Logical
Consistency Report’ and ’Completeness Report’ sections.
thanna
4. CAD Format Deliverables:
a. CAD drawings may be accepted as GIS deliverables, if COR approves.
b. All files must be accurately georeferenced and adhere to the requirements regarding the coordinate system, metadata, and the specified data Quality Control and Quality Assurance requirements.
c. CAD file conversions must have a unique identifier and a related table to link critical attribution normally found in GIS data.
I.E: Pipe size, capacity, locational accuracy, etc.
d. CAD deliverables shall include AutoCAD (DWG) files. CAD symbols placed within the design/drawing file shall adhere to the A/E/C
CAD Standard. CAD symbol libraries can be found on the Tri-
Service CAD/BIM Technology Center website.
https://cadbim.usace.army.mil/CAD https://www.wbdg.org/ffc/army-coe/cad-bim-technology-center or https://cadbimcenter.erdc.dren.mil/default.aspx?p=a&t=1&i=7.
5. Coordinate System:
All geospatial data, unless specified otherwise, shall be in the
Geographic
Coordinate System: GCS_WGS_1984, Datum: D_WGS_1984.
6. Metadata:
a. Feature Level Metadata: Feature-level (record level) attribute metadata is required to be populated for each GIS feature/record, per the current SDSFIE version.
Attributes for the current version are listed in APPENDIX B
b. Layer Level Metadata: Layer level metadata is required for all deliverables, structured according to the FGDC Content Standard for Digital Geospatial Data (CSDGM). Details on the standard can be found at http://www.fgdc.gov/metadata/geospatial—metadata— standards.
7. Quality Control and Quality Assurance:
The contractor shall take all appropriate and needed QA/QC measures to ensure data is complete, topologically correct, accurate, structured correctly, and formatted correctly per the scope of work and complete (to include):
a. **All data shall be visually inspected before submittal to the government.**
b. The numbers of records for all joined tables shall match, or the specific unmatched records shall be identified and explained to the satisfaction of the government.
c. All required attributes (per NDM current version shall be populated).
d. All domain constraints shall be adhered to, unless approved by the government, prior to submittal.
e. No erroneous overshoots, undershoots, dangles or intersections in the line work.
Amendment No. 0008 01 57 19.03 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS, dated April 14, 2025 thanna
f. All area type features shall be closed polygons.
g. Line features shall be snapped together where appropriate to support networks. For example, do not break linear features for labeling or other aesthetic purposes.
h. Lines shall be continuous and point features shall be digitized as points. For example, point features, such as manholes, shall not be drawn using only a circle (polygon) to represent its location.
i. No sliver polygons
j. Digital representation of the common boundaries for all graphic features must be coincident, regardless of feature layer
k. Geometric network connectivity shall be maintained for utility networks, where specified by the scope of work.
8. Field Collection:
a. Where field data collection is required, the contractor shall utilize conventional and other methods, such as a total station, or Global Positioning System (GPS) in accordance with the applicable Geospatial Positioning Accuracy Standards published by the Federal Geographic Data Committee (FGDC).
b. At a minimum, the contractor shall provide professional grade GPS collection at an accuracy level of +/- lm and shall use differential correction to target accuracies of +/- .5 m.
c. Where appropriate (as stipulated in the contract or as otherwise determined by the Government), the contractor shall use survey grade GPS, at an accuracy level of +/- 3 cm. Global Positioning
System (GPS) data collection activities will be based on a post-processed environment using an accurately sighted base station.
Base station files for post processing acquired locally (off-site
CORS Continuous Operating Reference Station) will be verified for accuracy.
d. GPS data on the location of utility lines and other features shall be captured at a minimum at the beginning, end, and at each turn or bend in the line and processed as a line feature type.
GPS data on the location of utility points and other features shall be captured at the centroid of the feature unless signal obstruction or access prohibits; otherwise points will be captured at a uniform distance and direction from the centroid and the offset captured in the metadata for that feature. Data on polygon features shall be collected at every vertex of the feature and processed as a polygon.
e. All survey-grade data collected shall be provided to the
Government in a digital format with an attached Survey Report identifying survey method, equipment list, calibration documentation, survey layout, description of control points, control diagrams, quality control report and field survey data.
thanna
f. A digital Survey Control Database (consisting of a survey marker database and a survey traverse database) will be produced for all survey control points established under this contract, including the horizontal and vertical order and coordinate location of each point.
g. Digitizing/Conversion: Where Digitizing/Conversion is stipulated in the contract, the contractor shall digitize/convert features from designated sources (including remotely sensed data, hardcopy scans and vector data) to support various GIS applications.
Digitizing/conversion routines will insure that 90 percent of all features will measure within 0.01 inches when reproduced at the scale of original imagery or data source
9. Photography.
a. Photography on-base must be approved in advance of visiting the base, the Contractor shall identify the personnel designated as photographers for this contract and shall identify the proposed areas/facilities to be photographed and provide installation (via
COR) with any required photographic equipment information.
b. All photographs to be delivered/used in the final report must be geotagged with the UTM of the picture location
Amendment No. 0008 01 57 19.03 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS, dated April 14, 2025 thanna
APPENDIX C: MEC SPOT Report Template
01 57 19.03 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS, dated April 14, 2025 thanna thanna
Project Name: See Maps and
Drawings below
LOT by Station: Digs LF /CY Seed Number(s) QC/QA Inspection Report #:
Print Name UXOQCS Signature
Totals
MEC 0
Print Name: QA Inspector Signature
Date Started:
MDAS lbs.
Cultural Debris lbs.
Date QA inspection:
Utilities Found: LEGENDS
W Water Line
P Power Line
UNK Unknown / Other
S Sewer /Drain Pipe
GR Grounding Rod
CL COMMUNICATION Line
Appendix D: QCQA Inspection Report Template
01 57 19.03 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS, dated April 14, 2025 thanna
APPENDIX B: Specifications for GIS Layers and Attributes
The contractor shall consult with the government points of contact to ensure data is placed into the appropriate layer. Please see http://datacollectionadvisor.com/ for full guidance
This section lists:
• SDSFIE Required Global Attributes: These must be populated for each record in all layers
• SDSFIE…