25R1303 P614 Note 10.pdf

PDF 372 KB Posted

Attached to
FY24 MCON P-614 JOINT CONSOLIDATED COMMUNICATIONS CENTER, US JOINT REGION MARIANAS, ANDERSEN, GUAM
Solicitation number
N6274225R1303
Issued by

About this file

This document is a Pre-Proposal Questions & Answers (Notice No. 10) for RFP N62742-25-R-1303, dated 28 April 2025, related to the FY24 MCON Project P-614 Joint Consolidated Communications Center at Joint Region Marianas Andersen, Guam. The document provides responses to several technical and project-specific questions from potential contractors, addressing topics such as utility line demolition, manhole demolition, and permitting duration.

Key details include a response to a question about the MEC Annex, which will be provided in a forthcoming amendment, and clarification that existing utility lines being demolished are not expected to contain asbestos. The Government has allocated six months for permitting, specifically for GEPA permitting required for clearing and grubbing work on site. The document emphasizes that these questions and answers are for information only and do not change the original RFP unless amended in writing on a Standard Form 30.

View the file

Other files

File Type Posted
25R1303 P614 Note25.pdf PDF
01_25R1303_AMD0017.pdf PDF
02_25R1303_ AMD 0017 Drawings.pdf PDF
25R1303 P614 Note22.pdf PDF
03_25R1303_01 91 19_AMD0015.pdf PDF
01_25R1303_AMD0015.pdf PDF
04_25R1303_08 91 00_AMD0015.pdf PDF
02_25R1303_01 91 00.15_AMD0015.pdf PDF
25R1303 P614 Note 21.pdf PDF
02_25R1303_09 69 13_AMD0013.pdf PDF
03_25R1303_26 33 53_AMD0013.pdf PDF
01_25R1303_AMD0013.pdf PDF
04_25R1303_AMD0013 DRAWINGS.pdf PDF
25R1303 P614 Note 18.pdf PDF
25R1303 P614 Note16.pdf PDF
02_25R1303_05 50 13_AMD0011.pdf PDF
03_25R1303_05 51 33_AMD0011.pdf PDF
06_25R1303_DRAWINGS_AMD0011.pdf PDF
04_25R1303_09 29 00_AMD0011.pdf PDF
05_25R1303_09 84 20_AMD0011.pdf PDF
01_25R1303_AMD0011.pdf PDF
25R1303 P614 Note14.pdf PDF
25R1303 P614 Note12.pdf PDF
05_25R1303_09 30 10_Amd0008.pdf PDF
03_25R1303_AMD 0010 DRAWINGS.pdf PDF
04_25R1303_AMD 0009_1737021_DRAWINGS.pdf PDF
06_25R1303_10 11 00_Amd0008.pdf PDF
12_25R1303_26 24 13_Amd0008.pdf PDF
03_25R1303_07 60 00_Amd0008.pdf PDF
02_25R1303_01 57 19.03 20_Amd0008.pdf PDF
11_25R1303_26 20 00_Amd0008.pdf PDF
09_25R1303_10 71 13.13_Amd0008.pdf PDF
08_25R1303_10 51 13_Amd0008.pdf PDF
01_25R1303_AMD0010.pdf PDF
02_25R1303_02 61 13_AMD0009.pdf PDF
07_25R1303_10 28 13_Amd0008.pdf PDF
10_25R1303_26 11 16_Amd0008.pdf PDF
01_25R1303_Amd0008.pdf PDF
01_25R1303_AMD0009.pdf PDF
03_25R1303_32 12 13_AMD0009.pdf PDF
04_25R1303_08 41 19_Amd0008.pdf PDF
13_25R1303_AMD 0008_1737021_DRAWINGS.pdf PDF
02_25R1303_01 57 19_AMD0010.pdf PDF
25R1303 P614 Note 8.pdf PDF
01_25R1303_Amd0006.pdf PDF
02_Signed AMD 0006_1737021_ARCH.pdf PDF
25R1303 P614 Note 6.pdf PDF
04_SIGNED Amd0005_1737021_ARCH.pdf PDF
01_25R1303 _Amd0005.pdf PDF
03_10 44 16_Amd0005.pdf PDF
Show 40 more

Latest 50 of 89 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND PACIFIC

258 MAKALAPA DR STE 100

PEARL HARBOR HI 96860-3134

RFP N62742-25-R-1303

Notice No. 10

28 April 2025

PRE-PROPOSAL QUESTIONS & ANSWERS

RFP N62742-25-R-1303

FY24 MCON PROJECT P-614 JOINT CONSOLIDATED COMMUNICATIONS

CENTER JOINT REGION MARIANAS ANDERSEN, GUAM

NOTE: The following questions and answers are provided for INFORMATION ONLY. The RFP remains unchanged unless it is amended in writing on a Standard Form 30.

RESPONSES DEFERRED FROM NOTICE NO. 8 DATED 14 April 2025

43. Reference: Non-CUI Spec Section 01 57 19.03 20: MEC Annex; Has a MEC Annex been prepared for this project site? If so, please provide.

ANSWER: MEC Annex has been prepared, and will be provided in a forthcoming amendment.

44. Reference: Non-CUI Dwgs CD102A, CD103A, CD104A; Existing Utility Lines to be Demolished; Dwgs CD102A, CD103A, and CD104A show existing toned underground lines to be demolished. We have the following questions:

1. For the basis of the bid, what material and diameter of the line shall be considered?

2. Are any of these lines to be considered as containing asbestos? If so, please provide pipe size and lineal feet to consider.

ANSWER: 1. Assume utility lines are buried with depth to top of duct bank as noted, and dimensions of 2-feet wide x 1-foot thick.

2. Lines being demolished are currently not expected to contain asbestos.

46. Reference: Non-CUI Dwg ET101A; MH Global Hawk MH480; On drawing ET101A, Global Hawk Manhole 480 has a call out for Sheet Note “3” for demolition of duct bank and cabling. Should the callout be for note “4” for core drill existing manhole? Or does the manhole get demolished? Please advise.

ANSWER: Global Hawk Manhole 480 must be demolished.

49. Reference: Non-CUI; Secure Storage Area;

1. Please provide location and dimensions for the Secure Storage Area.

DEPARTMENT OF THE NAVY

NAVAL FACILITIES ENGINEERING SYSTEMS COMMAND PACIFIC

258 MAKALAPA DR STE 100

PEARL HARBOR HI 96860-3134

RFP N62742-25-R-1303

2. Please Prime Contractor requirements for the secure storage area: Aggregates, Fencing & Gates, Utilities (Lighting, CCTV, etc.)

3. Please provide any construction schedule restraints from the time the secure storage area is constructed to when SUS or general construction may begin.

ANSWER:

1. Not required. Refer to CSP for CUI requirements para 6.8.c and 6.9.

2. N/A

3. N/A

72. With regards to the Government’s Answer to Question 4 in Notice 1, please provide the duration that the Government is allocating in the Period of Performance for “permitting”, and specifically, for GEPA permitting that is required to perform any clearing/grubbing work on site.

ANSWER: A duration of (6) months has been allocated by the Government.

File details come from the government source that posted it. Updated .