02_25R1303_01 91 00.15_AMD0015.pdf
PDF 80 KB Posted
- Attached to
- FY24 MCON P-614 JOINT CONSOLIDATED COMMUNICATIONS CENTER, US JOINT REGION MARIANAS, ANDERSEN, GUAM
- Solicitation number
- N6274225R1303
About this file
This document is a Section 01 91 00.15 specification for Building Commissioning for the FY24 MCON P-614 Joint Consolidated Communications Center project at Andersen Air Force Base, Joint Region Marianas. The specification outlines a systematic, quality-focused process for verifying and documenting that all commissioned systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet project requirements, with the goal of reducing cost and performance risks.
The specification details comprehensive requirements for the commissioning process, including the roles and responsibilities of the Commissioning Provider and Commissioning Team, communication protocols, systems to be commissioned (such as HVAC, lighting, plumbing, and building control systems), and key deliverables. Critical activities include design reviews, construction submittal reviews, commissioning site visits, inspections, testing procedures, training plans, and reporting. The document specifies detailed requirements for commissioning specialists, their qualifications, and the standards they must follow, with an emphasis on ensuring systems meet contract document requirements through rigorous testing and documentation.
View the file
Other files
Show 40 more
Latest 50 of 89 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY24 MCON P-614 JOINT CONSOLIDATED COMMUNICATIONS CENTER 1737021
JOINT REGION MARIANAS, ANDERSEN AIR FORCE BASE
SECTION 01 91 00.15
BUILDING COMMISSIONING
05/23, CHG 3: 08/24
PART 1 GENERAL
Building Commissioning is a systematic, quality-focused process for enhancing the delivery of a project that focuses on verifying and documenting that all of the commissioned systems and assemblies are planned, designed, installed, tested, operated, and maintained to meet the project requirements. The purpose is to reduce the cost and performance risks associated with delivering facilities projects, and to increase value to owners, occupants, and users.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 90.1 - IP (2019) Energy Standard for Buildings Except Low-Rise Residential Buildings
ASHRAE 202 (2024) Commissioning Process for Buildings and Systems
ASSOCIATED AIR BALANCE COUNCIL (AABC)
ACG Commissioning Guideline (2005) Commissioning Guideline
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB S1110 (2019) Whole Building Technical Commissioning of New Construction; 2nd Edition
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
ANSI/SMACNA 014 (2013) HVAC Systems Commissioning Manual, 2nd Edition
1.2 DEFINITIONS
Commissioning Process (Cx) - a quality-focused process for enhancing the delivery of a project. Refer to ASHRAE 202 for a comprehensive description of the commissioning process.
Commissioning Provider (CxC) - The entity who leads, plans, and coordinates the Commissioning Team. The terms Commissioning Provider, Commissioning Firm, Lead Commissioning Specialist, Commissioning Specialist, and Commissioning Authority (CA or CxA) when used by sustainable Third Party Certification (TPC) programs, are interchangeable.
SECTION 01 91 00.15 Page 1
Amendment 0015 01 91 00.15 BUILDING COMMISSIONING, dated May 15, 2025
Commissioning Authority – The Government retains the authority for oversight and assurance of the entire commissioning process, and final approval of all commissioning deliverables.
Government Acceptance Testing Representatives - Government Acceptance Testing Representatives perform the inherently Governmental function of technical oversight and quality assurance for critical systems, and is distinctly separate from the commissioning process. Government Acceptance Testing Representatives witness final testing of critical systems and report systems' acceptance to the COR. Submittals to be surveilled and approved by Government Acceptance Testing Representatives are identified in Section 01 33 00 SUBMITTAL PROCEDURES . Testing required to be witnessed by Government Acceptance Testing Representatives are identified in system level sections.
1.3 COMMUNICATION WITH THE GOVERNMENT
The Lead Commissioning Specialist (CxC) must submit all plans, schedules, reports, and documentation directly to the Contracting Officer's Representative concurrent with submission to the Quality Control (QC) Manager.
The Lead Commissioning Specialist must have direct communication with the Contracting Officer's Representative regarding all elements of the commissioning process; however, the Government has no direct contract authority with the Lead Commissioning Specialist.
1.4 COMMUNICATION WITH GOVERNMENT ACCEPTANCE TESTING REPRESENTATIVES
The QC Manager must communicate directly with the Government Acceptance Testing Representatives and Contracting Officer's Representative regarding Government acceptance testing activities. Inform the Contracting Officer's Representative when systems are ready for testing to be witnessed by Government Acceptance Testing Representatives, and allow access to the construction site and system(s) to be tested.
1.5 SYSTEMS TO BE COMMISSIONED
Coordinate commissioning and quality control activities for the following systems, equipment, and associated controls. System-specific requirements are located in the associated specification sections. Commission the following systems, equipment, and associated controls in accordance with this section and the inspection, testing, and quality control requirements of their respective sections:
Heating, ventilating, air-conditioning, and refrigeration systems (mechanical and passive) and associated controls (HVAC)
Lighting systems: interior and exterior, automatic and manual daylighting controls, occupancy sensing devices, automatic shut-off controls, time switching, and other lighting control devices, and dimming systems
Service hot-water systems and controls
Plumbing Systems
Building Control Systems
SECTION 01 91 00.15 Page 2
Utility Monitoring and Control Systems
Metering and sub-metering
Automatic Receptacle Control
Building Envelope in accordance with Section 01 91 19 BUILDING
ENCLOSURE COMMISSIONING.
Power Distribution
1.6 RELATED SECTIONS
Refer to the following technical sections for additional commissioning requirements for respective systems:
Section 01 91 19 BUILDING ENCLOSURE COMMISSIONING
Section 23 08 00 COMMISSIONING OF MECHANICAL AND PLUMBING SYSTEMS
Section 26 08 00 APPARATUS INSPECTION AND TESTING
1.7 COMMISSIONING TEAM
The Commissioning team will include, but is not limited to the following team members.
Ensure all Construction Activities for systems to be commissioned are coordinated with the appropriate commissioning team members.
a. Commissioning Provider
b. QC Manager
c. Sub-Contractor Representatives for each trade responsible for construction/installation of systems to be commissioned
d. Construction Manager (CM)
e. Technical Commissioning Specialists for each system to be commissioned
f. TAB Representative
g. Equipment manufacturer representatives
h. Government Contracting Officer
i. Government Representatives
j. Installation Maintenance Representative
k. Facility End User
l. Designer of Record (DOR)
m. Government Acceptance Testing Representatives
SECTION 01 91 00.15 Page 3
1.8 PROJECT SCHEDULE
Include the following tasks in the project schedule required by Section 01 32 17.00 20 COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS) and in the construction phase commissioning plan . Ensure sufficient time is scheduled to complete each item. The order of items listed below is not intended to imply a specified sequence:
a. Submission and approval of the Commissioning Firm Qualifications
b. Submission and approval of the Design Review Report
c. Submission and approval of the Interim and Final Construction Phase Commissioning Plans
d. Commissioning Kickoff Meeting
e. Regular Commissioning Coordination Meetings
f. Installation of permanent utilities (gas, water, electric, steam)
g. Building Enclosure Construction
h. Submission and approval of the Completed Building Enclosure Inspection Checklists
i. Manufacturer's Equipment Start-Up for each of the systems to be commissioned
j. Submission and approval of the Completed Commissioning Observation Checklists
k. Submission and approval of Certificate of Readiness for each system to be commissioned
l. Commissioning Testing, including Functional Performance Testing, for each system to be commissioned
m. Integrated Systems Tests
n. Post-test deficiency correction for each system to be commissioned
o. Re-Testing
p. Training for each of the systems to be commissioned
q. Submission and approval of the Initial and Final Commissioning Reports
r. Final testing required to be witnessed by Government Acceptance Testing Representatives, as identified in system level sections.
1.9 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES :
SECTION 01 91 00.15 Page 4
SD-06 Test Reports
Completed Construction Observation Checklists; G , Design Review Report; G , Interim Construction Phase Commissioning Plan; G , Final Construction Phase Commissioning Plan; G , ; S
Initial Commissioning Report; G , Issues Log; G , SD-07 Certificates
Commissioning Firm; G , Certificate of Readiness; G , SD-10 Operation and Maintenance Data
Maintenance and Service Life Plan; G , Systems Manual; G , SD-11 Closeout Submittals
Final Commissioning Report; G , Updated Final Commissioning Report; G , Final Commissioning Report (eNotebook); S
Updated Final Commissioning Report (eNotebook); S
1.10 COMMISSIONING FIRM
Employ the services of a Commissioning Firm and all Commissioning Specialists required to perform work for this project. The Commissioning Firm must be a first-tier subcontractor that is financially and corporately independent from prime contractor and all other subcontractors and the Designer of Record and that is not participating in any other work on this Contract, including design, furnishing equipment, construction, or testing, adjusting, and balancing.
a. Submit the Commissioning Firm's and Commissioning Specialists' qualifications, including the name of the firm and each CxC and each certification, no later than 30 calendar days after contract award notice to proceed .
b. If, for any reason, a specialist loses a certification during this period, immediately notify the Contracting Officer and submit another Commissioning Specialist for approval. An approved successor must validate all work performed for this project by the CxC who lost a certification.
SECTION 01 91 00.15 Page 5
1.10.1 Commissioning Specialists (CxC)
Assign Lead Commissioning Specialist and other appropriate Commissioning Specialists for the systems to be commissioned.
1.10.1.1 Lead Commissioning Specialist (CxC)
Lead Commissioning Specialist (CxC) coordinates all aspects of the commissioning process. Duties include leading and overseeing the commissioning work and acting as the primary point of contact for the commissioning work. CxC may serve as a systems Specialist if all requirements for both designations are met. CxC must have a minimum of five years of commissioning experience, including two projects of similar size and complexity to this project.
CxC must be certified in one of the following:
NEBB Building System Commissioning Professional (CxCP)
ACG Certified Commissioning Authority (CxA)
ICB/TABB Certified Commissioning Supervisor
BCA Certified Commissioning Professional (CCP)
AEE Certified Building Commissioning Professional (CBCP)
University of Wisconsin-Madison Qualified Commissioning Process Provider (QCxP)
ASHRAE Building Commissioning Professional (BCxP).
1.10.1.2 Commissioning Specialists
Refer to the related technical commissioning specification section for additional qualifications for each Commissioning Specialist associated with each system. Include all Commissioning Specialist qualifications with the Commissioning Firm submittal:
a. Mechanical Commissioning Specialist: The technical work associated with mechanical systems to be commissioned must be performed by a Commissioning Specialist certified by NEBB, ACG, ICB/TABB, AEE, University of Wisconsin-Madison, ASHRAE, or BCA in the commissioning of HVAC systems with five years of experience in the commissioning of HVAC systems.
b. Electrical Commissioning Specialist: The technical work associated with electrical systems to be commissioned must be performed by an engineering technician with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices. The lead engineering technician specified in specification Section 26 08 00 APPARATUS INSPECTION AND TESTING may serve as the Electrical Commissioning Specialist.
c. Building Enclosure Commissioning Specialist: The technical work associated with the Building Envelope system must be performed by a Building Enclosure Commissioning Specialist that is a registered architect or engineer, or building scientist, with five years of building enclosure design or construction experience or a professional
SECTION 01 91 00.15 Page 6 with training and Certification in Building Enclosure Commissioning from a third-party certification organization plus five years of commissioning experience. The commissioning provider must have the necessary training, experience, and FPT equipment.
1.11 COMMISSIONING STANDARD
Comply with the requirements of the commissioning standard under which the Commissioning Firm and Specialists qualifications are approved. When the firm and specialists are certified by BCA, AEE, ASHRAE, or the University of Wisconsin-Madison, comply with the requirements of one of these acceptable standards: ACG Commissioning Guideline , NEBB S1110, ANSI/SMACNA 014 , or ASHRAE 202. In a conflict, the most stringent requirements apply. In addition, comply with ASHRAE 90.1 - IP commissioning requirements for all systems. Refer to related technical commissioning specification sections for additional standards requirements.
Comply with applicable International Electrical Testing Association (NETA) testing standards for electrical systems. The following requirements apply to all project commissioning and test standards:
a. Implement all recommendations and suggested practices contained in the Commissioning Standard and test standards.
b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.
c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.
d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract.
e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning Standard.
f. Use any new requirements, recommendations, and procedures published or adopted by the body responsible for the applicable Commissioning Standards at the time of project award.
g. If there is a conflict between the requirements of the contract documents and the commissioning standard used, the contract documents take precedent.
1.12 SUSTAINABILITY THIRD PARTY CERTIFICATION (TPC)
The Commissioning Specialist must perform all commissioning activities, coordination, and submittals required by the sustainability Third Party Certification (TPC) program applied to this project, in accordance with Section 01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING.
1.13 ISSUES LOG
The Commissioning Specialist develops and maintains an Issues Log for the systems to be commissioned. The issues log documents and tracks resolution of deficiencies identified during submittal reviews, inspection, and testing. At any point during construction, any commissioning team member finding deficiencies may communicate those
SECTION 01 91 00.15 Page 7 deficiencies in writing to the Commissioning Specialist for inclusion into the Issues Log. For each issue, the Issues Log includes, but is not limited to, a unique reference number, description of the issue with contract requirement referenced, location of or equipment name/tags exhibiting the issue, the initials of the individual's name whom reported the issue, the date of first observation, the proposed resolution of the issue and date proposed, the date of any subsequent observations with applicable additional information, and the date of implementation of the final resolution of the issue as confirmed by the Commissioning Specialist and Contracting Officer. Issues must not be deleted from the issues log.
CxC must submit the Issues Log monthly and within three working days from changes to the Issue Log. The CxC is responsible for distributing the Issues Log to the Commissioning Team. QC Manager must track construction deficiencies identified in the Issues Log using a quality management system in accordance with Section 01 45 00 QUALITY CONTROL. The QC Manager is responsible for notifying the CxC and Contracting Officer of outstanding deficiencies and tracking them to resolution in accordance with Section 01 45 00 QUALITY CONTROL, "Quality Control Plan".
1.14 CERTIFICATE OF READINESS
Prior to scheduling Commissioning Tests for each system, the Quality Control Manager must issue a Certificate of Readiness for each system, certifying that inspections have been completed, open issues have been resolved, and the system is ready for Commissioning Tests. Refer to each related technical commissioning specification section for additional requirements.
Submit the Certificate of Readiness for each system days 20 working days prior to Commissioning Tests of that system. Do not schedule Commissioning Tests for a system until the Certificate of Readiness is approved by the Government.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 DESIGN REVIEW
The CxC and other Commissioning Specialists must review design documents.
Provide a Design Review Report identifying discrepancies or deficiencies that would prevent the systems to be commissioned from operating or performing effectively in accordance with the design requirements or being adequately safely maintained. Report must include individual list of each deficiency and corresponding corrective action necessary for proper system performance. Identify any discrepancies between the design and the Owner's Project Requirements Document. The Owner's Project Requirements Document is provided for commissioning review purposes only and does not form a part of the contract documents for this project. Submit the Design Review Report no later than 14 calendar days after approval of the Commissioning Firm and Commissioning Specialists . The Contracting Officer, Construction Manager, the Contractor's Project Manager, the CxC, and the Designers of Record for the associated systems must meet, discuss, and resolve any outstanding items contained in the report no later than 14 calendar days after submission of the report.
SECTION 01 91 00.15 Page 8
3.2 CONSTRUCTION SUBMITTAL REVIEWS
Coordinate construction submittal document reviews for commissioned systems and assemblies with the CxC. The commissioning submittal review does not replace the Government submittal review, in accordance with Section 01 33 00 SUBMITTAL PROCEDURES .
The CxC must identify construction submittals to be provided by the contractor for the commissioned systems. The CxC must evaluate construction submittals for compliance with the contract documents prior to submission to the Government . Include a copy of CxC comments with the construction submittals . Include a copy of the submittal document review transmittal and response in the Commissioning Report.
3.3 COMMISSIONING KICKOFF MEETING
Conduct a Commissioning Kickoff Meeting, led by the CxC, after approval of the Commissioning Firm and Commissioning Specialists, and no later than 30 days following approval of the Commissioning Firm and Specialists.
Discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this section.
The Construction Manager, Contractor's Project Manager, Quality Control team, Designer of Record, and the Government Acceptance Testing Representatives and other Government team members must attend this meeting. Invite the User and a Public Works Division Representative to attend this meeting.
3.4 REGULAR COMMISSIONING COORDINATION MEETINGS
The Quality Control team, Designer of Record, and the Government Acceptance Testing Representatives and other Government team members must attend this meeting. Sub-Contractor Representatives for each trade responsible for construction/installation of systems to be commissioned must attend this meeting as requested by the CxC. Invite the User and a Public Works Division Representative to attend this meeting.
CxC must conduct monthly commissioning coordination meetings when installation of commissioned systems begins. Provide status of commissioned systems, open issues log items, outstanding submittals, and upcoming commissioning activities. Conduct bi-weekly commissioning coordination meetings within 30 days of the scheduled date for commissioning testing.
3.5 CONSTRUCTION PHASE COMMISSIONING PLANS
The Interim Construction Phase Commissioning Plan identifies the commissioning and testing standards and outline the overall commissioning process, the commissioning schedule, the commissioning team members and responsibilities, lines of communication, documentation requirements for the construction phase of the project, and Template Building Enclosure Inspection Checklists. Submit the Interim Construction Phase Commissioning Plan, prepared by the CxC, 14 calendar days after the Construction Commissioning Coordination Meeting and 14 days prior to the start of construction of the building enclosure. Include the following items in the commissioning schedule in addition to the items in paragraph
SECTION 01 91 00.15 Page 9
PROJECT SCHEDULE: Commissioning Site Visits, Seasonal Testing, Warranty Phase Site Visit, Post-Construction Endurance Testing, and Updated Commissioning Report.
The Final Construction Phase Commissioning Plan includes the information provided in the Interim Construction Phase Commissioning Plan as well as commissioning construction observation checklists and test procedures such as Pre-Functional Checklists , Integrated Systems Test Checklists, and Functional Performance Test Checklists and other Commissioning Test Checklists for each building, for each system required to be commissioned, and for each component for inclusion in the Final Construction Phase Commissioning Plan. Refer to the related technical commissioning specification section for additional requirements for checklists. Submit the Final Construction Phase Commissioning Plan, prepared by the CxC, no later than 90 calendar days prior to the start of Commissioning Inspections. Once approved, file the approved plan in the Sustainability eNotebook.
3.5.1 Construction Observation Checklists
Construction Observation Checklists must include items for physical inspection or testing that demonstrate that installation and start-up of equipment and systems is complete. Refer to paragraph COMMISSIONING INSPECTIONS. Construction observation checklists must be tailored to verify the specific installation requirements and details of the construction documents and manufacturer's instructions.
3.5.2 Test Procedures and Checklists
Test procedures and checklists must include procedures that explain, step-by-step, the actions and expected results that will demonstrate that the systems perform in accordance with the contract. Refer to paragraph COMMISSIONING TESTS. Include the following sections and details appropriate to the systems being tested in the test procedures and checklists:
a. Notable system features including information about controls to facilitate understanding of system operation
b. Conclusions and recommendations. Conclusions must clearly indicate if system does or does not perform in accordance with contract requirements. Recommendation must clearly indicate that the system should or should not be approved by the Government.
c. Test conditions including date, beginning and ending time, and beginning and ending outdoor air conditions
d. Attendees
e. Identification of the equipment involved in the test
f. Control system feature identification
g. As-found condition of the system operation
h. List of test items with step numbers along with the corresponding feature or operation, intended test procedure, expected system response, and pass/fail indication.
SECTION 01 91 00.15 Page 10
i. Space for comments for each test item.
3.6 COMMISSIONING SITE VISITS
The CxC must visit the construction site no less than once every 90 days during construction of the commissioned systems to verify that construction is achieving the requirements of the contract documents. The frequency of the site visits must increase to bi-weekly within 90 days of the scheduled commissioning tests. The CxC must vist the construction site more frequently, as needed, to complete commissioning inspections.
Document deficiencies or issues in the Issues Log.
3.7 COMMISSIONING INSPECTIONS
Complete inspections using Construction Observation Checklists for each individual item of equipment or system for each system required to be commissioned in accordance with the commissioning plan. Indicate commissioning team member inspection and validation of each checklist item by initials. Validation of each checklist item by each team member indicates that item conforms to the contract documents and design in their area of responsibility. Commissioning Specialist validation of each checklist item indicates that each item has been installed correctly and in accordance with contract documents. Submit the initialed and Completed Construction Observation Checklists no later than 7 calendar days after completion of inspection of all checklists items for each system.
3.8 COMMISSIONING TESTS
Demonstrate that all systems, equipment, and components have been installed correctly and that the systems operate and perform, including interactive operation between systems, in accordance with contract documents. Perform tests as specified in related technical commissioning specifications. Provide all materials, services, and labor required to perform all commissioning tests.
Commissioning Specialist's duties include leading and documenting all tests for the systems to be commissioned with appropriate sub-contractors performing the Tests. The representatives listed in the paragraph COMMISSIONING TEAM must attend the tests with the exception of the Construction Manager .
3.8.1 Test Scheduling and Coordination
Schedule Commissioning Tests for each system only after the Certificate of Readiness has been approved by the Government for the system. Correct all deficiencies identified through any prior review, inspection, or test activity before the start of Commissioning tests.
Commissioning Tests and Integrated Systems Tests must be performed with the CxC present. Government reserves the right to witness all tests.
Coordinate test schedule with Government representatives.
3.8.2 Testing Procedures
Commissioning tests include tests such as functional performance and integrated systems tests. For electrical systems testing, include testing of sensor calibrations, control responses, safeties, interlocks, operating modes, capacity, lighting levels, and verification of all other electrical system contract performance requirements. Perform test procedures in
SECTION 01 91 00.15 Page 11 accordance with the commissioning standards specified. In addition, comply with the testing procedures specified in the sections listed in paragraph RELATED SECTIONS.
3.8.3 Sample Strategy
Refer to the sections identified in paragraph RELATED SECTIONS for sample strategy.
For electrical systems, test 100 percent of all equipment and systems except for the following. Test at the sample rate shown:
a. Lighting Controls 30%
3.8.4 Aborted Tests and Re-Testing
Abort any test if any deficiency prevents successful completion of the test or if any required commissioning team member is not present for the test. Re-test after all deficiencies identified during the original test have been corrected. Contracting Officer may withhold payment equivalent to lost time, re-testing, and aborted tests. These costs may include salary, travel costs, and per diem for Government team members.
3.9 TRAINING PLAN
CxC must review the training plan for training associated with the equipment and systems to be commissioned, checking that each plan has the trainer name, trainer contract information, training schedule and location. Submit review at least 30 days prior to the first training event. Incorporate CxC review comments prior to submitting training plan in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA and 01 78 24.00 20 FACILITY DATA WORKBOOK (FDW) . Update and resubmit the training plan based on any corrective action taken.
3.9 SYSTEMS MANUAL
The Systems Manual includes system single line diagrams, as-built sequences of operation and controls drawings, as-built control setpoints, recommended schedule for sensor and actuator calibration, recommended schedule of maintenance when not in the O&M manuals, recommended re-testing schedule with proposed testing forms, and full equipment warranty information for all commissioned systems. Update and resubmit the system manual information based on any corrective action taken during the warranty period.
3.10 COMMISSIONING REPORT
Submit an Initial Commissioning Report no later than 14 calendar days following commissioning team validation of all Commissioning Tests, including Functional Performance Tests, and Integrated Systems Tests , with the exception of Seasonal Tests. Submit a Final Commissioning Report upon completion of training and trend log reviews. File the approved Final Commissioning Report (eNotebook) in the Sustainability eNotebook. Include the following information in the Final Commissioning Report:
a. An executive summary describing the overall commissioning process, the results of the commissioning process, outstanding deficiencies and recommended resolutions, and seasonal testing that must be scheduled for a later date. Indicate, in the executive summary, whether the
SECTION 01 91 00.15 Page 12 systems meet the requirements of the contract documents.
b. A list of deficiencies discovered during the commissioning process and the corrective actions taken in the report.
c. Completed Building Enclosure Inspection Checklists, Pre-Functional Checklists and other Commissioning Observation Checklists, Commissioning Test Checklists such as Functional Performance Test Checklists and Integrated Systems Test Checklists, , the Air Leakage Test Reports and Diagnostic Test Reports, the Final Construction Phase Commissioning Plan, the Issues Log, Training Attendance Rosters, the Design Review Reports, Submittal Review Report, and any other documents as specified by related technical commissioning specification sections.
3.11 WARRANTY PHASE SITE VISIT
The Lead Commissioning Specialist must visit the building site concurrent with the 9 month warranty inspection to inspect building system equipment and review building operation with the building operating/maintenance staff, and identify any deficiency of the building systems to operate in accordance with the contract documents. The Commissioning Specialist must notify the Contracting Officer of any identified deficiencies and the proposed corrective action. Submit Updated Final Commissioning Report and Systems Manuals, documenting the results of the warranty phase inspection. Include other warranty or post-construction phase activities as specified in related technical commissioning specification sections, such as Seasonal testing results and Post-Construction Endurance Test and Trend Log Report. File the approved Updated Final Commissioning Report (eNotebook) in the Sustainability eNotebook.
SECTION 01 91 00.15 Page 13
-- End of Section --
SECTION 01 91 00.15 Page 14
| 01 91 00.15 - BUILDING COMMISSIONING |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.3 COMMUNICATION WITH THE GOVERNMENT |
| 1.4 COMMUNICATION WITH GOVERNMENT ACCEPTANCE TESTING REPRESENTATIVES |
| 1.5 SYSTEMS TO BE COMMISSIONED |
| 1.6 RELATED SECTIONS |
| 1.7 COMMISSIONING TEAM |
| 1.8 PROJECT SCHEDULE |
| 1.9 SUBMITTALS |
| 1.10 COMMISSIONING FIRM |
| 1.10.1 Commissioning Specialists CxC |
| 1.10.1.1 Lead Commissioning Specialist CxC |
| 1.10.1.2 Commissioning Specialists |
| 1.11 COMMISSIONING STANDARD |
| 1.12 SUSTAINABILITY THIRD PARTY CERTIFICATION TPC |
| 1.13 ISSUES LOG |
| 1.14 CERTIFICATE OF READINESS |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
| 3.1 DESIGN REVIEW |
| 3.2 CONSTRUCTION SUBMITTAL REVIEWS |
| 3.3 COMMISSIONING KICKOFF MEETING |
| 3.4 REGULAR COMMISSIONING COORDINATION MEETINGS |
| 3.5 CONSTRUCTION PHASE COMMISSIONING PLANS |
| 3.5.1 Construction Observation Checklists |
| 3.5.2 Test Procedures and Checklists |
| 3.6 COMMISSIONING SITE VISITS |
| 3.7 COMMISSIONING INSPECTIONS |
| 3.8 COMMISSIONING TESTS |
| 3.8.1 Test Scheduling and Coordination |
| 3.8.2 Testing Procedures |
| 3.8.3 Sample Strategy |
| 3.8.4 Aborted Tests and Re-Testing |
| 3.9 TRAINING PLAN |
| 3.10 COMMISSIONING REPORT |
| 3.11 WARRANTY PHASE SITE VISIT |
File details come from the government source that posted it. Updated .