N4008526R0005 Amendment 0004.pdf

PDF 2 MB Posted

Attached to
P1112 B72 Resiliency Improvements, Portsmouth Naval Shipyard (PNSY), Kittery, Maine
Solicitation number
N4008526R0005
Issued by

About this file

This document is Amendment 0004 to Solicitation N4008526R0005, a Design-Bid-Build (DBB) project for Resiliency Improvements at Portsmouth Naval Shipyard (PNSY) in Kittery, Maine, issued by NAVFACSYSCOM Mid-Atlantic on April 27, 2026, with an effective date of April 27, 2026.

The amendment extends the proposal due date from May 14, 2026 to May 21, 2026 (both at 2:00 PM EDT), while the Pre-Proposal Inquiry (PPI) cutoff date remains unchanged at April 23, 2026. The amendment incorporates specification and drawing revisions addressing 226 PPI responses and other clarifications. Key revisions include: updated mechanical drawings for piping systems, blower specifications (Aerzen GM 15L model, 25 HP, 492 ICFM @ 5.5 psi), CIP discharge pump requirements, electrical panel specifications (NEMA 4X, 316L stainless steel), fence grounding note modifications, preconstruction meeting timeline adjustments (extended to 60 calendar days from Notice to Proceed), removal of temporary piping requirements from contractor scope, confirmation that contractor operates systems 24 hours daily during the 48-day demonstration period, and clarifications on ultrasonic flowmeter specifications (40 fps maximum, 1% accuracy, 4-20mA output, NEMA4X transmitter). Additionally, revised Attachment H (Price Proposal Form) has been provided on SAM.gov. All terms and conditions remain unchanged except as noted herein, with the contracting officer James A. Godwin authorizing the amendment on April 27, 2026.

View the file

Other files

File Type Posted
N4008526R0005 Amendment 0010.pdf PDF
N4008526R0005 Amendment 0009.pdf PDF
GC100A_Milestones and Coordination Requirements_20260528.pdf PDF
N4008526R0005 Amendment 0008.pdf PDF
Attachment H - Price Proposal Form Revision 2.docx DOCX document
01 11 00.00 22_RevAmend08.pdf PDF
098 S-502 Rev. 1 P-1112.pdf PDF
A-450 - ENLARGED PLAN DETAILS.pdf PDF
101 S-505 Rev. 1 P-1112.pdf PDF
102 S-506 Rev. 1 P-1112.pdf PDF
Lifting_Eye_Comp_Cut_Sheet_LIFTMAX-PEP-00100 (050726).pdf PDF
A-400 - ENLARGED PLAN -PUMP ROOMS B AND S AND C.pdf PDF
075 S-102 Rev. 1 P-1112.pdf PDF
094 S-308 Rev. 1 P-1112.pdf PDF
P-1112 Drawing Updates 2026-04-29.pdf PDF
072 S-001 Rev. 1 P-1112.pdf PDF
086 S-124 Rev. 1 P-1112.pdf PDF
08 53 00.pdf PDF
41 22 13.14.pdf PDF
N4008526R0005 Amendment 0006.pdf PDF
N4008526R0005 Amendment 0005.pdf PDF
PPI 98 - V-104 Archaeology Area Outlined.pdf PDF
PPI 198 - 26 56 00.pdf PDF
PPI 203 - COMNAVREGMIDLANTINST_11320_11B.pdf PDF
PPIs 181.182.183.208 - Schedule of Special Inspections.pdf PDF
PPI 137 - 46 30 00 Attachments 1 to 4.pdf PDF
PPI 91 - Sheet 7 of 226 - H-101.pdf PDF
PPI 166 - Air Valve Detail.pdf PDF
PPI 200 - 32 17 23.pdf PDF
Option 13 - Accessory Structure_REV2.pdf PDF
Attachment H - Price Proposal Form Revised.docx DOCX document
A-500 - WALL SECTIONS.pdf PDF
N4008526R0005 Amendment 0003.pdf PDF
N4008526R0005 Amendment 0002.pdf PDF
P-1112 B72 Resiliency Improvement Site Visit Log.pdf PDF
N4008526R0005 Amendment 0001.pdf PDF
DBIDS 5500 Form.docx DOCX document
Attachment H - Price Proposal Form.docx DOCX document
Attachment G - Small Business Subcontracting Plan (SBSP) Template.docx DOCX document
P-1112 Drawings.pdf PDF
Attachment E - Historical Small Business Utilization.docx DOCX document
DBIDS 5512 Form.pdf PDF
Memorandum - Bidding Notes P-1112.pdf PDF
P-1112 Specifications.pdf PDF
Attachment F - Small Business Participation Commitment Document (SBPCD).docx DOCX document
Attachment D - Past Performance Questionnaire.docx DOCX document
Attachment C - Construction Experience Data Sheet.docx DOCX document
Attachment B - PIEE Vendor Access Instructions.pdf PDF
Attachment A - PPI Log Template.xlsx XLSX spreadsheet
N4008526R0005.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Block 14 (Description of Amendment/Modification): SOLICITATION NUMBER N40085-26-R-0005, DESIGN-BID-BUILD (DBB) P1112 B72

RESILIENCY IMPROVEMENTS, PORTSMOUTH NAVAL SHIPYARD (PNSY), KITTERY, MAINE

The proposal due date of 14 May 2026 NLT 2:00 PM EDT has been extended to 21 May 2026 NLT 2:00 PM EDT.

The Amendment is issued to incorporate the following:

1. Provide Specification/Drawing revisions (See summary of revisions).

2. Provide responses to PPIs (additional PPI responses will be forthcoming via Amendment(s)).

3. Provide revised Attachment H - Price Proposal Form (provided on SAM.gov).

4. Extend the proposal due date from 14 May 2026 to 21 May 2026 NLT 2:00 PM EDT. The PPI cutoff date of 23 April 2026 NLT 2:00 PM EDT remains unchanged.

Section 00 00 00 - Procurement and Contracting Requirements

The following changes have been made:

INFORMATION FROM TO

Response Due Date 14 May 2026 21 May 2026

N4008526R00050004

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

1. Specification/Drawing Continuation Sheet:

Drawing

No. Summary of Revision

PPI

No.

V-104 Boundary showing area where onsite archeologist is required. 98

C-102 Detail callouts for D-501 and D-502 have been corrected to D-401 and D-402. 54

C-102 Detail callouts for D-503 has been corrected to D-420. 55

C-102

Add a 12”x12”x12” PP-RCT Tee to the above ground outfall pipe at the below grade to above grade pipe transition near the corner of Building 178. The middle outlet of the tee must include a 12” gate valve and a 12” HDPE blind flange. The other outlet of the tee must include a 12” gate valve between the tee and the remaining above grade outfall pipe.

n/a

C-108 Government revised drawings for location of accessory structure identified in Bid Option 13. See drawings included in amendment.

A-402 Government revised drawings for location of accessory structure identified in Bid Option 13. See drawings included in amendment.

A-403 Government revised drawings for location of accessory structure identified in Bid Option 13. See drawings included in amendment.

A-500 Drawing revised to include detail F n/a

GC100

Revised notes order on drawing. The second Note 5 will become Note 6, Note 6 becomes Note 7, Note 7 becomes Note 8.

FA101 Revised keynote 1 to delete “explosion Proof” 170

M-102 General Sheet Note #5 will be revised to reference the new bridge crane (bid option #12) in lieu of the existing overhead crane.

D-101 Note 3 has been updated and expansion anchors have been removed. 151

D-102 Section views have been revised, reference D-301. 149

D-102 Call out on discharge of pumps has been changed to “Glass Lined DI Class 53” 150

D-102 Section views have been revised to direct to D-301. 120

D-102 Callout for providing removal 4’x6’ roof hatch has been reviewed to refer to S-124. 197

D-103

D-107

Drawing updated to include bypass connection and pig launching location outside of building 51

D-106

Drawings and process indicate an outdated blower selection and line sizing was used. Blower to be rated for a max capacity of 492 ICFM @ 5.5psi. The air line from the blowers to the membrane tanks should be revised to 6" rather than 3".

The motor will also now be 25 HP. Vendor Aerzen GM 15L model, kaeser, or approved equal. A flow switch and isolation valve will be on the blower discharge piping.

D-106 The combined HDPE line from the UF pumps to the UF break tank has been changed from 6-inch to 8-inch.

D-405 Section A has been revised to call out 8” SDSS piping to match Section C. 161

D-405 Section A has been revised to call out 8” SDSS piping to match Section C. 162

D-414

Add CIP discharge pump n/a

D-415

Add CIP Discharge Pump

D-415 A note to be added to drawing D-106: For the combined CIP system bi-directional pump, a PSV or a pressure switch with safety relay is required on the PD pump discharge.

D-505 Added air valve detail to drawing 166

D-607 Abbreviated Equipment List of Major Suppliers. Changed intake screen quantity from 2 to 1. n/a

E-002 Note will be deleted. Any unforeseen conditions will be handled in accordance with the FAR 52.236-2

Differing Site Conditions.

E-002

Add CIP Discharge Pump to Mechanical Equipment Wiring Schedule – Process Equipment Table. CIP

Discharge Pump schedule as follows:

Equipment: CIP Discharge Pump

Panelboard: PP-B72S

HP: 2

Volt: 460

Phase: 3

CB Size: 20

Wires per set: 3

Sets: 1

Cond: ¾"

Wire Size: 12

+GND: 12

Starter: VFD n/a

E-101

E-102

ED101

ED102

ED103

EL101

EL102

EP101

EP102

EP103

EP104

EP105

EP106

EP107

EP108

Reprint sheet to resolve discrepancy between drawing scale and graphic scale shown on drawings. 192

E-102

Revise Fence Grounding Note #1 to “FENCE POSTS MUST BE BONDED TO THE SUBSTATION

GROUND GRID AT INTERVALS NOT TO EXCEED 10 FEET USING BARE COPPER

CONDUCTOR (MINIMUM #2/0 AWG OR AS SPECIFIED BY THE GROUNDING STUDY).”

EP101

Add NEMA 4X VFD, rated per Mechanical Equipment Wiring Schedule – Process Equipment Table for

CIP Discharge Pump. Coordinate with equipment location shown in drawing sheet D-415 changes listed in this continuation sheet. Feed from Panel PP-B72S, Circuit 15.

n/a

EP109

Government revised drawings for location of accessory structure identified in Bid Option 13. See drawings included in amendment.

EP601

One-line diagram to be updated. The MCC-B72D branch feeding 06-01-006 will be removed and the branch feeding 06-01-005 will be revised to 06-01-005/006.

EP701

Replace PP-72S, Feeder No. 15 Spare breaker with 20A to support CIP Discharge Pump per continuation sheet changes on sheet E-002 and EP101.

Spec No.

Part / Subpart /

Paragraph Summary of Revision PPI No.

01 11 00.00 22 1.2.2.a This sentence has been deleted. 114

01 14 00.00 22 1.8.2 This section has been deleted. 115

01 30 00.00 22 1.4.2.2 Delete qualifications for contractor project manager. 118

01 30 00.00 22 1.6 and 1.6.2

Preconstruction meeting must take place within 60 calendar days from receiving the Notice to Proceed.

The Accident Prevention Plan and the Indoor Air

Quality Management Plan must be submitted to the

Contracting Officer 15 calendar days prior to the

Preconstruction meeting.

01 30 00.00 22 1.6 Preconstruction meeting must take place within 60 calendar days from receiving the Notice to Proceed.

01 30 00.00 22 1.6.2 The Preconstruction Survey Report must be submitted and approved prior to the start of on-site construction.

01 30 00.00 22 1.6.2

Facility Turnover Planning Meeting Agenda, Red

Zone Checklist-POAM, and NAVFAC PWD ME

Internal Service Requirements must be submitted at least 14 calendar days prior to the initial Red Zone meeting, to be held at approximately 75% of construction completion and be outlined in the baseline schedule.

01 45 35 Appendix A See revised Schedule of Special Inspections 181, 182, 183, 208

01 90 00.15 20 Attachment (2.0/A/6 &

2.0/I/1/d )

Revised paragraph to identify that the contractor is to operate the system 24 hrs. per day during the 48-day demonstration period.

02 83 00.00 22 3.1.1.3 No change to 1st paragraph. Delete 2nd and 3rd paragraph.

n/a

02 83 00.00 22 3.1.1.3

Revise specification to: "Furniture and equipment will remain in the lead, cadmium, and chromium

(VI) control area. Protect and cover furnishings and equipment or remove furnishings and equipment from the work area and store in a location approved by the Contracting Officer."

05 12 00 1.4.1.1 and 1.4.1.2

Revised paragraph. Shop and erection drawings are not required to be stamped by a PE. Connection designs are required to be stamped by a PE.

23 05 93 Attachment D

Deleted requirement for DALT. Revised

Attachment to only include the requirement to provide Seal Class A on all new ductwork.

23 64 26 2.4.5.c.5 The specified maximum sound level has been revised to 70 dBA from 63 dBA.

23 64 26 2.4.5.e Revised section from two valves to one valve. 58

26 56 00 Specification added to project 198

28 31 60

2.4.1.1 Change “Horns must be explosion proof…” to

“Horns must be corrosion proof…”

32 17 23 Specification added to project 200

Paragraph Summary of Revision PPI No.

40 60 00 2.4.3

Add paragraph 2.4.3.2 Ultrasonic Flow Meter.

Ultrasonic flowmeter must utilize high frequency transit time transducer. Flowmeter must be capable of measuring flow up to a maximum flow rate of 40 fps. Provide Ultrasonic Flow Meters complete with matched transducers, self aligning installation hardware and transducer cables. Ultrasonic transducers must be optimized for the specific pipe and process conditions for the application. The flow meter accuracy must plus or minus 1 percent of rate from 0.3 to 12 meters/sec 0 to 40 ft/sec. The flowmeter must be loop powered and have a 4-

20mA output. Transmitter shall be rated NEMA4X.

46 81 00 2.7.6

All Control Panels in the membrane supplier’s scope shall be rated for NEMA 4X, 316L stainless steel.

46 82 00 1.1.2.a.3a Temporary piping has been deleted from specification

46 82 00 2.3.2.d

Acceptable materials include Nickel Aluminum

Bronze (e.g., ASTM B148 C95800), Super Duplex

Stainless Steel, or Duplex Stainless Steel 2205.

Shaft sleeve is removed.

46 82 00 2.5.5

Add Section 2.5.5 CIP Discharge Pump

The CIP pump shall be an industrial-duty centrifugal chemical transfer pump with VFD control, designed for corrosive service including acidic and caustic solutions at temperatures up to

140°F.

Pump Basis of Design:

• Flow: 40 GPM (Primary design point)

• Head: 70 ft TDH

• Flow: 20 GPM (secondary point)

• Power: 2 HP (minimum)

• VFD Drive

• Material: Chemical-resistant polypropylene or approved equal

• Acceptable manufacturer: Finish Thompson DB

Series Magnetic Drive Pump or approved equal.

Provide the following on the pump discharge line in order of flow:

1. Spring-loaded chemical-compatible check valve immediately downstream of pump discharge

2. Full-port chemical-resistant isolation valve (2-inch) downstream of check valve

3. Pressure gauge (0–100 psi range) with chemical diaphragm seal installed on pump discharge for system monitoring

All valves and wetted components shall be compatible with acidic and caustic CIP waste service

Paragraph Summary of Revision PPI No.

Memorandum

Bidding Notes n/a

Delete Item 29 due to relocation of Bid Option 13 structure.

2. PPI Responses:

PPI Reference Question Government Response

Page Section Para.

1 Electrical Because this facility is owned by the

United States Federal Government, and is utilized as a Maintenance Utility

Building, we understand that Unified

Facilities Criteria (“UFC”) 3-520-01 and

Unified Facilities Guide Specifications

(UFGS) Section 26 05 19.10.10 shall apply for purposes of competitive bidding and project execution. To ensure that the project is bid and constructed in accordance with the applicable regulations and requirements, please confirm that UFC 3-520-01 and

UFGS Section 26 05 19.10.10 shall apply to this project. Specifically, please confirm that bidders are permitted to utilize the type(s) of material(s) described in UFC 3-520-01 and UFGS

Section 26 05 19.10.10 applicable to their scope of work despite any potentially contradictory provisions in the design plans and specifications.

As a federal project, all Department of

Defense UFC standards are applicable. Applicable UFGS specifications are included in the project technical specification sections, edited to project requirements. Reference the applicable technical specifications for requirements.

2 Electrical Regarding the Build America Buy

America Act (“BABA”), please confirm the products in this design and that are specified comply with all BABA requirements or otherwise please:

1. Identify any and all General

Applicability Waivers related to any products, categories of products or manufactured products specified for this project.

2. Name any and all project level waivers that have been proposed and/or awarded for this project.

Project is designed to comply with the

Buy American Act.

3 Given the complexity of this project and the level of effort required to prepare a comprehensive effort and proposal, we request that the proposal due date be extended to May 15, 2026. This will afford Contractors the time needed to provide the Government with comprehensive, cost efficient proposals.

See Amendment for due date extension.

4 Salvage disposition list, which items are assumed required and at what point during the project will the Government

Refer to AD101 for salvaged material.

Awardee shall submit post award RFI.

Contracting officer issue disposition for salvaged materials?

5 S-002 Pre-engineering metal building ,"Metal framed building, States the metal building manufacturer must provide supplemental framing to support the required building systems and equipment loads at no additional cost to owner."

Government to provide values for all equipment loads to be supported.

Contractor shall provide equipment loads based on selected manufacturer.

6 Please explicitly define the scope of the engineering requirements for the cold form metal framing

The Engineer delegates the design of the pre-engineered metal building

(PEMB) to the metal building manufacturer (MBM). The MBM will submit the design drawings and calculations to the Engineer I9:I213 for final review and approval after the

MBM has had the drawings and calculations stamped by a third-party licensed engineer.

7 S-101 Government to provide information related to size, depth, and installation date of existing duct banks shown on S-

101. Government to confirm existing ductbank conditions will be acceptable with proximity of pile installation efforts.

Location of ductbank was identified within design. Keynote #1 on S-104 indicates that the GC will need to field-verify the extents of the duct banks prior to pile installation and construction.

8 If specific manufacturers were used in space planning, design coordination and design of the building structure, please provide the information from the manufacturers that was incorporated into the building design. Please confirm design flexibility was incorporated to account for all approved manufacturers in the case an approved manufacturer is procured in lieu of the BOD.

Confirmed. Design flexibility was incorporated and no basis of design manufacture was required.

9 Will contaminated soils, classified as non-hazardous soil for disposal by spec definition be the responsibility of the contractor if discovered after bidding during soil classification testing?

Contaminated soils require increased

PPE controls and have special disposal restrictions as mandated by PNSY which will increase cost. How should bidders quantify this unforeseen increase?

The Contractor will need to dispose of all soils in accordance with the

Specifications in the RFP. The

Contractor should assume any soil determined 'contaminated' by the disposal facilities should be priced as hazardous soil for the purposes of bidding.

10 Confirm if any dust cleaning of the building surfaces will be necessary to remove hazardous dust prior to construction. E.g. lead, ACM, guano, pcb, etc.

Refer to RFP Specification Sections

02 82 00.00 22 and 02 83 00.00 22

11 Please confirm the building life safety has been evaluated by the

AHJ/Navfac/USACE FPE/QFPE and the layout shown on the drawings meets or exceeds the code requirements for the system. If not, please confirm how much scope is required to be installed for final acceptance but not shown on the documents.

Confirmed. NAVFAC Fire Protection

Engineer has reviewed the project bid documents.

12 C-001 Utility

Notes

Government to confirm note 7, if excavation does not begin within 27 days of a PWD ME Dig Safe, a new notification is required. Will this secondary notification be 14 calendar days as well?

Confirmed.

16 V-104 General

Note 2

Government to confirm the date of the

(latest edition) of the "Portsmouth Naval

Shipyard's current soil management standard operating procedure"

Latest revision is 2021.

17 GC10

General

Note 5

Government drawing shows note 5 repeated, with two different call outs.

Please revise to ensure proper action may occur

Note 5 is incorrectly repeated twice.

The second note 5 should be note 6, note 6 should be note 7, and note 7 should be note 8. The callouts are for the new work notes only. Note 5 and the call out is appropriate for the new work notes.

19 C-108 New

Work

Keynote 3 drawing notes, have a typos, please correct and confirm action item and location of 13' x 15' free standing building

Refer to Option 13 changes in location of accessory structure. See government marked up drawing C-

108, A-402, A-403, and EP-109.

21 CG50

Temporar y ASW

Tie-in/remova l

Government to confirm if an additional two week performance test will be required of the existing AWS when brought into service, prior to removing the temporary ASW pumps. Note 6 states to perform the reverse sequence to shut down temporary system connections.

Confirmed.

22 01 14

00.00

1.5.1.2

Yellow

Materials

Please confirm the extents of applicability of "yellow" and "orange-yellow", "Protective Clothing" under this section, particularly as it applies to typical construction PPE (i.e. vests, jackets, etc.)

Construction PPE such as safety vests/jackets, ear plugs, and safety goggles/glasses are allowed.

23 Please confirm any restricted areas, security islands, or other areas associated with this project that may require the use of escorts.

No escorts are required.

24 Government requires 3 week notice for escorts, confirm that escorts will be available 100% of the time provided 3 weeks notice is given and escorts are requested.

See response to PPI 23.

25 01 14

00.00 1.7

Government notes existing equipment and materials are to be protected during occupied building operations.

Government to provide a list of what materials, desks, chairs, office equipment etc. is anticipated to be covered, moved, or relocated during the duration of the project.

Equipment that requires protection during construction includes thermal and electrical equipment operating inside the facility.

28 Please identify any lighting that is considered to be "CIA Lighting", so that the proposers can quantify any potential temporary lighting necessary.

The lighting in this project is not part of enforcing security requirements for illumination of the CIA fence secure boundary and should comply with standard interior and exterior lighting requirements.

29 Please identify the specific ACI certification required for the "Lead

Foreman or Journeyman of the Concrete

Placing, Finishing, and Curing Crews" for cast in place foundations and/or flatwork.

The Lead Foreman or Journeyman must be an ACI certified Concrete

Flatwork Technician and Finisher.

30 How much ambient noise and visibility obstructions should be factored into the engineering of the fire alarm system?

Has the current design considered these factors?

Current design shows a general layout and location of fire alarm devices. It is the Contractors responsibility to determine the best location and characteristics for devices based on final equipment selections and layout.

31 Confirm if AACE 53R-06 will be used to determine if monthly NAS update will be accepted for payment or in lieu of this publication, please provide alternative standard or criteria.

Primavera P6 is required in accordance with specification 01 32

17.00 20.

32 Contract Documents include references for NFPA 101. Please confirm all applicable scope associated with this reference are detailed, described and/or identified in the plans and specifications and the design complies therewith.

Bid per plans and specifications.

33 Please confirm all existing pathways planned for installation and ductbanks depicted on this project have been evaluated for compliance with TIA-569 stipulations for bend, separation, etc.

Specification 27 10 00 and reference to TIA-569 is applicable to newly installed infrastructure only. Where identified for installation within existing infrastructure, compliance to this TIA-569 is not required.

34 Confirm the conduits sizes shown on the contract documents comply with the

TIA-569 requirements.

All conduits are sized minimum 3/4" in accordance with UFC standards and in compliance with TIA-569 requirements for horizontal installations.

37 E-002 Electrical

Demolitio n Notes

Note 5 on Electrical Demolition notes, appears to require additional notification and outage/shutdown approval. Will this notification/approval be required in addition to the outage requirement of 15 days? If so, what is the complete process for electrical outage and notification of approval?

Refer to specification section 01 14

00.00 22 for outage requirements.

38 Solicit ation

Pg 10

Factor 1, Corporate

Experienc e

13 We request that the Project Data Sheet page limit be expanded from 2 pages to 4 pages to allow our team to fully detail relevant project information.

Bid per RFP. Project Data Sheet shall not exceed two (2) pages.

39 00 10 00 The Bid Form Contains a column

"Option Line Item xxx" and then the item description lists an Option Item which does not match. When referenced on the contract drawings, please confirm that "Option Line Item" is being referenced. Please consider updating the item description to match the Option

Line Item.

Refer to the Memorandum Bidding

Notes P1112 released as part of the solicitation.

40 C-108 C-108 references Option 13, which does not existing on the Bid Form. Please confirm this is referencing Option 12.

Refer to the Memorandum Bidding

Notes P1112 released as part of the solicitation.

41 CG-

Several Plans reference the Temporary

ASW System as Bid Option 9. Please confirm if this should be Bid Option 8.

Refer to the Memorandum Bidding

Notes P1112 released as part of the solicitation.

42 Drawi ng D-

Keyno te #10

New work key note #10 on drawing D-

101 states to provide a bid alternative in option #3 to provide 70/30 copper nickel pipe. Bid option 3 states that this alternative is in lieu of all plastic piping.

Please confirm whether this option is just for HPPE and Aquatherm or PVC as well?

Bid Option 3 includes providing copper-nickel piping in place of

HDPE and polypropylene piping.

PVC piping is excluded.

43 Solicit ation

Factor 1 Corpo rate

Experi ence

Would the government consider allowing work performed as a subcontractor if the value of the work meets the pricing threshold/ complexity requirements as long as the contractor can also show prime experience on other projects included in the submission?

Bid per RFP. Experience shall be that of the Offeror performed as the Prime

Contractor. Experience of proposed subcontractors will not be considered.

Furthermore, experience of the offeror while working as a subcontractor will not be considered.

44 Standard

Form

The Bid Deadline of April 14th is short for a project of this complexity and may result in fewer GC bidders. Please consider extending the bid date by 2 weeks.

See Amendment for due date extension.

45 E-002 Electrical

Demolitio n Notes

Line item 3 - "…Electrical Contractor must visit the site prior to the submission of bids to become more familiar with actual conditions and extend of work" this investigation will require multiple visits, and per the specification required escorts to be made possible to access existing facilities. The project bid date will need to be pushed out to allow and accommodate site visits of existing facilities.

Bid per plans and specifications.

46 E-002 Electrical

Demolitio n Notes

Line item 1 - "Include in bid all costs for removal and relocation in the contract.

These cost must include work described in the contract documents with allowances for normal unforeseen difficulties when concealed work has been opened.." Government needs to define what the allowance carried should be valued at. Government to determine how many "normal occurrences" of unforeseen conditions should be carried in the bid.

Note will be deleted. Any unforeseen conditions will be handled in accordance with the FAR 52.236-2

Differing Site Conditions.

47 E-002 Electrical

Demolitio n Notes

Line item 4 - "Remove and/or relocate all existing electrical work which interferes with the new architectural and electrical layouts and schemes in full coordination with the architect's demolition plan" Government to confirm if additional items are to be removed/relocated or demoed not shown on the contract drawings provided for demolition/removal or relocation.

Bid per plans and specifications.

48 EP107 New

Work

Notes 1

Is there a time duration required between the shutdowns of Feeder 72-2A and 72-

23A? As in will both feeders be required to be in service before taking the second feeder down for a specific period of time?

Refer to sheet G-006.

49 AD00

General

Demolitio n Notes

Line item 1 states, "Contractor shall visit the site to verify and be fully aware of existing conditions prior to start of work.

Contractor shall identify all existing items of work schedule to remain or salvaged for reuse" Will the bid date be moved out beyond April 2026 to allow for multiple site visits and scope clarification?

See Amendment for due date extension.

50 AD00

General

Demolitio n Notes

Line item 1 states, "Contractor shall visit the site to verify and be fully aware of existing conditions prior to start of work.

Contractor shall identify all existing items of work schedule to remain or salvaged for reuse" Does the

Government not already have a list of which items are to be demoed or salvaged. The note is asking for the

Contractor to make those determination, which doesn't seem possible in the time provided.

Contractor to create a list and submit it to the COR for approval prior to the start of work.

51 C-102 New

Work

Note 35

Note states "By-pass connection and pig launching connection refer to Sheet D-

109" Sheet D-109 does not appear to have any additional information or details regarding these connections.

Please clarify or provide.

Drawing D-103 & D-107 updated to include bypass connection and pig launching location outside of building

52 C-102 New

Work

Note 28

Note directs contractor to install an ultrasonic flowmeter. Please provide specifications for the flowmeter being requested.

Flowmeter can be seen on D-601.

Refer to specification 40 60 00 for ultrasonic flow meter requirements.

53 C-102 New

Work

Note 4

Note states "PE coated 316 SS underground air pipe, power, and signal."

1. Confirm there shall be 3 separate pipes at this location.

2. What size pipe is required?

Refer to Detail A on sheet C-304.

54 C-102 Existing

48" ASW

Intake

Location/

Proposed outfall shown just below

Building

Detail callouts A. D-501 and A. D-502 as shown refer to an equipment pad detail and chemical injection nozzle detail respectively. It does not appear as though this was the engineers intent.

Please provide correct detail drawing references for the work at this location.

References have been corrected to D-

401 and D-402.

55 C-102 12" outfall just left of

Building

Detail callout A. D-503 refers to Fill

Pipe ID Labels. It does not appear as though this was the engineers intent.

Please provide correct detail drawing references for the work at this location.

Reference has been corrected to D-

420.

56 1361 23 64 26 2.4.5.a

.1

Spec calls for items to be skid mounted but drawing D-102 shows items separated out. Please confirm if this system needs to be “Turnkey” or parts to be shipped loose for a “Field-Install” by others.

Components may be skid-mounted or shipped loose for field installation by others.

57 1361 23 64 26 2.4.5.c Spec calls for 5hp pressure lubricated recip or rotary screw compressor and be

63 dBa or less, most screw units are 65-

70 dBa and recip units approx. 80 dBa.

Will a pressure lubricated reciprocating compressor equal to the ones already in operation at DD2 & DD3 be acceptable?

The specified maximum sound level has been revised to 70 dBA for the intake pump room. A pressure-lubricated reciprocating compressor equal to the units currently in operation at DD2 and DD3 is acceptable, provided the installed unit does not exceed 70 dBA. provided they fit in space provided.

58 1361 23 64 26 2.4.5.e Spec calls for TWO fast-acting pneumatic valves but there is only one valve & screen referenced on the drawings. Please confirm only ONE valve needs to be provided

One valve needs to be provided.

59 1361 23 64 26 2.4.5.f

.2.b

Spec calls for a lockable disconnect with type-J fusing. Is it acceptable to supply no disconnect on the panel?

Provide lockable disconnect with

Type J Flushing per specification.

60 1 01 75 00 Please provide this section as it is missing from RFP.

Bid per plans and specifications.

61 1 40 05

13.96

1.1 ASME B31.1 & 3 requirements are

documented in numerous parts of the P-

1112 specification but are not present in

Section 46 80 00 BWRO, 46 81 00

SWRO and 46 82 00 Immersed

Membrane System. Please confirm that

ASME B31.1&3 are not applicable to the membrane filtration system.

ASME B31.1&3 are not applicable to the membrane filtration system.

62 1 46 80 00 1.2 As the BWRO is installed downstream of the SWRO, please confirm the BWRO does not need to be suitable for seawater.

The BWRO treats SWRO permeate only and does not require seawater process design. However, as the units are located in a coastal/marine environment, materials must be suitable for external salt exposure.

Standard galvanized components and carbon steel fasteners are acceptable provided they have proven service experience in similar coastal

SWRO/BWRO installations and corrosive water will not be in contact with the galvanized components.

63 11 46 81 00 2.7.6 Please confirm if all Control Panels in membrane supplier's scope should be rated for NEMA 4X Versus NEMA 4

CS. NEMA 4X 316L Stainless Steel is the industry standard for marine and coastal environments. It provides superior resistance to chlorides and pitting compared to 304 stainless steel or carbon steel.

All Control Panels in the membrane supplier’s scope shall be rated for NEMA 4X, 316L stainless steel.

64 10 46 82 00 1.3B Barium: Please confirm units of these values. The expected concentration should be in ug/L.

Confirmed. The expected concentration should be in ug/L for

Barium.

65 19 46 82 00 2.3.2d The Permeate/backwash pumps Boerger casing is Duplex SS 2205 and not bronze. Please validate the MOC selection as this will impact the pump selection. Also Boerger rotary lobe pumps do not have shaft sleeves, as they do not have product wetted shafts.

Acceptable materials include Nickel

Aluminum Bronze (e.g., ASTM B148

C95800), Super Duplex Stainless

Steel, or Duplex Stainless Steel 2205.

Shaft sleeve is removed.

66 19 46 82 00 2.3.2d Please allow WEG as an approved motor vendor.

WEG may be submitted as an engineer approved equal.

67 27 46 82 00 2.10.3 a

NSF 61 certification/compliance is typically required in drinking water applications. Please confirm if NSF 61 certification is required. 316 SS is not recommended upstream of the BWRO.

Duplex 2205 or Nylon materials are typically utilized and recommended.

NSF 61 certification/compliance is not required for this project. For piping and components upstream of the BWRO, the use of Duplex 2205 stainless steel or approved Nylon materials is acceptable and recommended due to enhanced corrosion resistance in brackish water environments. 316 stainless steel shall not be used in these locations.

68 40 60 00 There are two sets of directions for controls documentation. Please clarify that Section 46 82 00 is applicable and not Sections 40 60 00.

Section 46 82 00 is applicable to the desalination equipment. Section 40 60

00 is applicable to the controls contractor integrating the desalinization equipment into the balance of plant controls.

69 22 40 60 00 2.10.3.

3.1

Help: Please clarify that these requirements are for the plant SCADA system and not the PLC system.

see response to PPI 68.

70 24 40 60 00 2.10.3.

System Access Control: Please clarify that these requirements are for the plant

SCADA system and not the PLC system.

see response to PPI 68.

71 D-106 Aeration Blower and Line Sizing:

Drawings and process indicate an outdated blower selection and line sizing was used. Blower to be rated for a max capacity of 492 ICFM @ 5.5psi. The air line from the blowers to the membrane tanks should be revised to 6" rather than 3". The motor will also now be 25

HP. Please note a flow switch and isolation valve will be on the blower discharge piping.

Drawings and process indicate an outdated blower selection and line sizing was used. Blower to be rated for a max capacity of 492 ICFM @

5.5psi. The air line from the blowers to the membrane tanks should be revised to 6" rather than 3".

The motor will also now be 25 HP.

Vendor Aerzen GM 15L model, kaeser, or approved equal. A flow switch and isolation valve will be on the blower discharge piping.

72 D-106 Permeate Ultrasonic Flowmeters: Please consider full bore flanged E&H Promag

Magmeters for this application (3-FIT-1-

002/3/4).

Ultrasonic flow meter will be used after the BWRO, as RO permeate is too low in conductivity for a magnetic flow meter. E&H Promag Magmeter is not accepted.

73 D-106 Common Permeate Piping to UF Break

Tank: Please revise the pipe size of the combined permeate piping from 6" to 8" to reduce line velocities to <8 fps.

The combined HDPE line from the

UF pumps to the UF break tank has been changed from 6-inch to 8-inch.

74 D-106 UF Drain Pumps Common Discharge

Magmeter: Please consider installing a magmeter on the common line of the UF

Drain Pump Discharge for pump protection and drain control.

Due to limited space, a meter will not be installed on the UF drain pump pipe. A meter (07-FIT01-001) is installed on the 12" common outfall pipe.

75 D-404 Air Ejector System: Air ejector panels will be supplied for the UF membrane trains but are not shown on the drawings.

Please clarify their location.

The air ejector system panels will be indicated on the drawings and to be located adjacent to the UF membrane trains inside the UF tanks room

(Room S).

76 D-409 Membrane Tank Raw Water Pipe Size:

Drawings show 6" line from raw water common header to individual membrane trains, except D-409 which shows 8".

Please revise the line size to 8".

10" PVC piping will be used for the common raw water line, and 6" PVC piping will connect the common header to the individual UF tanks, as shown on drawing D-406.

77 D-415 CIP Pump PSV: For the combined CIP system bi-directional pump, a PSV or pressure switch with safety relay is required on the PD pump discharge.

Please refer to the attached drawing.

A note added to drawing D-106: For the combined CIP system bi-directional pump, a PSV or a pressure switch with safety relay is required on the PD pump discharge.

78 D-416 CIP Tank: For the combined CIP system bi-directional pump, a PSV or pressure

See response to PPI 77.

switch with safety relay is required on the PD pump discharge.

79 Given the size, complexity, and technical requirements of this procurement, we requested a bid extension to May 21.

This additional time would support more complete and competitive proposals that provide best value to the NAVFAC.

Currently other ongoing NAVFAC procurements are the main focus of other vendors, and extending the bid date will provide for better vendor coverage and thus help ensure the best possible price for NAVFAC.

See Amendment for due date extension.

80 4 00 21 00 3(a)(1)

, item

The solicitation requires submission of financial statements as part of the proposal. Please confirm the acceptable method of submission for these documents. Specifically, can Offerors submit financial statements via a DoD-approved secure transfer method, or must all financial documents be submitted directly through PIEE as part of the proposal package.

Financial statements can be submitted with the Offeror's price proposal as requested in the RFP. Alternately, if required, Offeror's may submit financial statements securely via

DoDSafe. Financial documents submitted this way must still comply with the proposal due date as stated in the RFP. Late submissions will not be accepted.

81 Can NAVFAC provide to bidders current photos of key access areas within

Building 72 for pre-bid purposes. This would help with vendor coordination for vendors that were unable to make the site visit.

No.

82 solicit ation

Factor 1 Corpo rate

Experi ence

Would the government consider allowing the overall project size standard to be reduced to $5mil if there was still a single project requirement of $15mil as currently written. We feel this will add previously completed projects on island to qualify for this technical package.

Bid per RFP.

83 solicit ation

Factor 1 Corpo rate

Experi ence

Would the government consider altering the scope requirements to match those of the complexity part A to include industrial processes/ distribution, pumping stations or similar. We feel this will expand on relevant qualifying projects.

See Amendment 0003 for revisions.

84 Price

Propos al

CLIN

Option

Would the government consider providing a SF value to this 1LS line item for equal comparison of proposals.

Drawing A-101 indicates to correct deficiencies to the existing historic brick and appears to cloud the entire interior and exterior of Pump room S whereas A-

200 & A600 depicts a smaller portion of the exterior facade and interior walls. We don't see that the masonry wall paint was tested for anything other than asbestos on H-102. Does the government have

LCC results for this interior coating masonry wall? Will sponge jet be an acceptable method for removing coating from historic brick? If not, full removal of coating to allow repointing will be limited based on previous experience.

Bid per plans and specifications.

85 Price

Propos al

All It appears the memorandum has altered the price proposal form for multiple

CLINs. Will the government be issuing a new version of the price proposal form?

Utilize the originally provided Price

Proposal Form which remains valid.

The Memorandum - Bidding Notes which provided the clarification to coordinate the CLIN numbering employed in the drawings and specs with the CLIN numbering on the Price

Proposal Form. Example, include costs for the scope described on drawings as Option No. 2 in the Price

Proposal Form as CLIN 0002 (Option

No. 1), Option Item No. 1: North and

South Cooling Tower Permeate

Supply.

86 D-607 SH

182/226

The government has provided an abbreviated equipment list of major suppliers for the project. Would the government be willing to provide the full equipment list with all valves that have identifiable tag IDs listed in the process drawing set.

Bid per plans and specifications.

87 H-102 SH 8 of

The existing ceiling paint for the entire S room is in extremely poor condition.

There was no test result for this coating provided on H-102, nor was there a map provided for the samples collected in the saltwater room. Would the government provide this map corresponding to samples collected in B72 to bidders.

Would the government be able to provide sampling results for the ceiling paint to bidders. Are bidders to assume only the minimal amount of paint removal to facilitate new work/ penetrations in their proposals.

See H101 and H102 for sample locations and tables of sample results.

Sample results of ceiling paint in S room are not available. Assume ceiling paint to contain RCRA 8 metals. See 02 83 00.00 22 for handling requirements. Bid abatement requirements per plans and specs.

90 S-122 Detail E on Drawing S-122 shows details for concrete repairs. Note 1 states to assume 30SF of repairs for bidding purposes, what depth of repair should be assumed for bidding purposes?

Additionally confirm that no supplemental rebar is required in these repair areas.

For bidding purposes, assume repair depth of less than or equal to 3 inches.

Confirmed, no supplemental rebar is required in these repair areas (existing rebar to remain).

91 H-102 Drawing H-102, which is indicated as

Hazardous Material - Plan 2 of 2, references Drawing H-101. There is no drawing H-101 for Hazardous Material

Plan 1 of 2, please provide drawing H-

101.

H-101 has been provided in amendment.

93 5 00 21 00 Factor

1 -

Corpo rate

Experi ence

The solicitation limits Factor 1 –

Corporate Experience to two (2) pages.

Given the complexity and scope of relevant project experience necessary to demonstrate qualifications for this project, we request NAVFAC revise this limit to four (4) single-sided pages, or two (2) double-sided pages, to allow for more complete descriptions of project scope, resiliency features, performance outcomes, and overall relevance.

Bid per RFP. Project Data Sheet shall not exceed two (2) pages.

94 With current volatility in commodity pricing - would NAVFAC consider adding a Economic Price Adjustment form for items of significant quantity as part of this proposal? Without inclusion of an EPA contractors will price in potentially significant amounts of escalation into the base price.

Recommend concrete, rebar, various sizes of piping, tanks, wire, conduit, and premanufactured building all for potential inclusion into the EPA.

No. Please bid per RFP.

95 Attachme nt H

Price form attachment H includes line items 001A, B, C for various abatement items in respective locations. Please confirm contractor is to include in these items only abatement as specifically indicated or shown on contract documents.

Bid per plans and specifications.

96 Attachme nt H

NAVFAC frequently includes unit price line items on the bid form for abatement of typically encountered hazardous materials to allow for pricing in the event additional quantities beyond indicated are encountered. Would NAVFAC consider adding similar bid items to this proposal?

Bid per plans and specifications.

98 V-104 Drawing V-104 has a note indicated a callout of an overall boundary of historical areas. However, no overall boundary is established. Please clarify what area of the project will require onsite archeologists while excavation is proceeding.

See redlined drawing V-104 with dashed red polygon defining the boundary/limits that require on-site monitoring, documentation, and reporting of excavation activities.

The on-site monitoring, documentation, and reporting must be performed by a qualified archaeologist and in accordance with the approved work plan in accordance with the specifications.

101 01 11

00.00 22

1.2.2.f Significant portions of the work are within the operational buildings. If the intent is that escorts are needed to perform work in areas such as Rooms S, M, and C in Bldg 72 and within Building

242 - please confirm escorts will be available during all workdays in the indicated hours of available work, as lack of escorts would stop work and impact the project schedule. Or please provide clarity on areas where escorts are anticipated.

See response to PPI 23.

103 Due to a very recently submitted bid at

PNSY for significant project in the same work area, we are requesting extension to the proposal due date to May 21st as many of the same vendors will be involved in pricing this project and additional time will provide for better pricing for NAVFAC.

See Amendment for due date extension.

104 46 82 00 1.1.2 Please clarify Contractor "design" responsibility listed herein. While many of these items may not be designed by the Section 46 82 00 Vendor, the design for many, if not all appear to be completed as part of the project design by the DOR.

The contractor shall provide design only where explicitly required in the contract or vendor specifications. All other systems and components shall be installed per the DOR’s design.

109 46 82 00 3.2.4 Is the Contractor required to maintain bonds and insurance through the 1-year period contemplated by Bid Option 7.

Yes, bonds are required to be held through the duration of the warranty period.

110 46 82 00 3.2.4 If Bid Option 7 is exercised, will the

Government provide a work location (i.e.

office/desk/other) for the Lead Plant

Operator or is this to be provided by the

Contractor?

Government will provide work space with desk for Lead Plant Operator.

112 Bid

Form/Dra wings

The bid option numbers as identified in the drawing set do not match the bid options as identified in the proposal form. Ex. Drawing C-107 identifies the work as "Option 6" whereas the work on the proposal form is for "Post construction completion follow-on services. Please correct the proposal form to match the option work as shown on the drawings.

Refer to the Memorandum Bidding

Notes P1112 released as part of the solicitation.

113 C-105 New work note 1 instructs contractor to construct a permanent bulkhead at connection to building 72 and to refer to

S-310. Drawing S-310 does not show anything relating to a bulkhead. Please advice.

Reference has been corrected to S-

308. See memorandum - Bidding

Notes.

114 01 11

00.00 22

1.2.2, a

Please clarify extent and locations of desired "temporary partitions"

This sentence has been removed from specification.

115 01 14

00.00 22

1.8.2 Please identify all items within the

project identified as "Critical

Infrastructure"

This part of the specification has been removed.

116 01 14

00.00 22

1.16 Please confirm that "Only Contractor

company-owned vehicles will be allowed to park on the Portsmouth Naval

Shipyard" and the Jamaica Island parking lot is not available for contractor

POVs.

Bid per plans and specifications.

117 01 30

00.00 22

1.4.2 Please advise if the Project Manager is

required to be "on the job-site at all times during the performance of the Contract work.", similar to the Superintendent.

This is not currently stated as a requirement.

Bid per plans and specifications.

118 01 30

00.00 22

1.4.2.2 It is stated that "Approval of the Project

Manager by the Contracting Officer is required prior to the start of construction.", however this section does not identify minimum qualifications for this approval to be based upon or duties to be performed by the Project Manager.

Please advise.

Qualifications not require for contractor's project manager.

119 01 30

00.00 22

1.6 This section states that certain

Preconstruction Submittals must be submitted 30-calendar days prior to the

Preconstruction Meeting.

This section states that the

Preconstruction Meeting must take place within 45-calendars days from the Notice to Proceed.

It is not practical to have the Accident

Prevention Plan and the Indoor Air

Quality Management Plan created within

15-days of the Notice to Proceed.

We recommend that the requirement be modified such that these Preconstruction

Submittals must be approved prior to the start of on-site construction.

Specification section 01 30 00.00 22 will be revised to say the

Preconstruction meeting must take place within 60 calendar days from receiving the Notice to Proceed. The

Accident Prevention Plan and the

Indoor Air Quality Management Plan must be submitted to the Contracting

Officer 15 calendar days prior to the

Preconstruction meeting.

120 D-102 Shows A and B Section Arrows directing to page D-310. There is no page D-310.

Is is supposed to direct to D-301?

Drawing has been revised to direct to

D-301.

121 01 30

00.00 22

1.6 This section states that certain

Preconstruction Submittals must be submitted 15-calendar days prior to the

Preconstruction Meeting.

This section states that the

Preconstruction Meeting must take place within 45-calendars days from the Notice to Proceed.

It is not practical to have these nine items created within 30-days of the

Notice to Proceed.

We recommend that the requirement be modified such that these Preconstruction

Submittals must be approved prior to the start of on-site construction.

Specification section 01 30 00.00 22 will be revised to say the

Preconstruction meeting must take place…