This is Section 01 14 00 "Work Restrictions" from a construction solicitation for a Special Operations Forces SDVT2 Operations Support Facility at JEB Little Creek-Fort Story, VA. The document outlines key operational requirements and restrictions for contractors working on the project.

The specifications detail working hours (7 a.m. to 3:30 p.m.), procedures for work outside regular hours (requiring 15 days advance notice), and utility cutover requirements. Contractors must familiarize personnel with activity regulations including safety, fire, traffic and security protocols. Additional requirements include: submitting a list of contractor/subcontractor contact information, following a no-smoking policy within and outside buildings except in designated areas, maintaining clear company identification on all equipment and vehicles, and coordinating utility interruptions (water, sewer, electric, HVAC, etc.) for after-hours, weekends or holidays. The document references FAR 52.204-2 Security Requirements and Alternate II as applicable contract clauses.

View the file

Other files

File Type Posted
Attachment D - P909 Price Proposal Form R3.docx DOCX document
24R2862 Amendment 0014.docx DOCX document
Attachment D - P909 Price Proposal Form R2.docx DOCX document
P909 Amendments Index.pdf PDF
24R2862 Amendment 0013.pdf PDF
Attachment B Wage Determination.pdf PDF
Attachment X - Lithium Battery Current Quantities.pdf PDF
24R2862 Amendment 0012.pdf PDF
24R2862 Amendment 0011.pdf PDF
W_LIttle Creek Oneline.pdf PDF
V_Secured Area Second Floor.pdf PDF
24R2862 Amendment 0010.pdf PDF
24R2862 Amendment 0009.pdf PDF
24R2862 Amendment 0008.pdf PDF
1704761-CS101.pdf PDF
DOD_Anti-ram_Vehicle_Barriers_September_2024.pdf PDF
6_ESR_A20.pdf PDF
---5_RR_G209 WOMENS TOILET.pdf PDF
24R2862 Amendment 0007.pdf PDF
Part 2 General Requirements.pdf PDF
5_RR_D105_MAINTENANCE RM-O2 SAFE.pdf PDF
5_RR_D106_MAINTENANCE RM.pdf PDF
5_RR_D109_COMPRESSOR ROOM.pdf PDF
3_site_analysis.pdf PDF
5_RR_D104_BATTERY STORAGE.pdf PDF
NAVFAC High Performance and Sustainable Building Checklist GOALS.pdf PDF
5_RR_G111_MENS TOILET.pdf PDF
6_ESR_D20.pdf PDF
---5_RR_G207 MENS TOILET.pdf PDF
6_ESR_D30.pdf PDF
5_RR G108 WOMENS TOILET AND SHOWER.pdf PDF
Part 3 Chapter 1 changes.pdf PDF
5.0_Room.Requirements_Amendment.0006.pdf PDF
SPACE TABULATION.23Oct2024xlsx.pdf PDF
U_Telecommunication_Point_Of_Connection.pdf PDF
Spec.ESR_Amendment.0006.pdf PDF
24R2862 Amendment 0006.pdf PDF
24R2862 Amendment 0005.pdf PDF
24R2862 Amendment 0004.pdf PDF
24R2862 Amendment 0003 Site Visit Log.pdf PDF
24R2862 Amendment 0002.pdf PDF
Attachment J - PTS_SECTION_Z10.pdf PDF
Attachment I - 1704761 CONTINUATION SHEET Ammendement 0002.pdf PDF
ATTACHMENT G - SECNAV FORM 5512.pdf PDF
ATTACHMENT H - ONE DAY PASS FORM.xls XLS spreadsheet
24R2862 Amendment 0001.pdf PDF
Attachment A- R18_P909_RFP Plans_23.12.11 SITE PLAN.pdf PDF
24R2862 SOF General Requirements.pdf PDF
Attachment C-Pre-Proposal Inquiry Form.xlsx XLSX spreadsheet
Attachment F - JA ML-22-02 Class FRCS Standardization.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SDTV2 OPERANTION SUPPROT FACILITY 24P0909AMMENDMEN

SECTION 01 14 00

WORK RESTRICTIONS

11/22, CHG 3: 08/24

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

SD-07 Certificates

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.2.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Working Hours

Regular working hours will consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., , , excluding Government holidays.

1.2.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving

SECTION 01 14 00 Page 1

SDTV2 OPERANTION SUPPROT FACILITY 24P0909AMMENDMEN

the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.2.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and are considered utility cutovers pursuant to the paragraph

WORK OUTSIDE REGULAR HOURS.

1.3 SECURITY REQUIREMENTS

Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply:

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --