24R2862 Amendment 0008.pdf
PDF 301 KB Posted
- Solicitation number
- N4008524R2862
About this file
This is Amendment 0008 to solicitation N4008524R2862 for the P909 SOF SDVT2 Operations Support Facility at JEB Little Creek-Fort Story, Virginia Beach, VA, extending the proposal due date to January 17, 2025 at 2:00PM EST.
The amendment makes several key changes including: incorporating a revised price proposal form, updating drawings and RFP information, providing PPI responses, adding DOD anti-ram vehicle barriers requirements, updating the VA Little Creek Approved CJ&A DDC document, and modifying site layout specifications. Notable changes include revising the heavy duty concrete laydown area requirements from the west to east side of the building with updated minimum square footage requirements, clarifying perimeter fencing requirements (7-foot high fence with 1-foot 3-strand barbed wire outrigger), modifying RF shielding requirements for specific rooms, and providing responses to multiple technical questions regarding telecommunications, cybersecurity, HVAC systems, and other building systems. The amendment includes detailed responses to over 100 contractor questions covering various aspects of the facility design and construction requirements.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 28
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
12/20/2024
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
See Item 6
8. NAME AND ADDRESS OF CONT RACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
N40085-24-R-2862
X 9B. DATED (SEE ITEM 11)
09/17/24
10A. MOD. OF CONT RACT /ORDER NO.
10B. DAT ED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENT S OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of th is amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15 and returning 1 copies of the amendment; (b) By acknowledging receipt of th is amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT
TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of th is amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitat ion and th is amendment, and is received prior to the opening hour and date specified.
12. ACCOUNT ING AND APPROPRIAT ION DAT A (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICAT IONS OF CONT RACTS/ORDERS.
IT MODIFIES THE CONT RACT /ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONT RACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED TO REFLECT THE ADMINIST RAT IVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORT ANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N4008524R2862 P909 SOF SDVT2 OPERATIONS SUPPORT FACILITY, JEB LITTLE CREEK-FORT STORY, VIRGINIA
BEACH, VIRGINIA
Contract POC: Demetrice Jenkins, demetrice.jenkins2.civ@us.navy.mil
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONT RACTING OFFICER (Type or print)
TEL: EMAIL:
15B. CONT RACT OR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNIT ED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
EXCEPTION TO SF 30
STANDARD FORM 30 (Rev. 11/16) APPROVED BY OIRM 11-84 Prescribed by GSA
FAR (48 CFR) 53.243
N40085-24-R-2862
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 0008
The purpose of this amendment is to incorporate the following:
1. Extend the proposal due date
2. Continuation Sheet to update drawings and RFP information
3. Provide PPI Responses
4. DOD_Anti-ram_Vehicle_Barriers_September_2024 (attached separately)
5. VA_LittleCreek_ApprovedCJ&A_DDC_Exp20291101_Redacted (attached separately)
6. Attachment D – P909 Price Proposal Form_R1 (attached separately)
7. 1704761-CS101 (attached separately)
1. The proposal due date is extended from 07 January 2025 to 17 January 2025 at 02:00PM EST.
2. Continuation Sheet
DRAWINGS:
RFP - PART 6, ATTACHMENT A DRAWINGS
DELETE Civil engineering drawing sheet… P909 SOF SDVT2 OPS SUPPORT FAC-SITE PLAN – SHEET
CS102
RFP - PART 6, ATTACHMENT A DRAWINGS
REPLACE Civil engineering drawing sheet… P909 SOF SDVT2 OPS SUPPORT FAC-SITE PLAN – SHEET
CS101 file name: 1704761-CS101 transmitted with this amendment
RFP:
RFP - PART 3, CHAPTER 3.0 SITE ANALYSIS, 3.2.4 SITE LAYOUT
DELETE “Provide a heavy duty concrete laydown area on the west side of the building (100 ft. by 130ft.)” with “Provide a heavy duty concrete laydown area on the east side of the building (min. requirement 3239 SY).
RFP - PART 3, CHAPTER 3.0 SITE ANALYSIS, 3.2.4 SITE LAYOUT
REPLACE “Provide a heavy duty concrete laydown area on the west side of the building (100 ft. by 130ft.)” with “Provide a heavy duty concrete laydown area on the east side of the building (min. requirement1670 SY).
RFP - PART 6, ATTACHMENTS
REPLACE – Attachment L – VA Little Creek Approved CJ&A DDC EXP 20241031 with VA Little Creek
Approved CJ&A DDC EXP 20291101 transmitted with this amendment.
3. Provide responses to the following PPI’s: 416, 430, 434, 437, 439, 446-447, 454, 459, 463, 481, 492, 505-506, 509-512, 517-520, 525, 527, 545, 557-568, 570-574, 576-586, 588-590, 593-612, 614-622, 624-641, 643
PPI
Reference Question Response
Page Section Para
416 Amend
005 page
Part 3
Chapter 6 Section
G20
G204001 and
G204004
Part 3 – Chapter 6, ESR G20, Section G204001 Fencing & Gates is where it states “Not Used.”
Section G204004 Security
Structures is also noted as “Not
Used. "In Part 4 – Section G20, Paragraph G204001 specifies chain-link security fence and gates. Part 4
– Section G20, Paragraph G204004 discusses security structures (active and passive vehicle barriers), but states “Where identified for project elsewhere in this RFP…”.
Part 3 and Part 4 of the RFP are in conflict if security fencing is required or not and where it is required as the site drawing does not indicate any fencing. Please clarify if security fencing and gates are required around this site to limit access to parking lot, building, and laydown yard.
Perimeter fencing is required. Base bid for fencing is 7 foot high fence with 1 foot 3 strand out rigger barb wire, chainlink, polyvinyl coated, 9 gauge steel fabric ties.
Refer to UFC 4-022-03 drawing UFC 701 for more detail and UFGS section 32 31
13.53. For bid option with deadmen and
anti crash barriers refer to this UFC and
UFGS as well along with approved DOD anti-ram vehicle crash barriers see attachment in Amendment 8. Security fencing and gates are required around the perimeter of the building and laydown areas.
430 PDF Page
17-18---
AND---
PDF Page
SECTIO
N 01 30
00;
subsectio n 1.7
PRECO
NSTRU
CTION
MEETIN
G ---
AND---
Part 3, Chapter
2, Section
2.3.6
Cybersec urity
The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to:
daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, Confirm that the ISSE to be provided by the Control
System Integrator Contractor is to be present at the
PRECONSTRUCTION
MEETING and that the ISSE must meet DoD 8140.03, formerly known as DoD
8570.01-M, the Department of Defense (DoD) instruction that relates to information systems security (ISSE).
Confirm that the ISSE must demonstrate acceptable qualifications of DOD Work
Role ID: 462 Control
Systems Security Specialist, certification vendor information for GICSP, or its equivalent in other DOD
8140 certification recognition requirements applicable to
IAM/IAT Level 2 or higher for the duration of the contract.
The ISSE will be the contracting agency hired under contract to perform the duties designated for Steps 1 through 3 of the
RMF process.
prosecution of the work, government acceptance, final inspections and contract close-out.
Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.----
AND----
"Contractor to provide an
Information System
Security
Engineer
(ISSE)(Contra ctor)"
434 PDF Page
Part 3, Chapter 2, Section
2.3.6
Cybersec urity
Review authorization Strategy for each system.
Per UFC 4-010-06, 10 OCTOBER
2023, Chapter 1, Section 1-2 PURPOSE AND SCOPE, which states: "This UFC does not implement the RMF and does not address anything beyond the design of the system. Use of this UFC does not result in an ATO under the RMF process but will provide a system that is more capable of receiving an
ATO than a system not designed in accordance with this UFC."
Therefore, any Authorization to
Operate as per the Department of
Defense RISK MANAGEMENT
FRAMEWORK are the responsibility of the Navy, NAVFAC Chief of Civil Engineer and the Functional Authorizing Official (FAO) which has jurisdiction for authorizing all Navy ashore control systems and any work beyond the application of the
Cybersecurity Design Process as stated in UFC 4-010-06 for the purposes of obtaining any ATO is beyond this scope. The FAO carries out the responsibilities of
Authorizing Official (AO) as required in UFC 4-010-06, Cybersecurity of Facility-Related
Control Systems. FAO reserves the
Correct, the 4-10-06 guidance does not provide the RMF requirements for the package to achieve or invest in an ATO.
That’s where the UFGS 25-5-11 comes into play, which does provide the necessary background for materials and requirements to achieve and ATO. 25-08-
11 guidance further gives the contracting agency the requirements that are specific to the scope of work necessary to complete the required deliverables for ATO submissions.
right to accept or deny risk of a control system.
437 PDF Page
Part 3, Chapter
2, Section
2.3.6
Cybersec urity
"The FLS shall be designed for integration into the existing base-wide front-end monitoring system."
For the application of UFC 4-010-
06 Cybersecurity of Facility-Related
Control Systems design process, confirm that (U)NAVFAC FAO
Fire and Life Safety (FLS)
Supplement Final v1_CISO
FAODR Signed.pdf for all FLS will be used and that therefore a separate
UFGS 25 05 11.00 will not be required for any new FLS being connected to an already existing basewide system. (Reference Naval
Facilities Engineering Command
(NAVFAC) Fire and Life Safety
(FLS) Supplement, Authorization
Supplement Version 1.0, 13 July 2020.
A separate UFGS 25 05 11 for FLS is typically not needed.
439 PDF Page
SECTIO
N 01 33
10.05 20, subsectio n 1.11.5
Cybersec urity
Basis of
Design
Provide a single submittal indicating criteria and describe requirements for integrating cybersecurity in the design and construction of the facility-related control systems in accordance with UFC 4-
010-06. The basis of design must describe specific guidance for control systems with the assigned
Confidentiality
, Integrity and
Availability
(C-I-A) impact ratings and shall list the security controls with recommendati ons and justifications for future tailoring of the
Prior to the onsite CDW, it shall be assumed that the CIO4 Point of
Contact for MIDLANT will provide the required USN RMF Information
System Categorization Forms v1.2 for each of the following, identified, FRCS for this project: ESR D10, CONVEYING (ELEVATOR), ESR
D20, WATER DISTRIBUTION
AND COMPRESSED AIR
SYSTEMS, ESR D30, HVAC
(Utility Management and Control
System - UMCS), ESR D30, DDC and BUILDING AUTOMATION
SYSTEMS, ESR D50,
ELECTRICAL POWER AND
LIGHTING SYSTEMS, ESR D50,
INDUSTRIAL CONTROL
SYSTEMS, ESR G30,
MECHANICAL SITE UTILITIES
AND ADVANCED METERING
SYSTEMS, ESR G40,
ELECTRICAL + COMM SITE
UTILITIES AND ADVANCED
METERING SYSTEMS
CIO2 to provide the categorization forms, however, they are no longer required for step 1 of the RMF process. We still utilize them for assistance in filling information in eMASS, however they are not required for the RMF process.
The FRCS for all systems under ESR
D10,D20,D30 are owned by NAVFAC.
The FRCS for all systems under ESR G30 and G40 are owned by NAVFAC UEM.
security control set.
446 834 Part 3, Chapter
ESR F10 Please confirm the level of Forced
Entry Protection required for this project.
Forced Entry LOP is defined in the SEPA dated May 2023 (CUI) Provide level of protection to provide at least 30 minutes of delay as define in UFC 4-026-01.
447 N/A Part 6, CD102
N/A A laydown/work area around
Building 3814 will be needed to complete demolition activities.
Please confirm the area/limits of work that will be available to the
Contractor for this scope.
A laydown area will be identified during the charette.
454 N/A Amendm ent 0005, Bidder
Inquiry
Response
#13
N/A The Government's response to
Bidder Inquiry #13 does not address the question. Please review and respond.
The facility is within a controlled perimeter of JEB Little Creek Installation.
459 442, CS102
Part 3, Chapter
3.2.4 3.2.4 Site Layout states
"Provide a heavy duty concrete layd own area on the west side of the buil ding (100 ft. by 130 ft.)". Part 6
CS102 SITE PLAN shows this area located to the east of the building adjacent to Intercove Road. Please confirm the conceptual site layout on CS102 supersedes the description in Chapter 3.
Desired layout is to be on the east side of the building. Dimensions for the laydown area has been updated as well to match
BFR laydown requirement of 3239 SY for the laydwon area. (See amendment 0005)
The laydown area can be separated into smaller laydwon areas to accommodate the site. Attachment A is provided for conceptual reference only. Designer of
Record (DOR) must design a site plan that meets the RFP and UFC requirements.
463 9 Part 3, Chapter
2.3.5 2.3.9 Antiterrorism Criteria includes the statement, "Develop the site based on the requi rements of UFC 4-010--
01 and JEB Little Creek – Fort Stor y command operations orders." The referenced JEB Little Creek – Fort Story command operations orders cannot be located within the RFP criteria provided. Please provide a copy of this document.
Delete JEB Little Creek – Fort Story com mand operations orders. Add "Develop the site based on the requirements of UFC
4-010-01 and in accordance with Design
Criteria as defined by SEPA dated May
2023 (CUI). For bidding purpose assume
MEDIUM level of protection unless otherwise indicated or required.
481 N/A Amend
0005, Bidder
Inquiry
#59
N/A Follow-up to previous RFI (Bidder
Inquiry #59)
Previous: "Please provide Enclosure
009 as referenced in RFP section
G401003 to identify points of connections of primary electrical loop."
Amendment 0005, Government response to Bidder Inquiry #59 states "Enclosure 009 does not exist, utility plans are located in part 6 attachment A and the locations of the SF6 pad mounted switchgear must be coordinated with existing utilities and with government during design." We request the government to provide direction on the location of the switches for bidding purposes as the locations have substantial financial impact. Please provide
Enclosure 009 or a Utilities plan showing the intended locations for the new pad mounted switchgear.
See Amendment 0006, continuation sheet.
Radial loop is no longer needed. Tie into existing switch. The location of switch is at the coordinates 36.918883, -76.166191.
492 Part 3 Ch
6 /
D2020
Domestic
Water Flow
Distribution
The RFP requires a flow test be performed to determine domestic water system requirements. Is a preliminary flow test available to determine whether a booster pump is required for the domestic water supply?
A flow test is required to be performed by the selected bidder.
505 9 Part 3 Ch
3.2.4 3.2.4 Site Layout directs the
Contractor to "Provide a heavy duty concrete laydown area on the west s ide of the building (100 ft. by 130 ft.
)." Please clarify that the desired layout area is to be located on the east side of the building in accordance with the Attachment A -
Site Plan and Bubble Diagram.
Desired layout is to be on the east side of the building. Dimensions for the laydown area has been updated as well to match
BFR laydown requirement of 3239 SY for the laydown area. (See amendment 5) The laydown area can be separated into smaller laydown areas to accommodate the site. Attachment A is provided for conceptual reference only. Designer of
Record (DOR) must design a site plan that meets the RFP and UFC requirements.
506 13 Part 3 Ch
2.6.1 2.6.1 Blast Related Design and
Mitigation - please clarify the necessary levels of blast mitigation that will be required to be implemented and upheld in accordance with the Security
Engineering Planning Assessment
(anticipated to be completed in
January 2023).
Refer to SEPA performed on May 2023
509 13 Part 3 -
Ch 3
Basis for
Bidding
3.2.13.1 -
Unsuitable soils
Under the Basis for Bidding, the 6th item on the list says that
"Excavated onsite soils are unsuitab le for reuse as backfill and fill in str ucture and pavement areas and may only be reused as common fill. Imp orted Backfill and Fill Material mus t be used in all structure and paveme nt areas and for utility and foundatio n excavation backfill." The quantity of onsite soils that are unsuitable is unknown. Please provide a unit price line item on the bid form with a predetermined quantity.
See Amendment 0008, Revised
Attachment D- Price Proposal Form
510 13 Part 3 -
Ch 3
Basis for
Bidding
3.2.13.1 -
Sutcharge
Under the Basis for Bidding, the
10th item on the list says that
"Preloading or surcharge will be required for mitigating excessive long-term consolidation settlement assoc iated with site grade increase." If a surcharge or preloading of material is required, we need to know how thick the surcharge material needs to be and how long the settlement period needs to be for the surcharge before it can be removed.
See Amendment 0008, Revised
Attachement D- Price Proposal Form
511 14 Part 3 -
Ch 3
Basis for
Bidding
3.2.13.1 -
Dewatering
Under the Basis for Bidding, there is an item on the list says that
"All construction dewatering effluen t is to be containerized, treated, and tested prior to onsite discharge in ac cordance with the prescriptive 01 57
19 Specification." There is no way of quantifying the amount of water that will need to be containerized, treated, and tested prior to onsite discharge. Please provide a unit price line item on the bid form with the quantity of water in gallons that is to be treated.
See Amendment 0008, Revised
Attachment D- Price Proposal Form
512 5 Part 3 - Ch 3
3.1.2 In section 3.1.2 under Man Made
Conditions, it says there is Known
Contamination.Based on the finding s of the preliminary Geotechnical Si te Characterization (Ref. Part 6 Atta chments), contaminated soil and gro undwater were encountered at the pr oject site. There is no way of quantifying the amount of contaminated soil and groundwater that will be encountered on the project site. Please provide a unit price line item for both soil and water on the bid form with a quantity for each.
See Amendment 0008, Revised Attachment D- Price Proposal Form
517 Bid Price
Schedule
Price Proposal form calls for Bid
Option 5 calls Access Flooring.
However, no where in there RFP specifically says which rooms are to recieve access flooring. Please confirm which rooms would recieve access flooring for in Bid Option 5 on the Price Proposal form.
Access flooring / Elevated tiered flooring is anticipated in room X210 - N2 Joint
Operations Center (JOC)
518 7 Part 3 Ch
2.3.2.7 2.3.2.7 Radio Frequency Shielding
Mitigations references Part 5, Specification section
13 49 20.00 10. This specification section has not been provided in the
RFP. Please provide section 13 49
20.00 10 or delete the reference from the RFP.
Delete Refrence to Specification 13 49 20
00 10. Design to latest ICD/ICS standard.
519 7 Part 3 Ch
2.3.2.7 Please clarify the RF Shielding
testing requirements and provide the frequency range that the RF Shielding must be tested to.
40-60 db of RF attenuation. For testing requirements coordinate with CTTA.
520 PART 3
CHAP 6
/ ESR D1
0 -
UMCS notes a CJ&A for DDC systems that expired on 10/31/24.
Please provide updated J&A if one exists.
See Amendment 0008, updated CJ&A is attached.
525 Part 3 -
Chapter 2
- Page 9
2.3.5 Antiterrorism
Criteria
Please confirm for the AT/FP design, facility will be considered as without controlled perimeter, even though facility is well within the
JEB controlled entry/ perimeter.
See response to PPI#454
527 Part 3 -
Chapter 2
- Page 9
2.3.5 Antiterrorism
Criteria
Please confirm if the AT/FP design will still need to comply with
Appendix B of UFC 4-010-01 as per the section or Chapter 3 can be utilized
Confirmed. See responses to PPI#15
Amendment 0005 and PPI#463
545 7; 3 Part 3 Ch
2; Part 3
Ch 6; 5.0
Room
Require ments
2.3.2.7;
F104001
Please clarify the continuous architectural RF shielding barrier requirements for the second level
CAA and SAA. Part 3 Ch 6 states that the RF shielding "foil must be run from floor deck to roof deck and overlapped minimum 6” onto the de cks." Per 5.0 Room Requirements for CAA and SAA second level rooms, B1010 Floor - RF Shielding and B301090 Other Roofing - RF
Shielding, contractor is to "Provide
RF Shielding and required RF mitig ations within entire second floor ass embly, and
Provide RF Shielding & required R
F mitigations within all second floor roof assemblies."
Confirm if continuous RF foil is to be applied onto the entire 2nd floor metal deck and 2nd floor roof metal deck, or if a minimum 6" overlap of the RF Shielding foil onto the floor and roof metal deck is compliant.
Only a portion of the second floor is required to be shielded. Shielding standards and certification requirements have been provided/ referenced.
557 PDF page
Section
5.0
Room
Require ments, C101-
Commun ications
Closet
SPECIAL
REQUIREME
NTS: Provide
(4) full-sized racks for
NIPR, SIPR,
GREY
Network & (1) additional
Rack for capacity.
"FF&E
INFORMATI
ON FOR
COORDINAT
ION: FF&E
and AV
Equipment will be funded seperately as a midification to the construction contract.
Infrastructure to support all
FF&E and AV must be included in the construction contract.
Contractor's
Interior
Designer must validate and determine
FF&E
requirements on in-depth interviews with Activity at Concept
Design
Workshop."
Required Information From
Government is needed. Government
POCs will need to determine if this space is designated as a
"Communications Closet" instead of a "Communication Room during the
"in-depth interviews with Activity at Concept Design Workshop:"
1. NIPR, SIPR, GREY etc.
requirements listed but no Tempest requirements provided.
2. Space requirements between differing networks, (NIPR, SIPR, GREY etc.) is not identified.
3. Cooling Requirements for
Infrastructure listed not identified, (e.g., Secondary HVAC?, AHUs?
etc.)
4. Separate power circuit requirements with back up power not identified.
5. Double Door requirements/Access Control
Requirements Not identified.
6. Confirm the four racks are as listed: one rack for NIPR, one rack for SIPR, one rack for GREY and one additional rack for capacity.
1.All network should follow the CTTA.
2.Follow CNSAM TEMPEST/1-13 for separation
3.Contractor to provide HVAC affording to UFC 3-580-01 4.Provide UPS in each server rack enough capacity for 10minutes to allow enough time for back up generator to turn on.
5.Coordinate with security and CTTA. All telecom space to have a minimum of a keypad for entry.
6.Correct
558 PDF page
Section
0.1 .33
00.05 20
Preconstructio n Submittals
Network
Analysis
Schedule
(NAS)
Confirm that the "Network Analysis
Schedule" refers to the provision of a comprehensive view of how the project will be executed, including key milestones, potential critical paths, and estimated completion dates, for review and approval by the project owner and is NOT any
Network Analysis Schedule of point connections or riser diagrams that might refer to any Authority to
Operate (ATO) submittal requirements, as any Authorization to Operate as per the Department of
Defense RISK MANAGEMENT
FRAMEWORK are the
Confirmed responsibility of the Navy, NAVFAC Chief of Civil Engineer and the Functional Authorizing
Official (FAO) which has jurisdiction for authorizing all Navy ashore control systems and any work beyond the application of the
Cybersecurity Design Process as stated in UFC 4-010-06.
559 1. Is RF shielding on the 1st floor limited to Rooms C104 N6 EKMS
Vault, M112 Medical Office, M112
Medical Office? Or not required?
It’s requested in the Room Requirements but references to the second floor.
N6, N2, Command, N3, TU 1-4, G206 and divers room must have RF shielding.
T202, T201, G201, G20, S201, A201,A203,A202 do not require RF shielding.
The building layout is preliminary and is subject to change. RF shielding can be added to rooms that do not require them in order to keep continuous RF shielding as needed.
560 2. Clarify if the 2nd floor Secure
Area requires RF shielding barrier
“6-sided Box” (floors, walls, roof/ ceili ngs) or each room in the Secure
Area should receive RF shielded barrier?
Each room does not need individual RF shielding. A 6 sided box style RF shielding that encompass the entirety of the room is sufficient
561 3. Clarify if the entire 2nd floor
Non-Secure area requires the RF shielding? Is RF shielding also required in the partitions separating the rooms? RFP calls for the RF shielding in the Non-Secure
Corridor G206, Men’s Toilet G207, Janitor Closet G208, Women’s
Restroom G209, etc. but Training
Rooms T201and T02 don’t show any RF shielding requirements.
"N6, N2, Command, N3, TU 1-4, G206 and divers room must have RF shielding.
T202, T201, G201, G20, S201, A201,A203,A202 do not require RF
The building layout is preliminary and is subject to change. RF shielding can be added to rooms that do not require them in order to keep continuous RF shielding as needed. "
562 The Dive Suite has Room
Requirements for small offices
D202 thru D205 but is missing similarly sized Room Requirement for D206 and D207. Please provide those missing Room Requirement sheets.
Please disregard D206 and D207 as they are no longer required for this project as per the Amendment 0006 updated Room
Requirement sheets.
563 The Dive Suite requests windows and sun control devices in four small offices. Please confirm if the intent of the window is to have a view to the outside, or is the intent
Both a view and Natural light would be ideal just to get natural light into the space.
564 CS102 Sheet
CS105,
AMD
The revised site plan issued with
AMD 0005 shows the Road Option to the west of the P909 project, which forms a loop around existing building 125. For this road section, please clarify what is required for these roads. For example, the IAP calls for curb and gutter, sidewalks, street furniture, landscape strips, lighting, ground cover and grasses, canopy trees, and wayfinding.
None of these are referenced in Part
3 of the RFP. Are they required for the road option and the base bid option?
For the "Road Option", curb and gutter is not required. For the base bid, curb and gutter, sidewalks, etc, are required.
565 CS102 Sheet
CS105,
AMD
The revised site plan issued with
AMD 0005 shows the road section from Intercove to Cove Road.
Please clarify what is required for these roads. For example, the IAP calls for curb and gutter, sidewalks, street furniture, landscape strips, lighting, ground cover and grasses, canopy trees, and wayfinding. None of these are referenced in Part 3 of the RFP. Are they required for the road option and the base bid option?
This section is part of the base bid and the
IAP applies.
566 CS102 Sheet
CS105,
AMD
Please confirm whether the Option
Road is considered Primary or
Secondary.
Secondary
567 CS102 Sheet
CS105,
AMD
Please confirm whether the extension of Intercove to Cove
Road is Primary or Secondary.
Secondary
568 CS102 Sheet
CS105,
AMD
Please provide as-builts of site utilities in the path of the new
Option Road, and whether their removal/relocation is required as a part of this work.
As-builts is not able to be provided at this time but removal and relocation of utilities is not anticipated at this time.
570 Price
Proposal
Form
All Options on the Price Proposal
Form – What is the time frame for accepting the Bid Options provided on the Price Proposal Form? Will these Bid Options be accepted or declined at the time project award so the design can move forward with or without these options?
See Amendment 0008, reference Revised
Attachment D Price Proposal Form. See
General Bid Notes.
571 Price
Proposal
Form
Option No. 2 on the Price Proposal
Form is for the Platoon Storage
Room. These three rooms are listed in the space tabulation document. Will the required building square footage decrease if
The required building square footage will
NOT be decreased if this option is not accepted.
this option is not accepted? Or is this option intended to be a CLIN for accounting purposes only?
572 Price
Proposal
Form
Option No. 3 on the Price Proposal
Form is for the Staging and Set up
Area. Will the required building square footage decrease if this option is not accepted? Or is this option intended to be a CLIN for accounting purposes only?
The required building square footage will
NOT be decreased if this option is not accepted.
573 Price
Proposal
Form
Option No. 4 on the Price Proposal
Form is the Drive Lane Around the
Complex. Please provide further clarification on where this drive line is required.
General location is shown on the plans.
The charrette will determine final layout and limits.
574 Price
Proposal Form
Option No. 5 on the Price Proposal
Form is the Access Floor. Per Addendum #5 it was stated that the access flooring has been omitted from this project. Is the base bid design not to include access flooring? If access flooring is not be included in the base bid, is it the intent that all project scope that would be typically run under an access floor be run overhead and exposed in the secured areas?
Access flooring is limited to the N2/JCO room where tiered seating is anticipated.
Exposed utilities shall not be considered.
576 Addendu m 6 PPI
In Addendum #6 question 418, the answer mentions Amendment
0007. Is there an Amendment 0007 or was this a typo?
Yes, please reference Amendment 0007, continuation sheet.
577 Addendu m 5
Option No. 6 on the Price Proposal
Form is the Training Rooms and
Stair Tower. Per Addendum #5 no stair tower is part of this bid option. Will the price proposal be updated to indicated that it is just the two rooms and not including the stairs? Will the required building square footage decrease if this option is not accepted? Or is this option intended to be a CLIN for accounting purposes only?
Yes the square footage will decrease if those areas are not constructed. The required number of exists from the second floor will not decrease. The stair referenced in this option is only if another stair is needed to accommodated the increase in occupant load when the training rooms are eventually built.
578 Amend
006 PPI
resposnes
The response to PPI # 35 is in contradiction to the response provided in PPI #36. Please clarify the response for PPI # 35 regarding rooms P230, P231, P232, P233 and
P235.
For clarification, all Room Requirement sheets were re-issued as per Amendment
0006. Any Room Requirement sheets that existed prior are to be disregarded. Lastly, be aware that there are modifications to
Room Requirement Sheets in Amendments after Amendment 0006.
579 Amend
006 PPI
responses
The response to PPI # 36 is in contradiction to the response provided in PPI #35. Please clarify the response for PPI # 36 regarding rooms P210, P214, P215, P216 and
P217.
For clarification, all Room Requirement sheets were re-issued as per Amendment
0006. Any Room Requirement sheets that existed prior are to be disregarded. Lastly, be aware that there are modifications to
Room Requirement Sheets in Amendments after Amendment 0006.
580 Amend
006 PPI
responses
The response to PPI 42 states that room P202 should be adjusted to indicate 200sf on the space tabulation document, however the space tabulation document has been revised to only 130sf. Please confirm which number is correct.
As noted on the revised Amendment 0006
Space Tabulation document, the building total area and associated space areas (P202 for example) are approximations and the final area should be determined by the selected Designer of Record.
581 Amend
006 PPI
responses
The response to PPI #42 does not clarify if the area for spaces P203, P211, P213, P215 have been changed to accommodate the quantity of furniture indicated in the
FF&E cost summary. Please provide an updated FF&E cost summary and direction on the final size for the rooms listed
Please refer to the revised Room
Requirement sheets and revised FFE Cost
Summary that were issued in Amendment 0006.
582 Amend 005 page
FC-2-
000-05N
Part 3 Chapter
2 Section
2.5.2
Section
131-8.2.3
It was previously confirmed that a 70/30 ratio would apply to plumbing fixtures at restrooms (70 male / 30 female). Does this ratio apply to showers as well? Does the
188 Occupants stated on page 430 of the RFP Amend 005 apply to shower counts? In FC-2-000-05N, page 112, section 131-8.2.3, does
'one shower for every 10 PN' apply?
The 70/30 ratio applies to showers.
583 Pavement design will require a
PCASE analysis per UFC requirements; please provide lifecycle design information including service factor; vehicle loading and design life requirement for all discrete road pavement sections. (Each named roadway).
This may be further explored post-award however a response is not available at this time.
584 Please provide any special vehicle provisions required road geometric design (special operational trailer-combination vehicle operations/ramps/ground clearances, vertical and horizontal slope transition requirements, turning radii and maximum/minimum curb transition heights allowed).
Design vehicle is a wb-67 for the truck thru lane and Intercove Rd. and Gator
Blvd. intersections would need to be design accordingly.
585 Design information for loop road around Maritime Operations Center is lacking; please confirm grading requirements for vehicle and logistics management, parking and container storage around the building. Include vehicle types, turning radii, vertical transition requirements and outline drainage requirements including compliance with local, state and federal water
DOR is responsible for providing circulation based upon the user. DOR must comply with all local, state, and federal laws.
quality criteria (please confirm applicability of Chesapeake Bay Act and Virginia Stormwater
Management Program requirements).
586 There is limited information on site utilities in the Road Option / Bldg
125 area; please confirm requirement for integrating existing utilities and replacement of utilities prior to paving new roads.
The area in question is already a gravel area that has transportation vehicles riding on it. Replacement of utilizes is not anticipated.
588 various Part 3, Chapter
5 &
Chapter
C101002 Room Requirements sheets for D201, D202, P201, P202, P204, P205, P207, P213, P230, P232, P233, and P234 all include
Uniformat line item C101002
Demountable Partitions but no
Specific Requirements. These rooms also include Uniformat line item C101001 Fixed Partitions that features Specific Requirements.
Chapter 6 ESR C101002 indicates to provide moveable walls floor-to-ceiling that can be repositioned without creating construction dust or material waste. These spaces all carry a requirement for STC 55 lab-tested/STC-50 field tested partition assemblies which is not achievable with a demountable partition system. Additionally, meeting STC requirements will require acoustical partition assembly construction from the top of demountable partition systems to the underside of structural deck which will not support reconfiguration/repositioning without creating construction dust or material waste. Please clarify the following:
a) The scope/design intent/extent of demountable partitions at each of the rooms identified in Part 3, Chapter 5.
b) Where demountable partition systems are required they do not need to meet the STC-55 lab tested requirement.
c) If demountable partition systems are required they must be bid as part of the construction costs and not incorporated as FF&E.
Demountable partitions are not required in the rooms that are listed. here.
589 828 Part 3, ESR G20
G204001 ESR G204001 FENCING AND
GATES states "Not Used". Please confirm perimeter fencing is not required for this project. Or, if fencing/controlled access is required, provide all related basis of design criteria, including height, material, finish, access control and gates.
Perimeter fencing is required. Base bid for fencing is 7 foot high fence with 1 foot 3 strand out rigger barb wire, chainlink, polyvinyl coated, 9 gauge steel fabric ties.
Refer to UFC 4-022-03 drawing UFC 701 for more detail and UFGS section 32 31
13.53. For bid option with deadmen and
anti crash barriers refer to this UFC and
UFGS as well along with approved DOD anti-ram vehicle crash barriers see attachment in Amendment 8.
590 12 Part 3, Chapter
2.4 Section 2.4 Appropriate Design
references that the platoon storage areas open directly to an exterior fenced in concrete drive-aisle;
however, there is no further basis design criteria related to this scope of work item found within the RFP and ESR G204001 FENCING AND
GATES states "Not Used". Please clarify the basis of design criteria for this fencing including minimum height, fence materials, finish, gates/secure access requirements, and if a roof/lid is required.
Perimeter fencing is required. Base bid for fencing is 7 foot high fence with 1 foot 3 strand out rigger barb wire, chainlink, polyvinyl coated, 9 gauge steel fabric ties.
Refer to UFC 4-022-03 drawing UFC 701 for more detail and UFGS section 32 31
13.53. For bid option with deadmen and
anti crash barriers refer to this UFC and
UFGS as well along with approved DOD anti-ram vehicle crash barriers see attachment in Amendment 8.
593 N/A N/A N/A The RFP does address an anticipated need for concrete over the metal roof deck to meet security/blast requirements.
Amendment 0005 bidder inquiry response to items #13, #14, #15 state that the Security Engineering
Planning Assessment (SEPA) will not be provided until post award.
For bidding purposes please confirm that concrete is not required at the roof deck over CAA or SAA spaces.
Designer must take a six Sided approach when developing the design of these spaces. Wall, Floors Ceilings Doors
Windows if any, penetrations. There is no concrete requirement as long as the 6 sided box fully meets the control requirements.
594 5 Part 3, Chapter
2.3 Section 2.3.2.5.3 lists an Electronic
Key Management Systems (EKMS)
Vault within the N6 Intes/Comms group suite. Please confirm the room number and location for this space as the 4.1 Space Tabulation and Chapter 5 Room Requirements conflict. Please confirm the 6-sided box for this space is to be constructed in accordance with
EKMS-1E Electronics Key management System Policy and
Procedures for NAVY requirements.
The entirety of the N6 Suite is outside the secure perimeter. The Vault is located on the first Floor and is room C104
595 164 of
Amendm ent 6
Room
Require ments
E203 E203 MAC Private Office, Uniformat B1010 Floor calls for RF
Shielding as required (AR). The
Adjacencies line item states this room is be located within the general corridor adjacent to the break room on the second floor.
Please clarify if this room is
E203 is located outside the secured area.RF Shielding is not required required to be within the RF
Shielded CAA boundary?
596 166 of
Amendm ent 6
Room
Require ments
E204 E204 CCC Private Office indates to refer to sheet E203 for Uniformat room requirements. E203 MAC
Private Office, Uniformat B1010
Floor calls for RF Shielding as required (AR). The Adjacencies line item for E204 CCC Private
Office states this room is be located within the general corridor adjacent to the N1 Suite on the second floor.
Please clarify if this room is required to be within the RF
Shielded CAA boundary?
E204 is located outside the secured area.RF Shielding is not required
597 6 of 293 Amendm ent 6
Room
Require ments
C104 C104 - N6 EKMS Vault is included with Amendment 0006 and C206
Vault is not. The Room
Requirements sheet for C104 is populated with several references to the second floor; however, the room is listed as being on the first floor.
Please confirm that C104 - N6
EKMS Vault is located on the first floor.
C104 is located on the First Floor
598 229/232 of 293
Amendm ent 6
Room
Require ments
P205 & P206 How are Task Unit spaces P205
TU1 and P206 TU2 separated from each other, e.g. full height partition walls with a door between them, demountable partition walls with a door between them, or are they open to each other?
Open space, Systems furniture will delineate the space.
599 239/243 of 293
Amendm ent 6
Room
Require ments
P212 & P219 How are Task Unit spaces P212
TU3 and P219 TU4 separated from each other, e.g. full height partition walls with a door between them, demountable partition walls with a door between them, or are they open to each other?
Open space, Systems furniture will delineate the space.
600 229/247 of 293
Amendm ent 6
Room
Require ments
P205 & P230 How are Task Unit spaces P205
TU1 and P230 TU5 separated from each other, e.g. full height partition walls with a door between them, demountable partition walls with a door between them, or are they open to each other?
P205 and P230 are in separate suites.
P205 is in TU-1 suite, and P230 is in TU-5
Suite.
601 Part 3, Chapter
G403010 &
G403011
ICS & Cybersecurity OSP POC
Confirmation
Response to RFI #72 and #103 clarified the Industrial Control System (ICS) and Cybersecurity are separate systems from the telecom system described in G403001, to review Attachment U for the
Telecommunications Point of
Connection, and Building 3165 address. Bldg 3165 is approximately
5,000ft away from the new P909 building.
Questions:
1. Please clarify the point of connection for these two systems.
Are we splicing to existing fiber in existing Handhole 53? Or does the fiber need to be routed all the way back to Building 3165?
2. If Building 3165 is the point of connection, please confirm if existing underground telecom infrastructure will be used to
Building 3165. Or will new infrastructure need to be provided back to Building 3165?
1.Provide new duct bank and fiber to
Handhole 53 and connect to existing 144f infrastructure to establish connectivity with building 3165.
2.Yes utilize existing telecom infrastructure from handhole 53 to building
3165.
602 1399 Part 6 TS101 Telecom OSP Duct bank
Amendment 0006 provided
Attachment U Telecommunication
Point of Connection which directs bidders that existing Handhole 53 will be the point of connection for
P909.
RFI #241 clarified the new duct bank routing on Part 6 TS101
Telecom Site Plan is "new to the connection point." The routing shown on TS101 does not appear to be valid with the updated information that the point of connection will be existing
Handhole 53.
Question:
1. Please confirm the routing shown in the original RFP TS101 is no longer required.
2. Please confirm the proposed new duct bank routing from P909 to existing Handhole 53.
1. The original routing is no longer required.
2.Provide new duct bank from Q909 along
Intercove Rd, Cove Rd and Helicopter Rd.
Coordinate with base UEM and verify existing utilities.
603 RFI 242 Telecom Outside Plant
RFI #242 asks for clarity on the telecom point of connection.
Response to RFI #242 states to refer to Attachment U
Telecommunication Point of
Connection and states "it is the contractor's responsibility to terminate within the building."
Attachment U only appears to show existing Handhole 53 as the point of connection, not a building.
Question: please clarify if the telecom point of connection will be spliced to existing fiber in Handhole
53, or if the telecom fibers will need to be routed back to a building for the point of connection.
Provide new duct bank and fiber to
Handhole 53 and connect to existing 144f infrastructure to establish connectivity with building 3165.
604 RFI 243 Exterior PDS to Building 3854
Per the response to PPI #243, the
Protective Distribution System
(PDS) will be buried and tied into
Building 3854. It is understood that a buried PDS falls under the classification of a Category 2 PDS per CNSSI No. 7003, and that a
Category 2 PDS is required for
Controlled Access Areas with Top
Secret and Sensitive
Compartmented Information in medium threat environments. It is also understood that for medium threat environments, the PDS carrier must be an EMT, rigid pipe, PVC, or similar type conduit, buried a minimum of one (1) meter below the surface, and encased within the center of mass of approximately 8” of concrete.
1. Please confirm that our understanding of a Category 2 PDS being required is correct and that the area in which the PDS will be buried between CAAs in the new facility and Building 3854 will be considered a medium threat environment.
2. Please confirm that our understanding of the buried PDS infrastructure is correct and what size conduit for the PDS will be
1. Correct provide category 2 PDS.
2. Provide 4in PVC conduit.
required.
605 RFI 319 X203 Comm Room Data Sheet
Response to RFI #319 appears to indicate a room data sheet for X203
Comm Room was provided in
Amendment 0006 but it does not appear to be provided with the updated room data sheets.
Question: Please confirm if the room is required or provide the missing X203 Comm Room data sheet.
Room X203 is not required.
606 RFI 317 SOCRATES Network Confirmation
RFI #317 asked if the SOCRATES network drops will be routed to the
SIPR rack. Response to RFI #317 stated "This extends to all areas 838 the project" and does not appear to answer the question.
Question: Please confirm the
SOCRATES network drops will be routed to the SIPR rack.
Correct, the Socrates network drops will be routed to the SIPR racks
607 RFI 244,
SIPR Fiber vs Copper Confirmation
Response to RFI #312 states the
SIPR outlet requirements is Cat 6
UTP. Response to RFI #244 states the use of horizontal fiber is permitted for SIPR.
1. If horizontal fiber is used for
SIPR outlets, is Fiber To The
Desktop permitted and if so, what is the SIPR fiber outlet requirement?
2. If this is not permitted, is fiber to be brought near the outlet and a media converter used to convert to
CAT6?
Fiber to be brought near Desktop and converted to CAT6 for ease of use and hardware compatibility.
608 RFI 248 CCTV Camera Locations
RFI #248 asked if there are any additional camera locations besides the exterior of the building (all corners of the building and all entrances and exits) and the two (2) interior locations. The response to
RFI #248 does not appear to answer the question. Please confirm the required locations for CCTV system cameras.
Coordinate with SSM, in addition to the exterior cameras, provide a minimum of one camera for all entry and exits of the building.
609 N/A Part 3 -
Chapter
ESR D30 Response to PPI #293 indicated a
DOAS is required per UFC 3-410-
01. However per UFC 3-410-01 a
DOAS is only required when sum of all ventilation air into facility is greater than 750 cfm and design includes direct-expansion equipment delivering outside air, which is not a condition of the RFP design which requires chilled water coils at air handlers per ESR Section
D304008. Please confirm a DOAS is not required.
A DOAS is not required. Provide total enthalpy energy recovery device in each air handling unit per RFP ESR D309090.
610 N/A N/A N/A Will the Government please consider extending the proposal due date to Friday, December 20, 2024?
There are still outstanding RFI responses carrying potentially significant design impacts and next week is a short week due to the
Thanksgiving holiday. This extension would address the pending holiday, allow the
Government time to respond to outstanding RFIs, and offerors time to incorporate and respond to any changes resulting from Government
RFI responses.
Yes.
611 N/A General
Require ments
N/A Per the RFP, all Communication
Closets will have 4 server racks.
Based on the square footage of the
Comm Closets, 4 server racks will not fit. Confirm quantity of server racks in each Comm Closet.
Layout and size of telecom room and closet is preliminary. The size and equipment layout is subset to change if needed.
612 CS102 N/A N/A On CS102, the heavy duty concrete depicted adjacent to the P909 structure stops short of either laydown area north and south of the truck access road. Please confirm that this area shown for heavy duty concrete is the only location it is required.
It is required in the two laydown areas on sheet CS101 and for the section located in the drive thru truck lane.
614 N/A Room
Require ments
N/A The RFP lists an STC 55 for the entire exterior envelope including roof. The highest rating available for a roof assembly is STC 53, please confirm this is acceptable.
This is not acceptable.
615 N/A Room
Require ments
N/A In many cases the STC ratings shown in the Part 4.1 Space
Tabulations on pages 447 through
456 of the Amendment 0005 RFP document do not match those shown in the Part 5.0 Room Requirements on pages 458-719. For example, the room requirements for the second floor spaces state "Provide STC 55
(min) rated interior partitions for entire second level.", while the space tabulations show the General
Spaces having no STC rating, The
N1 Admin spaces as STC 40 and the remaining second floor spaces as STC 50. Should the STC ratings for the proposed design meet the requirements of the Part 5 Room
Requirements or the Part 4.1 Space
Tabulations?
Minimum STC ratings for second Floor is
55 unless otherwise stated in the room requirement sheets.
616 N/A Amendm ent 006
PPI
Response s
PPI 270
response
"Response PPI #270 states:
""Reference PPI #191 response.""
There is no PPI #191 or responses provided "
The response was provided in Amendment
617 N/A Amendm ent 006
PPI
Response s
PPI 272
response
Response PPI #272 states:
"Coordinate with PPI #270" which states "Reference PPI #191 response." There is no PPI #191 or responses provided. Please provide
PPI #191 and response or a response to PPI #272.
The response was provided in Amendment
618 N/A Amendm ent 006
PPI
Response s
PPI 214
response
PPI 214 references a JEB Little
Creek - Fort Story IAP dated
October 2013 but does not include the document. Please provide all bidders with October 2013 JEB
Little Creek - Fort Story IAP
Document.
This is an error.