Attachment H Revised 7.10.2020 v2.pdf
PDF 8 KB Posted
- Attached to
- Hurricane Florence Recovery Training and Storage Facilities at MCB Camp Lejeune. Package 3
- Solicitation number
- N4008519R9253
About this file
This document outlines a phased construction schedule for three projects under Solicitation Number N4008519R9253 from the Naval Facilities Engineering Command. The projects include replacing the II MEF Simulation/Training Center, constructing a new MCCSSS Log Ops School, and replacing the LOGCOM CSP Warehouse, all to be completed at Marine Corps Base Camp Lejeune in North Carolina as part of Hurricane Florence recovery efforts. The schedule dictates that design work for the Simulation/Training Center replacement must be completed within 365 days of contract award, construction should begin within 730 days, and all work must finish within 1095 days. Similarly, design should finish on the Log Ops School within 730 days, with start of construction at 1095 days and project completion within 1460 days. Design of the warehouse replacement should be finished within 1095 days, construction should start at 1460 days, and all work must conclude within 1825 days.
View the file
Other files
Show 40 more
Latest 50 of 97 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT H
PHASED CONSTRUCTION SCHEDULE
Within the overall program schedule, commence and complete the work in phases. Complete each phase of the work within the number of calendar days stated in the following schedule:
a. Schedule start day design: The day designated when the Concept Development Workshop commenced; the number listed is the number of calendar days from the award of contract.
b. Completion day design: The day designated is when the final construction documents and specifications have been approved by the Government; the number listed is the number of calendar days from the award of contract.
c. Schedule start day construction: The day designated when construction commences, the number listed is the number of calendar days from the award of contract. Mobilization of office support spaces does not qualify as construction.
d. Contract completion date: The day designated as when all contract requirements have been completed; the number listed is the number of calendar days from the award of contract.
e. Schedule:
Project Number
Project Title Priority
Schedule Start Date
Design
Completion Date
Design
Schedule Start Date
Construction
Contract Completion
Date
P1338F II MEF Simulation/Training
Center Replacement
P1512F MCCSSS Log Ops School 2
P1527F LOGCOM CSP Warehouse
Replacement
File details come from the government source that posted it. Updated .