ATT_RFI177178_TFFPackage3_PriceSchedule_R4.pdf

PDF 552 KB Posted

Attached to
Hurricane Florence Recovery Training and Storage Facilities at MCB Camp Lejeune. Package 3
Solicitation number
N4008519R9253
Issued by

About this file

This document is a price schedule for a federal design-build contract opportunity to provide three training and storage facilities at Marine Corps Base Camp Lejeune in North Carolina as recovery efforts from Hurricane Florence. The contract consists of three contract line item numbers (CLINs) for the facilities, with base prices and several options listed separately. CLIN 0001 is for the P1338F Second Marine Expeditionary Force Simulation Training Center, CLIN 0002 is for the P1512F Marine Corps Community Services Logistics School, and CLIN 0003 is for the P1527F Logistics Command Combat Service Support Warehouse. Furniture, fixtures, equipment, audiovisual, and security systems are included as separate CLINs for each facility. Demolition, exterior enclosure methods, flooring, and parking surfaces are among the optional CLINs. The solicitation number is provided as N4008519R9253 and issued by the Naval Facilities Engineering Command for the Department of the Navy.

View the file

Other files

File Type Posted
M107 1512_6_ESR_B30_R1.pdf PDF
1527_6_ESR_B30_R1.pdf PDF
M107 1512_2_project_objectives_R1.pdf PDF
JRC 1512_6_ESR_D30_R2.pdf PDF
1338_6_ESR_D30_R2.pdf PDF
19R9253 Amendment 0020.pdf PDF
Price Proposal Form Rev 7.10.pdf PDF
LOG OPS 1512_2_project_objectives_R1.pdf PDF
1338_6_ESR_B30_R1.pdf PDF
1527_6_ESR_D30_R2.pdf PDF
LOG OPS 1512_6_ESR_D30_R2.pdf PDF
Attachment H Revised 7.10.2020 v2.pdf PDF
M107 1512_6_ESR_D30_R2.pdf PDF
JRC 1512_6_ESR_B30_R1.pdf PDF
JRC 1512_2_project_objectives_R1.pdf PDF
1338_2_project_objectives_R1.pdf PDF
1527_2_project_objectives_R1.pdf PDF
LOG OPS 1512_6_ESR_B30_R1.pdf PDF
ATT_RFI177178_TFFPackage3_PriceSchedule_R5.pdf PDF
19R9253 Amendment 0019.pdf PDF
19R9253 Amendment 0018.pdf PDF
19R9253 Amendment 0017.pdf PDF
Att_RFI 292 - TFF Package 3_P1512F Phasing Plan_R1.pdf PDF
Att_RFI 254 - TFF Package 3__5_Room_P1512 LOG OPS_5 Room Req-Mothers Room_R1.pdf PDF
Att_RFI 242 and 248 - TFF Package 3_M107 Exterior Photos.pdf PDF
Att_RFI 291 - TFF Package 3_P1512F LOG OPS_F20_R1.pdf PDF
19R9253 Amendment 0016.pdf PDF
19R9253 Amendment 0015.pdf PDF
19R9253 Amendment 0014.pdf PDF
19R9253 Amendment 0013.pdf PDF
19R9253 Amendment 0012.pdf PDF
ir78.pdf PDF
ir78 pipe.pdf PDF
20200409_Hadnot-1707-PRE-FINAL.pdf PDF
Att_RFI 94 - TFF Package 3_P1527F_E10_R2.pdf PDF
Att_RFI 186 - TFF Package 3_P1512F M107_Additional As-Built.pdf PDF
1527_6_ESR_D30_R1.pdf PDF
Att_RFI 97 - TFF Package 3_P1512F LOG OPS_E20_R1.pdf PDF
19R9253 Amendment 0011.pdf PDF
Att_RFI 97 - TFF Package 3_P1527F_E20_R1.pdf PDF
JRC 1512_6_ESR_D30_R1.pdf PDF
1338_6_ESR_D30_R1.pdf PDF
Att_RFI 97 - TFF Package 3_P1512F JRC_E20_R1.pdf PDF
LOG OPS 1512_6_ESR_D30_R1.pdf PDF
M107 1512_6_ESR_D30_R1.pdf PDF
Att_RFI 97 - TFF Package 3_P1338F_E20_R1.pdf PDF
Att_RFI 97 - TFF Package 3_P1512F M107_E20_R1.pdf PDF
TFF MILCON D303001andD304006 REV5.docx DOCX document
19R9253 Amendment 0010.pdf PDF
ATT_RFI 177 - 178_TFF Package 3_Price Schedule_R3.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F-1

ATTACHMENT F – PRICE PROPOSAL FORM

1.1 CONTRACT LINE ITEMS

The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.

Provide the CLIN lump sum price for the following items:

CLIN 0001 – P1338F 2ND MEF SIMULATION TRAINING CENTER BASE PRICE: Price includes the following:

Price for the Total Amount for CLIN 0001 for shall provide the full project scope, excluding other Base Bids

(CLIN 0002, 0003), complete and in-place in accordance with the Design Build RFP even if not specifically listed below.

0001: P1338F 2ND MEF Simulation Training Center:

Price for provision of all work for P1338F complete.

Basis of Bid for CLIN 0001 shall be the Total Amount for CLIN 0001, but not including the work indicated or specified to be provided under any other CLIN.

DESCRIPTION ESTIMATED

QUANTITY

UNIT TOTAL PRICE

0001AA All work complete in accordance with the RFP for CLIN 0001 including 0001AB, 0001AC and

0001AD.

1 LS $

0001AB Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20 Exterior Enclosure Enter selected Exterior Enclosure System below:

1 LS $

0001AC Complete work for the facility inside the 5 foot line

1 LS $

0001AD Complete work for the site work outside the 5 foot line

1 LS $

0001AE Design 1 LS $

Total CLIN 0001 (0001AA+0001AE): $

F-2

CLIN 0002 – P1512F MCCSSS LOG OPS SCHOOL: Price includes the following:

Price for the Total Amount for CLIN 002, P1512F MCCSSS LOG OPS SCHOOL shall provide the full project scope, excluding other Base Bids (CLIN 0001, 0003), complete and in place in accordance with the

Design Build RFP even if not specifically listed below.

0002: P1512F MCCSSS LOG OPS SCHOOL Price for provision of all work for P1512F complete.

Basis of Bid for CLIN 0002 shall be the Total Amount for CLIN 0002, but not including the work

UNIT TOTAL PRICE

0002AA All work complete in accordance with the RFP for CLIN 0002 including 0002AB, 0002AC, 0002AD, 0002AE and

0002AF.

1 LS $

0002AB Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20 Exterior Enclosure Enter selected Exterior Enclosure System below:

1 LS $

0002AC Complete work for the facility inside the 5 foot line

1 LS $

0002AD Complete work for P1512F Joint Reception Center inside the 5 foot line

1 LS $

0002AE Complete work for P1512F M107 Renovation to the 5 foot line

1 LS $

0002AF Complete work for the site work outside the 5 foot line

0002AG Design 1 LS $

Total CLIN 0002 (0002AA + 0002AG): $

F-3

CLIN 0003 – P-1527F LOG COM CSP Warehouse BASE PRICE: Price includes the following:

Price for the Total Amount for CLIN 0003 for P-1527F LOG COM CSP Warehouse shall provide the full project scope, excluding other Base Bids (CLIN 0001, 0002), complete and in-place in accordance with the

Design Build RFP even if not specifically listed below

0003: P-1527F LOG COM CSP Warehouse:

Price for provision of all work for P1527F complete.

Basis of Bid for CLIN 0003 shall be the Total Amount for CLIN 0003, but not including the work

UNIT TOTAL PRICE

0003AA All work complete in accordance with the RFP for CLIN 0003 including 0003AB, 0003AC and

0003AD.

1 LS $

0003AB Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20 Exterior Enclosure Enter selected Exterior Enclosure System below:

1 LS $

0003AC Complete work for the facility inside the 5 foot line

1 LS $

0003AD Complete work for the site work outside the 5 foot line

0003AE Design 1 LS $

Total CLIN 0003 (0003AA + 0003AE): $

F-4

Refer to paragraph 1.3 for Planned Modification Bid notes.

CLIN 0004– PLANNED MODIFICATION FOR P1338F – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in accordance with the RFP and in accordance with the following schedule:

CLIN ITEM GOVERNMENT

FF&E

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0006 (GOVT FF&E

ESTIMATE + HAR

AMOUNT)

0004 FF&E $2,756,804

$137,840 $ 2,894,644

CLIN 0005– PLANNED MODIFICATION FOR P1338F – Price includes the following:

Price to procure and supervise installation of the Audio/Visual System (AV) complete in accordance with the

RFP and in accordance with the following schedule:

AV ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0006 (GOVT FF&E

ESTIMATE + HAR

0005 AV $1,681,440

$84072 $ 1,674,512

CLIN 0006– Not Used.

PLANNED MODIFICATION FOR P1338F – Price includes the following:

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance with the RFP and in accordance with the following schedule:

ESS ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0007 (GOVT ESS

ESTIMATE + HAR

0006 ESS $

F-5

CLIN 0007 – OPTION 1 for P1338F, Demolition and Disposal:

Price for Total Amount to provide the full option scope complete and in place in accordance with the RFP even if not specifically listed below. Refer to paragraph 1.2 for explanation of option.

UNIT TOTAL PRICE

0007 Demolition and disposal of Building Foundations (outside footprint)

CLIN 0008 – OPTION 2 for P1338F, Demolition and Disposal:

UNIT TOTAL PRICE

0008 Demolition and disposal of Buildings, Complete (Outside Footprint)

CLIN 0009 – OPTION 3 for P1338F, Parking areas to be gravel:

UNIT TOTAL PRICE

0009 Gravel parking areas 1 LS $

CLIN 0010 – OPTION 4 for P1338F:

NOT USED

0010 Not Used $

CLIN 0011 – OPTION 5 for P1338F, Tilt-up Construction vs Brick Wall Cavity: NOT USED.

DESCRIPTION

ESTIMATED UNIT TOTAL PRICE

0011 NOT USED 1 LS $

F-6

CLIN 0012 – OPTION 6 for P1338F, Terrazzo Flooring for all corridors and main entry:

0012 Terrazzo Flooring 1 LS $

CLIN 0012A – OPTION 6A for P1338F, Operable Folding Partitions:

UNIT TOTAL PRICE

0012A Operable Folding Partitions with door access

CLIN 0013– PLANNED MODIFICATION FOR P1512F – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0006 (GOVT FF&E

ESTIMATE + HAR

0013 FF&E $14,829,218

$741,461 $ 15,570,678

CLIN 0014– PLANNED MODIFICATION FOR P1512F – Price includes the following:

Price to procure and supervise installation of the Audio/Visual Equipment (AV) complete in accordance with the RFP and in accordance with the following schedule:

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0006 (GOVT FF&E

ESTIMATE + HAR

0014 AV $1,254,723

$62,736 $ 1,317,459

F-7

CLIN 0015 – PLANNED MODIFICATION FOR P1512F – Price includes the following: NOT USED

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0007 (GOVT ESS

ESTIMATE + HAR

0015 ESS $

CLIN 0016 – OPTION 1 for P1512F, Demolition and Disposal:

UNIT TOTAL PRICE

0016 Demolition and disposal of Building Foundations (outside

CLIN 0017 – OPTION 2 for P1512F, Demolition and Disposal:

UNIT TOTAL PRICE

0017 Demolition and disposal of Buildings, Complete (Outside

CLIN 0018 – OPTION 3 for P1512F, Parking areas to be gravel:

0018 Gravel parking areas 1 LS $

F-8

CLIN 0019 – OPTION 4 for P1512F: Tiered Access Floors in Log Ops School Classrooms

NOT USED

RFP even if not specifically listed below.

UNIT TOTAL PRICE

0019 Not Used Tiered Raised Access Floors

CLIN 0020 – OPTION 5 for P1512F, Tilt-up Construction vs Brick Wall Cavity: NOT USED

0020 Tilt-up Construction 1 LS $

CLIN 0021 – OPTION 6 for P1512F, Repair M107 Roof in lieu of Replace:

UNIT TOTAL PRICE

0021 Repair M107 Roof in lieu of Replace

CLIN 0022 – OPTION 7 for P1512F, M107 Sloped Roof: Not used.

0022 M107 Sloped Roof 1 LS $

CLIN 0023 – OPTION 8 for P1512F, Additional pavement for Troop Formations:

UNIT TOTAL PRICE

0023 Additional pavement for Troop Formations (2 ea)

F-9

CLIN 0024 – OPTION 9 for P1512F, Terrazzo flooring at all corridors and Main Entry:

0024 Terrazzo Flooring 1 LS $

CLIN 0025– PLANNED MODIFICATION FOR P1527F – Price includes the following:

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0006 (GOVT FF&E

ESTIMATE + HAR

0025 FF&E $3,114,412

$155,720 $ 3,270,132

CLIN 0026– PLANNED MODIFICATION FOR P1527F – Price includes the following:

Price to procure and supervise installation of the Audio/Visual Equipment (AV) complete in accordance with the RFP and in accordance with the following schedule:

AV ESTIMATE

HAR (NTE 5%) HAR

AMOUNT

(GOVT FF&E

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0006 (GOVT FF&E

ESTIMATE + HAR

0026 AV $10,420

$521 $ 10,941

F-10

CLIN 0027– PLANNED MODIFICATION FOR P1527F – Price includes the following: NOT USED

Price to procure and supervise installation of the Electronic Security System (ESS) complete in accordance

HAR (NTE 5%) HAR

AMOUNT

(GOVT ESS

ESTIMATE X

HAR%)

TOTAL FF&E

ESTIMATED

AMOUNT FOR CLIN

0007 (GOVT ESS

ESTIMATE + HAR

0027 ESS $

CLIN 0028 – OPTION 1 for P1527F, Demolition and Disposal:

UNIT TOTAL PRICE

0028 Demolition and disposal of Building Foundations (outside

CLIN 0029 – OPTION 2 for P1527F, Demolition and Disposal:

UNIT TOTAL PRICE

0029 Demolition and disposal of Buildings, Complete (Outside

CLIN 0030 – OPTION 3 for P1527F, Parking areas to be gravel:

0030 Gravel parking areas 1 LS $

F-11

CLIN 0031 – OPTION 4 for P1527F, Metal Panel Exterior Cladding vs Brick Cavity Wall:

0031 Exterior Metal Cladding 1 LS $

CLIN 0032 – OPTION 5 for P1527F, Tilt-up Construction vs Brick Wall Cavity: NOT USED

0032 Tilt-up Construction 1 LS $

CLIN 0033 – OPTION 6 for P1527F, Membrane Roofing vs Low slope Metal Roofing:

UNIT TOTAL PRICE

0033 Membrane Roofing vs Low slope Metal Roofing

CLIN 0034 – OPTION 7 for P1527F, Reduce Overall Wall Height & Add Pallet Racks:

UNIT TOTAL PRICE

0034 Reduce Overall Wall Height & Add Pallet Racks

F-12

1.2 Explanation of CLIN Items

CLIN 0001

Total amount of Base Amount CLIN 0001 shall provide the full project scope, excluding Bid Options defined below, complete in place in accordance with the RFP even if not specifically listed. Explanation of specific work items as defined as follows:

CLIN 0001: P1338F 2ND MEF SIMULATION TRAINING CENTER - includes all P1338F Base Bid

Work and includes, but is not limited to, the design and construction of the building and site utilities;

providing construction permitting fees, and all incidental and related work.

0001AA: All work complete in accordance with the RFP for CLIN 0001 including 0001AB, and

0001AC.

0001AB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

Exterior Enclosure. Enter selected Exterior Enclosure in the space provided.

0001AC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, and equipment for construction of the facility and all incidental and related work.

0001AD: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and equipment for grading and drainage, paving, utilities, and all incidental and related work.

0001AE: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, electrical, and all incidental and related work.

CLIN 0002

Total amount of Base Amount CLIN 0002 shall provide the full project scope, excluding Bid Options defined below, complete in place in accordance with the RFP even if not specifically listed. Explanation of

CLIN 0002: P1512F MCCSSS LOG OPS SCHOOL - includes all P1512F Base Bid Work and includes, but is not limited to, the design and construction of the building and site utilities; providing construction permitting fees, and all incidental and related work.

0002AA: All work complete in accordance with the RFP for CLIN 0002 and including the work indicated or specified under 0002AB through 0002AE.

0002AB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

Exterior Enclosure. Enter selected Exterior Enclosure in the space provided.

0002AC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, 0002AD: P1512F Joint Reception Center and work inside the 5 foot line, excluding design costs, F-13 includes labor, materials, and equipment for construction of the facility and all incidental andrelated work.

0002AE: P1512F M107 Renovation and work inside the 5 foot line, excluding design costs, includes labor, materials, and equipment for construction of the facility and all incidental and related work.

0002AF: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and

0002AG: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, CLIN 0003

Total amount of Base Amount CLIN 0003 shall provide the full project scope, excluding Bid Options defined below, complete in place in accordance with the RFP even if not specifically listed. Explanation of

CLIN 0003: P-1527F LOG COM CSP Warehouse - includes all P1527F Base Bid Work and includes, but is not limited to, the design and construction of the building and site utilities; providing construction permitting fees, and all incidental and related work.

0003AA: All work complete in accordance with the RFP for CLIN 0003 and including the work indicated or specified under 0003AB through 0003AC.

0003AB: Complete work for the facility Exterior Enclosure in accordance with Part 3 ESR B20

Exterior Enclosure. Enter selected Exterior Enclosure in the space provided.

0003AC: Facility and work inside the 5 foot line, excluding design costs, includes labor, materials, 0003AD: Site work outside the 5 foot line, excluding design costs, includes labor, materials, and

0003AE: Design includes provision of all work associated with the site and building design including but not limited to architecture, structural, geotechnical, interior design, civil, mechanical, CLIN 0004 – Planned Modification for P1338F

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in accordance with the RFP.

CLIN 0005 – Planned Modification for P1338F

F-14

Price to procure and supervise installation of the Audio/Visual Equipment (AV) complete in accordance with the RFP.

CLIN 0006 – NOT USED

CLIN 0007 – Planned Option 1 for P1338F

Delete the work for the demolition and disposal of building foundations outside of the P1338F II Simulator

Training Facility footprint complete in accordance with the RFP.

CLIN 0008 – Planned Option 2 for P1338F

Delete the work for the demolition and disposal of building (including foundations) outside of the P1338F II

Simulator Training Facility footprint complete in accordance with the RFP.

CLIN 0009 – Planned Option 3 for P1338F

Delete the work for the asphalt surface course at parking areas for P1338F II Simulator Training Facility.

Price for parking areas to be gravel complete in accordance with the RFP.

CLIN 0010 – Planned Option 4 for P1338F

Not used.

CLIN 0011 – Planned Option 5 for P1338F NOT USED

Delete the work for brick cavity wall assembly over CMU backup. Price for tilt-up wall concrete panel construction complete in accordance with the RFP.

CLIN 0012 – Planned Option 6 for P1338F

Delete the flooring finishes in the corridors and Main Entry (identified in RFP Part 3, Chapter 5 Room

Requirements). Price as terrazzo flooring complete in accordance with the RFP.

CLIN 0012A – Planned Option 6A for P1338F

Delete movable partitions between Simulation Classrooms (identified in RFP Part 3, Chapter 5 Room

Requirements). Price as Operable Partitions (with door access) complete in accordance with the RFP.

F-15

CLIN 0013 – Planned Modification for P1512F

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

CLIN 0014 – Planned Modification for P1512F

Price to procure and supervise installation of the Audio/Visual Equipment (AV) complete in accordance

CLIN 0015 – Planned Modification for P1512F NOT USED

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0002.

CLIN 0016 – Planned Option 1 for P1512F

Delete the work for the demolition and disposal of building foundations outside of the P1512F LOGOPS

School, Joint Reception Facility and M107 Renovation building footprint(s) complete in accordance with the RFP.

CLIN 0017 – Planned Option 2 for P1512F

Delete the work for the demolition and disposal of building (including foundations) outside of the P1512F

LOG OPS School, Joint Reception Facility and M107 Renovation building footprint(s) complete in

CLIN 0018 – Planned Option 3 for P1512F

Delete the work for the asphalt surface course at parking areas for P1512F. Price for parking areas to be gravel complete in accordance with the RFP.

CLIN 0019 – Planned Option 4 for P1512F

Not Used.

Provide “tiered” raised access floor (7” steps per row of desks) in Log Ops School Classrooms (1-9) in lieu of the flat raised access flooring with a slab recess of 6” that is the base bid.

CLIN 0020 – Planned Option 5 for P1512F NOT USED

Delete the work for brick cavity wall assembly over CMU backup. Price for tilt-up wall concrete panel

F-16

CLIN 0021 – Planned Option 6 for P1512F

Delete the work for roof replacement of M107 Renovation included in CLIN 002AD. Price for repairing

M107 roof complete in accordance with the RFP.

CLIN 0022 – Planned Option 7 for P1512F

Delete the work for roof replacement of M107 Renovation included in CLIN 002AD. Price for adding a

High Slope Roof to M107 roof complete in accordance with the RFP.

CLIN 0023 – Planned Option 8 for P1512F

Price for providing the additional pavement for Troop Formations between existing BEQ Buildings M445 and M446 and between M445 and M450 complete in accordance with the RFP.

CLIN 0024 – Planned Option 9 for P1512F

Delete the flooring finishes in the corridors and Main Entry (identified in RFP Part 3, Chapter 5 Room

Requirements. Price as terrazzo flooring complete in accordance with the RFP.

CLIN 0025 – Planned Modification for P1527F

Price to procure and supervise installation of the Furniture, Fixtures, and Equipment (FF&E) complete in

CLIN 0026 – Planned Modification for P1527F

Price to procure and supervise installation of the Audio/Visual Equipment (AV) complete in accordance

CLIN 0027 – Planned Modification for P1527F NOT USED

Price for provision, installation, testing, and associated training for the Electronic Security System (ESS) complete in accordance with the RFP as necessary for the facility. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Closed Circuit Television (CCTV), boundary switches, electronic latches, motion sensors, electronic entry control, and security monitoring and control workstations. ESS design, design submittals, pathways and electrical power are excluded from this item and shall be priced in the base bid CLIN 0003.

CLIN 0028 – Planned Option 1 for P1527F

Delete the work for the demolition and disposal of building foundations outside of the P1527F LOGCOM

Warehouse Facility footprint complete in accordance with the RFP.

F-17

CLIN 0029 – Planned Option 2 for P1527F

Delete the work for the demolition and disposal of building (including foundations) outside of the P1527F

LOGCOM Warehouse Facility footprint complete in accordance with the RFP.

CLIN 0030 – Planned Option 3 for P1527F

Delete the work for the asphalt surface course at parking areas for P1527F LOGCOM Warehouse Facility.

Price for parking areas to be gravel complete in accordance with the RFP.

CLIN 0031 – Planned Option 4 for P1527F

Delete the work for brick cavity wall assembly. Price for metal wall panel exterior cladding complete in

CLIN 0032 – Planned Option 5 for P1527F NOT USED

Delete the work for brick cavity wall assembly over CMU backup. Price for tilt-up wall concrete panel

CLIN 0033 – Planned Option 6 for P1527F

Delete the work for low sloped metal roofing. Price for membrane roofing complete in accordance with the

RFP.

CLIN 0034 – Planned Option 7 for P1527F

Price to reduce the overall wall height by 5’-4” and add additional pallet racks complete in accordance with the RFP.

NOTE: The Government reserves the unilateral right to award the Option(s) to the Contractor at the negotiated price within 180 Calendar Days after the Contract Award Date. If Options are exercised, the

Contract Completion Date remains.

File details come from the government source that posted it. Updated .