1338_6_ESR_B30_R1.pdf
PDF 116 KB Posted
- Attached to
- Hurricane Florence Recovery Training and Storage Facilities at MCB Camp Lejeune. Package 3
- Solicitation number
- N4008519R9253
About this file
This document provides specifications for a roofing system as part of a design-build request for proposal for hurricane recovery training and storage facilities at Marine Corps Base Camp Lejeune in North Carolina. The roof system shall be watertight and include a standing seam metal roof in 3004 aluminum coated with PVDF. Insulation shall meet requirements in UFC 1-200-02 and UFC 3-110-03. Compatible gutters, downspouts, flashings and trim shall be provided. The related federal contract opportunity is solicitation number N4008519R9253 for Package 3 which includes replacement projects for MCCSSS Log Ops School, II MEF Simulation/Training Center, and LOGCOM CSP Warehouse at MCB Camp Lejeune to recover from Hurricane Florence. The awarding agency is the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
Show 40 more
Latest 50 of 97 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design-Build Request for Proposal RTA Hurricane Florence Recovery Training and Storage Facilities 3 March27 May 2020 Marine Corps Base Camp Lejeune, North Carolina
PART 3 - CHAPTER 6/ESR B30 - P1338F II MEF SIMULATION/TRAINING CENTER REPLACEMENT - Page 1
B30 ROOFING – P1338F II MEF SIMULATION/TRAINING
CENTER REPLACEMENT
B30 GENERAL SYSTEMS DESCRIPTION
Roof systems shall be watertight. Provide complete roof system design and construction services for the entire new facility roof system, including all ancillary and incidental work necessary for a complete, new, watertight roof system installation.
Submittal Requirements: Components of a minimum roof submittal shall include the roof plan, method of drainage, standard details and details unique to the project, wind load calculations and requirements.
Provide a Pre-Design Roofing Conference (if required in RFP Part 4) and Pre-Construction Roofing Conference to assure roof design and construction is properly coordinated before construction begins.
Refer to UFC 3-110-03, Roofing, UFC 3-101-01, Architecture, and UFC 1-200-02 High Performance Sustainable Buildings for additional roofing requirements such as Energy Star qualified products.
MOST RELEVANT CODES AND STANDARDS
Refer to Part 3, Chapter 1.
B3010 ROOF COVERINGS
B301001 STEEP SLOPE ROOFING SYSTEMS
Provide a SSMR (standing seam metal roof system). The slope and configuration of the roofing is suggested in the Base Exterior Architectural Plan (BEAP), 2010, Section 4.2, Hadnot Point.
Refer to Part 3, Chapter 2 for prescribed roof slope.
The roof system shall be designed and attached to resist wind uplift pressures calculated in accordance with ASCE 7. Uplift resistance shall be validated by applicable Factory Mutual (FM), Underwriters Laboratories (UL) or ASTM uplift resistance test procedures. The roof material must be 3004 aluminum, ASTM B209M ASTM B209..
Organic Coatings for the metal roof must be a PVDF coating as specified in Part 6, Roof specification section 07 61 15. 00 20 Aluminum Standing Seam Roofing. All other material and construction for metal roofing are per Part 6 specification section.
The spacing of standing seams shall between 12 inches and 18 inches on center as prescribed in the BEAP.
Sub-purlins for the Structural Metal Roof System shall be galvanized and shop painted.
SSSMRS Warranty Certificate. – Provide warranty requirements as defined in Part 6, Roof specification section 07 61 15. 00 20 Aluminum Standing Seam Roofing.
Specular Gloss of Finished roof surfaces must have a specular gloss value of 10 or less at an angle of 85 degrees or 30 plus or minus the value specified in the project program at 60 degrees when measured in accordance with ASTM D 523.
Design-Build Request for Proposal RTA Hurricane Florence Recovery Training and Storage Facilities 3 March27 May 2020 Marine Corps Base Camp Lejeune, North Carolina
PART 3 - CHAPTER 6/ESR B30 - P1338F II MEF SIMULATION/TRAINING CENTER REPLACEMENT - Page 2
B301002 LOW SLOPE ROOFING SYSTEMS
NOT USED
B301003 ROOF INSULATION AND FILL
Provide roof insulation values no less than in accordance with UFC 1-200-02 High Performance and Sustainable Buildings and UFC 3-110-03 Roofing.
B301004 FLASHINGS AND TRIM
Provide flashing and trim for the Aluminum Standing Seam Metal roof per specification section 07 61 15. 00 20 Aluminum Standing Seam Roofing in Part 6 of this RFP.
B301005GUTTERS AND DOWNSPOUTS
Provide gutters and downspouts compatible with roofing material and finish. Concealed (interior) gutters and downspouts are prohibited.
B301006 ROOF OPENINGS AND SUPPORTS
NOT USED – this includes any type of horizontally oriented glazed roof opening that includes skylights and solar tubes that are prohibited for this project.
B301090 OTHER ROOFING
Provide lightning protection, without penetrating the roofing or flashing components.
--End of Section--