This document outlines requirements for selective building demolition and hazardous component abatement as part of a design-build request for proposal for hurricane recovery training and storage facilities at Marine Corps Base Camp Lejeune in North Carolina. The scope of work includes complete demolition of 25 buildings and removal of all associated utilities, mechanical, electrical, and communications systems. Offerors must hire a private qualified person as a subcontractor to ensure compliance with hazardous material abatement work plans and perform independent inspections and verification for asbestos, lead-based paint, and any other hazardous materials identified in destructive surveys to be provided by the government. The solicitation also requires disposal of all materials in accordance with specifications.
View the file
Other files
Show 40 more
Latest 50 of 97 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Design-Build Request for Proposal RTA Hurricane Florence Recovery Training and Storage Facilities 3 March 20205/11/2020 Marine Corps Base Camp Lejeune, North Carolina Rev 01
PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 1
F20 SELECTIVE BUILDING DEMOLITION – P1512F LOG
OPS SCHOOL
SYSTEM DESCRIPTION
A group of individual buildings are to be removed in their entirety as a part of the scope of this RFP. Refer to the list in F2010 Building Elements Demolition.
MOST RELEVANT CODES AND STANDARDS
Refer to Part 3, Chapter 1.
GENERAL SYSTEMS REQUIREMENTS
Perform all off-site work necessary to meet the requirements of the project, local codes, reference standards, technical specifications and performance criteria.
Identify and obtain all permits to comply with all federal, state, and local regulatory requirements associated with this work. The contractor shall submit complete the "Permits Record of Decision" (PROD) form with the first design submittal package. A blank PROD form is in the UFC 3-201-01, Civil Engineering. Contractor shall determine correct permit fees and pay said fees. Copies of all permits, permit applications, and the completed PROD form shall be forwarded to the EFD Environmental Reviewer.
Coordinate and obtain approval from the Contracting Officer for proposed haul route(s), work site access point(s), employee parking location(s) and material laydown and storage area(s).
F2010 BUILDING ELEMENTS DEMOLITION
This project includes the complete demolition of the following: Buildings M90, M90A, M95, M119, M121, M122, M123, M126, M130, M132, M305, M311, M313, M403, M405, M406, M409, M411, M412, M413, M415, M416, M418, M420, and M422.
F2010 1.1 GENERAL DEMOLITION
Remove indicated existing structures 48 inches below existing grade.
F2010 1.2 UTILITIES
Remove all existing utility service connections including but not limited to water, sanitary sewer, natural gas, electric, and telecom. All service connections shall be demolished to the service main and capped per all State and Federal requirements.
Utility demolition must be coordinated with on-site personnel for planned outages.
Demolition of buildings' associated telecommunications services and pathways must be coordinated with Base Telephone office.
For natural gas demolition notify PNG when a facility is ready for demolition. Once the facility has been confirmed for demolition PNG will remove and retire the meter. PNG will valve off the lateral at the main and will disconnect both ends of the gas lateral, the meter side, and the main side. To depict retirement, PNG will remove the lines 4 to 5 feet from each end. Remove the remaining line left by PNG. Once a meter is retired, the lateral cannot be reused for a new facility.
PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 2
F2010 1.3 DUST CONTROL
Prevent the spread of dust and debris to occupied portions of the building and avoid the creation of a nuisance or hazard in the surrounding area.
F2010 1.4 TRAFFIC CONTROL
Where pedestrian or vehicle safety is endangered, use traffic barricades to reroute traffic to safe routes.
F2010 1.5 WEATHER PROTECTION
NOT USED
F2010 1.6 BURNING
Where burning is permitted, adhere to federal, state and local regulations shall be required.
Contractor must comply with Base Bulletin 5090 (Open Burning of Vegetation Debris aboard Marine Corps Base Camp Lejeune and Marine Corps Air Station New River). Refer to Part 6 Attachments – General for the Base Bulletin 5090.
All open burning shall be coordinated with the Air Quality Manager at MCBCL (910-451-5836).
F201001 SUBSTRUCTURE & SUPERSTRUCTURE
Brief descriptions of the buildings to be demolished follow. Refer to Demolition Site Plans in Part 6 for additional information.
Building M130 is a multi-winged single story building with shallow foundations supporting load bearing masonry walls and a wood truss roof structure.
Building M132 is a single story building with shallow foundations supporting load bearing masonry walls and a wood truss roof structure.
Building M403 is an H-shaped single story building with shallow foundations supporting load bearing masonry walls and a wood truss roof structure.
All remaining buildings to be demolished are similar to those outlined above.
F201002 EXTERIOR CLOSURE
The buildings listed above to be demolished in their entirety are low one story structures built in the 1940s and have various exterior materials dating from that time that include load bearing masonry exterior wall systems, windows and doors.
F201003 ROOFING
The buildings to be demolished have sloped roofs with primarily asphalt shingle roofing.
F201004 INTERIOR CONSTRUCTION & FINISHES
The building listed above to be demolished have been renovated at various times and in recent years. They have a combination of interior partition systems that includes CMU, gypsum wall board and metal stud partitions, and various other more historic partition systems. All have toilet rooms and finishes associated with toilet rooms.
PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 3
F201005 CONVEYING SYSTEMS
No conveying systems are being demolished
F201006 MECHANICAL SYSTEMS
Demolish mechanical and plumbing systems. Follow Camp Lejeune Mechanical Design Guidance for proper refrigerant handling.
F201007 ELECTRICAL SYSTEMS
Demolish existing buildings’ electrical distribution systems in their entirety, including equipment, luminaires, devices, wiring, pathways. Contact Tony Beckwith at (910) 451-2790 to coordinate electrical demolition. If unsuccessful, contact the construction manager who will coordinate with the Public Works Department.
Demolish existing buildings’ communications systems in their entirety, including equipment, devices, wiring, and pathways.
Demolish existing buildings’ fire alarm systems in their entirety, including equipment, devices, wiring, and pathways. Prior to demolition, contact Base fire alarm technicians and allow time for their retrieval of existing fire alarm system panels, devices, and appliances. Contact David Jones (910) 376-0437 to schedule the removal of the existing fire alarm system components. If unsuccessful, contact the construction manager who will coordinate with the Public Works Department.
F201008 EQUIPMENT & FURNISHINGS
Equipment and furnishings must be removed by the Contractor prior to removal of the building.
F201090 OTHER NON-HAZARDOUS SELECTIVE BUILDING
DEMOLITION
NOT USED
F2020 HAZARDOUS COMPONENT ABATEMENT
A Hazardous Material Survey Report will be provided by the government for each building listed in Section F2010 above. The reports are to be provided after the issuance of this RFP but prior to the award of the project.
F2020 1.1 PRIVATE QUALIFIED PERSON (PQP)
The General Contractor is required to hire, as a first tier subcontractor, a PQP to ensure compliance with the approved work plans and perform independent inspections, testing and verification of the hazardous components work including: asbestos, lead containing paint, and any other hazardous material identified in the Destructive Hazardous Material Survey Report.
F2020 1.2 FURNISHINGS
All furnishings in the listed buildings will be removed prior demolition.
F2020 1.3 ASBESTOS
Refer to F2020 above.
PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 4
F2020 1.4 LEAD BASED PAINT
Refer to F2020 above.
F2020 1.5 PAINT RELATED WORK
Refer to F2020 above.
F2020 1.6 MERCURY & LLR COMPONENTS
Refer to F2020 above.
F2020 1.7 PCB'S
Refer to F2020 above.
F2020 1.8 OZONE DEPLETING SUBSTANCES (ODS)
Refer to F2020 above.
F2020 1.9 ANIMAL DROPPINGS
Refer to F2020 above.
F2020 1.10 MOLDS AND SPORES
Refer to F2020 above.
F2020 1.11 DISPOSAL
Perform disposal in accordance with the RFP and the specifications and plans provided in Part 5 and Part 6.
F202001 SUBSTRUCTURE & SUPERSTRUCTURE
Refer to F2020 above.
F202002 EXTERIOR CLOSURE
Refer to F2020 above.
F202003 ROOFING
Refer to F2020 above.
F202004 INTERIOR CONSTRUCTION & FINISHES
Refer to F2020 above.
F202005 CONVEYING SYSTEMS
No conveying systems are to be demolished
F202006 MECHANICAL SYSTEMS
Refer to F2020 above.
F202007 ELECTRICAL SYSTEMS
Refer to F2020 above.
PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 5
F202008 EQUIPMENT & FURNISHINGS
Refer to F2020 above.
F202090 OTHER HAZARDOUS SELECTIVE BUILDING DEMOLITION
NOT USED
--End of Section--