Att_RFI 291 - TFF Package 3_P1512F LOG OPS_F20_R1.pdf

PDF 132 KB Posted

Attached to
Hurricane Florence Recovery Training and Storage Facilities at MCB Camp Lejeune. Package 3
Solicitation number
N4008519R9253
Issued by

About this file

This document outlines requirements for selective building demolition and hazardous component abatement as part of a design-build request for proposal for hurricane recovery training and storage facilities at Marine Corps Base Camp Lejeune in North Carolina. The scope of work includes complete demolition of 25 buildings and removal of all associated utilities, mechanical, electrical, and communications systems. Offerors must hire a private qualified person as a subcontractor to ensure compliance with hazardous material abatement work plans and perform independent inspections and verification for asbestos, lead-based paint, and any other hazardous materials identified in destructive surveys to be provided by the government. The solicitation also requires disposal of all materials in accordance with specifications.

View the file

Other files

File Type Posted
M107 1512_6_ESR_B30_R1.pdf PDF
1527_6_ESR_B30_R1.pdf PDF
M107 1512_2_project_objectives_R1.pdf PDF
JRC 1512_6_ESR_D30_R2.pdf PDF
1338_6_ESR_D30_R2.pdf PDF
19R9253 Amendment 0020.pdf PDF
Price Proposal Form Rev 7.10.pdf PDF
LOG OPS 1512_2_project_objectives_R1.pdf PDF
1338_6_ESR_B30_R1.pdf PDF
1527_6_ESR_D30_R2.pdf PDF
LOG OPS 1512_6_ESR_D30_R2.pdf PDF
Attachment H Revised 7.10.2020 v2.pdf PDF
M107 1512_6_ESR_D30_R2.pdf PDF
JRC 1512_6_ESR_B30_R1.pdf PDF
JRC 1512_2_project_objectives_R1.pdf PDF
1338_2_project_objectives_R1.pdf PDF
1527_2_project_objectives_R1.pdf PDF
LOG OPS 1512_6_ESR_B30_R1.pdf PDF
ATT_RFI177178_TFFPackage3_PriceSchedule_R5.pdf PDF
19R9253 Amendment 0019.pdf PDF
19R9253 Amendment 0018.pdf PDF
19R9253 Amendment 0017.pdf PDF
Att_RFI 292 - TFF Package 3_P1512F Phasing Plan_R1.pdf PDF
Att_RFI 254 - TFF Package 3__5_Room_P1512 LOG OPS_5 Room Req-Mothers Room_R1.pdf PDF
Att_RFI 242 and 248 - TFF Package 3_M107 Exterior Photos.pdf PDF
19R9253 Amendment 0016.pdf PDF
19R9253 Amendment 0015.pdf PDF
19R9253 Amendment 0014.pdf PDF
19R9253 Amendment 0013.pdf PDF
19R9253 Amendment 0012.pdf PDF
ir78.pdf PDF
ir78 pipe.pdf PDF
20200409_Hadnot-1707-PRE-FINAL.pdf PDF
Att_RFI 94 - TFF Package 3_P1527F_E10_R2.pdf PDF
Att_RFI 186 - TFF Package 3_P1512F M107_Additional As-Built.pdf PDF
1527_6_ESR_D30_R1.pdf PDF
Att_RFI 97 - TFF Package 3_P1512F LOG OPS_E20_R1.pdf PDF
19R9253 Amendment 0011.pdf PDF
Att_RFI 97 - TFF Package 3_P1527F_E20_R1.pdf PDF
ATT_RFI177178_TFFPackage3_PriceSchedule_R4.pdf PDF
JRC 1512_6_ESR_D30_R1.pdf PDF
1338_6_ESR_D30_R1.pdf PDF
Att_RFI 97 - TFF Package 3_P1512F JRC_E20_R1.pdf PDF
LOG OPS 1512_6_ESR_D30_R1.pdf PDF
M107 1512_6_ESR_D30_R1.pdf PDF
Att_RFI 97 - TFF Package 3_P1338F_E20_R1.pdf PDF
Att_RFI 97 - TFF Package 3_P1512F M107_E20_R1.pdf PDF
TFF MILCON D303001andD304006 REV5.docx DOCX document
19R9253 Amendment 0010.pdf PDF
ATT_RFI 177 - 178_TFF Package 3_Price Schedule_R3.pdf PDF
Show 40 more

Latest 50 of 97 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Design-Build Request for Proposal RTA Hurricane Florence Recovery Training and Storage Facilities 3 March 20205/11/2020 Marine Corps Base Camp Lejeune, North Carolina Rev 01

PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 1

F20 SELECTIVE BUILDING DEMOLITION – P1512F LOG

OPS SCHOOL

SYSTEM DESCRIPTION

A group of individual buildings are to be removed in their entirety as a part of the scope of this RFP. Refer to the list in F2010 Building Elements Demolition.

MOST RELEVANT CODES AND STANDARDS

Refer to Part 3, Chapter 1.

GENERAL SYSTEMS REQUIREMENTS

Perform all off-site work necessary to meet the requirements of the project, local codes, reference standards, technical specifications and performance criteria.

Identify and obtain all permits to comply with all federal, state, and local regulatory requirements associated with this work. The contractor shall submit complete the "Permits Record of Decision" (PROD) form with the first design submittal package. A blank PROD form is in the UFC 3-201-01, Civil Engineering. Contractor shall determine correct permit fees and pay said fees. Copies of all permits, permit applications, and the completed PROD form shall be forwarded to the EFD Environmental Reviewer.

Coordinate and obtain approval from the Contracting Officer for proposed haul route(s), work site access point(s), employee parking location(s) and material laydown and storage area(s).

F2010 BUILDING ELEMENTS DEMOLITION

This project includes the complete demolition of the following: Buildings M90, M90A, M95, M119, M121, M122, M123, M126, M130, M132, M305, M311, M313, M403, M405, M406, M409, M411, M412, M413, M415, M416, M418, M420, and M422.

F2010 1.1 GENERAL DEMOLITION

Remove indicated existing structures 48 inches below existing grade.

F2010 1.2 UTILITIES

Remove all existing utility service connections including but not limited to water, sanitary sewer, natural gas, electric, and telecom. All service connections shall be demolished to the service main and capped per all State and Federal requirements.

Utility demolition must be coordinated with on-site personnel for planned outages.

Demolition of buildings' associated telecommunications services and pathways must be coordinated with Base Telephone office.

For natural gas demolition notify PNG when a facility is ready for demolition. Once the facility has been confirmed for demolition PNG will remove and retire the meter. PNG will valve off the lateral at the main and will disconnect both ends of the gas lateral, the meter side, and the main side. To depict retirement, PNG will remove the lines 4 to 5 feet from each end. Remove the remaining line left by PNG. Once a meter is retired, the lateral cannot be reused for a new facility.

PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 2

F2010 1.3 DUST CONTROL

Prevent the spread of dust and debris to occupied portions of the building and avoid the creation of a nuisance or hazard in the surrounding area.

F2010 1.4 TRAFFIC CONTROL

Where pedestrian or vehicle safety is endangered, use traffic barricades to reroute traffic to safe routes.

F2010 1.5 WEATHER PROTECTION

NOT USED

F2010 1.6 BURNING

Where burning is permitted, adhere to federal, state and local regulations shall be required.

Contractor must comply with Base Bulletin 5090 (Open Burning of Vegetation Debris aboard Marine Corps Base Camp Lejeune and Marine Corps Air Station New River). Refer to Part 6 Attachments – General for the Base Bulletin 5090.

All open burning shall be coordinated with the Air Quality Manager at MCBCL (910-451-5836).

F201001 SUBSTRUCTURE & SUPERSTRUCTURE

Brief descriptions of the buildings to be demolished follow. Refer to Demolition Site Plans in Part 6 for additional information.

Building M130 is a multi-winged single story building with shallow foundations supporting load bearing masonry walls and a wood truss roof structure.

Building M132 is a single story building with shallow foundations supporting load bearing masonry walls and a wood truss roof structure.

Building M403 is an H-shaped single story building with shallow foundations supporting load bearing masonry walls and a wood truss roof structure.

All remaining buildings to be demolished are similar to those outlined above.

F201002 EXTERIOR CLOSURE

The buildings listed above to be demolished in their entirety are low one story structures built in the 1940s and have various exterior materials dating from that time that include load bearing masonry exterior wall systems, windows and doors.

F201003 ROOFING

The buildings to be demolished have sloped roofs with primarily asphalt shingle roofing.

F201004 INTERIOR CONSTRUCTION & FINISHES

The building listed above to be demolished have been renovated at various times and in recent years. They have a combination of interior partition systems that includes CMU, gypsum wall board and metal stud partitions, and various other more historic partition systems. All have toilet rooms and finishes associated with toilet rooms.

PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 3

F201005 CONVEYING SYSTEMS

No conveying systems are being demolished

F201006 MECHANICAL SYSTEMS

Demolish mechanical and plumbing systems. Follow Camp Lejeune Mechanical Design Guidance for proper refrigerant handling.

F201007 ELECTRICAL SYSTEMS

Demolish existing buildings’ electrical distribution systems in their entirety, including equipment, luminaires, devices, wiring, pathways. Contact Tony Beckwith at (910) 451-2790 to coordinate electrical demolition. If unsuccessful, contact the construction manager who will coordinate with the Public Works Department.

Demolish existing buildings’ communications systems in their entirety, including equipment, devices, wiring, and pathways.

Demolish existing buildings’ fire alarm systems in their entirety, including equipment, devices, wiring, and pathways. Prior to demolition, contact Base fire alarm technicians and allow time for their retrieval of existing fire alarm system panels, devices, and appliances. Contact David Jones (910) 376-0437 to schedule the removal of the existing fire alarm system components. If unsuccessful, contact the construction manager who will coordinate with the Public Works Department.

F201008 EQUIPMENT & FURNISHINGS

Equipment and furnishings must be removed by the Contractor prior to removal of the building.

F201090 OTHER NON-HAZARDOUS SELECTIVE BUILDING

DEMOLITION

NOT USED

F2020 HAZARDOUS COMPONENT ABATEMENT

A Hazardous Material Survey Report will be provided by the government for each building listed in Section F2010 above. The reports are to be provided after the issuance of this RFP but prior to the award of the project.

F2020 1.1 PRIVATE QUALIFIED PERSON (PQP)

The General Contractor is required to hire, as a first tier subcontractor, a PQP to ensure compliance with the approved work plans and perform independent inspections, testing and verification of the hazardous components work including: asbestos, lead containing paint, and any other hazardous material identified in the Destructive Hazardous Material Survey Report.

F2020 1.2 FURNISHINGS

All furnishings in the listed buildings will be removed prior demolition.

F2020 1.3 ASBESTOS

Refer to F2020 above.

PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 4

F2020 1.4 LEAD BASED PAINT

Refer to F2020 above.

F2020 1.5 PAINT RELATED WORK

Refer to F2020 above.

F2020 1.6 MERCURY & LLR COMPONENTS

Refer to F2020 above.

F2020 1.7 PCB'S

Refer to F2020 above.

F2020 1.8 OZONE DEPLETING SUBSTANCES (ODS)

Refer to F2020 above.

F2020 1.9 ANIMAL DROPPINGS

Refer to F2020 above.

F2020 1.10 MOLDS AND SPORES

Refer to F2020 above.

F2020 1.11 DISPOSAL

Perform disposal in accordance with the RFP and the specifications and plans provided in Part 5 and Part 6.

F202001 SUBSTRUCTURE & SUPERSTRUCTURE

Refer to F2020 above.

F202002 EXTERIOR CLOSURE

Refer to F2020 above.

F202003 ROOFING

Refer to F2020 above.

F202004 INTERIOR CONSTRUCTION & FINISHES

Refer to F2020 above.

F202005 CONVEYING SYSTEMS

No conveying systems are to be demolished

F202006 MECHANICAL SYSTEMS

Refer to F2020 above.

F202007 ELECTRICAL SYSTEMS

Refer to F2020 above.

PART 3 - CHAPTER 6/ESR F20 - P1512F LOG OPS SCHOOL - Page 5

F202008 EQUIPMENT & FURNISHINGS

Refer to F2020 above.

F202090 OTHER HAZARDOUS SELECTIVE BUILDING DEMOLITION

NOT USED

--End of Section--