19R9253 Amendment 0017.pdf
PDF 135 KB Posted
- Attached to
- Hurricane Florence Recovery Training and Storage Facilities at MCB Camp Lejeune. Package 3
- Solicitation number
- N4008519R9253
About this file
This amendment modifies a solicitation for Hurricane Florence Recovery Training and Storage Facilities at Marine Corps Base Camp Lejeune in North Carolina. The opportunity includes three projects: the MCCSSS Log Ops School, the II MEF Simulation/Training Center Replacement, and the LOGCOM CSP Warehouse Replacement. The amendment provides responses to questions from offerors. It clarifies that wood trim is only required in specific rooms of certain buildings, and that the FF&E and A/V procurement meeting and over-the-shoulder review will occur via conference call rather than in person in Norfolk, Virginia. The Department of the Navy, Naval Facilities Engineering Command issued the solicitation.
View the file
Other files
Show 40 more
Latest 50 of 97 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
PPI response
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 14-May-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9253
X 9B. DATED (SEE ITEM 11)
15-Nov-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
14-May-2020
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9253
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0017
This amendment hereby incorporates PPI Responses:
# Reference Question Government Response Page Sect Para
Part 3 Chapt er 6
ESR
C30
LOG
OPS,
JRC,
and
M107
C3010
Wood trim is stated in C301090 of the LOG OPS, JRC, and M107. The location of the wood trim which includes crown molding, wainscot, and chair rail is not specfied in the room requirements. Please provide locations of where wood trim is required within the buildings.`
Wood trim would be located as follows:
• LOG OPS-Conference and CIO office
• JRC-H&S CIO office, OIC office and
Conference room
Chapt er 6
ESR
E20
FF&E
and A/V
In the FF&E and A/V section of Part 3, it states the FF&E and A/V Procurement meeting must occur at MIDLANT in Norfolk VA prior to the DD Submittal. Please confirm the meeting is to take place in Norfolk and not in Jacksonville, NC.
Sentence following “Provide the following FF&E and A/V meetings and submittals”.
Should read “F&E and A/V Procurement Requirements Meeting (Interior Design
Orientation): This meeting will occur via conference call prior to the Design Development (35%-50%) Submittal and the development of the FF&E package.
Chapt er 6
ESR
E20
FF&E
and A/V
In the FF&E and A/V section of Part 3, it states the FF&E and A/V Over-the-Shoulder meeting must occur at MIDLANT in Norfolk VA prior to the DD Submittal. Please confirm the meeting is to take place in Norfolk and not in Jacksonville, NC.
Sentence following “Provide the following FF&E and A/V meetings and submittals”.
Should read “F&E and A/V Procurement Requirements Meeting (Interior Design
Orientation): This meeting will occur via conference call prior to the Design Development (35%-50%) Submittal and the development of the FF&E package.
(End of Summary of Changes)
File details come from the government source that posted it. Updated .