Att_RFI 292 - TFF Package 3_P1512F Phasing Plan_R1.pdf
PDF 260 KB Posted
- Attached to
- Hurricane Florence Recovery Training and Storage Facilities at MCB Camp Lejeune. Package 3
- Solicitation number
- N4008519R9253
About this file
This document outlines the phasing plan for construction projects under Solicitation Number N4008519R9253 from the Department of the Navy Naval Facilities Engineering Command. The solicitation is for Package 3 of Hurricane Florence Recovery Training and Storage Facilities at Marine Corps Base Camp Lejeune, and includes projects for the MCCSSS Log Ops School, II MEF Simulation/Training Center Replacement, and LOGCOM CSP Warehouse Replacement.
The phasing plan details the sequence for replacing the existing MCCSSS Motor Transport Training Building with a new Log Ops School facility. This will include relocating existing MAT trailers currently occupying the construction site, building the new school, moving users from the existing building into the new one, and then commencing renovation of the existing building for other tenants. Construction is scheduled to start by December 2020 and be complete by September 2023. The document provides guidance for coordination between the contractor and government entities during the construction and user relocation process.
View the file
Other files
Show 40 more
Latest 50 of 97 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
As of 9/17/2019 5/11/2020
Rev 01 www.jacobs.com | worldwide
Phasing of MCCSSS Log
Ops School For P1512F – PHASING PLAN http://www.jacobs.com/
2 p - Phasing Plan
Construction Phasing Summary
Construct 2 single story academic and reception facilities:
• Ph. 1.a: New MCCSSS Log Ops Facility
– Construct New
– Relocate Log Ops School to newly completed facility
• Ph. 1.b: New Joint Reception Center Facility
– Includes H/S Functions and student in-processing functions
– Can be built concurrent with Ph 1.a
• Ph. 2a: Move Operations from current M107 Bldg. to the New Log Ops
• Ph. 2b: Move Users into New Joint Reception Center Facility
– Demo existing user buildings
• Ph. 3: Renovate and Convert Bldg. M107 for Multiple Tenants
– Admin & Training Center to support tenants
– Other TECOM Functions
• Ph. 4: Move Tenants from existing buildings into Renovated and Remodeled M107 Bldg.
• Ph. 5: Demo existing support facilities
– Prior to demolition, the base fire alarm techs want to scavenge old fire alarm equipment from buildings to be demolished, and Hazmat abatement will be performed before the buildings will be demolished.
– Demolition Includes Buildings: M90, M90A, M95, M100, M119, M121, M122, M123, M126, M130, M132, M305, M313, 403, M405, 406, M409, M411, M412, M413, M415, M416, M418, M420 and M422
KEY CONSTRUCTION MILESTONES:
– Contract Award by 09/2020
– Construction Start by 12/2020
– Construction Complete by 09/2023
3 p - Phasing Plan
Detailed Sequence of MCCSSS Log Ops School Phasing
Scope for replacement of the MCCSSS Motor transport training building and additional buildings is contained under DD1391, Project Number P1512F. Scope of P1512F includes construction/Renovation of the following facilities:
➢ Joint Reception Center (CC17110)
➢ MCCSSS Log Ops School (CC17120)
➢ Renovate and convert the current MCCSSS motor transport training building M107
Additional relocations (not in contract – but AE2 is required to coordinate with the gov’t) for P1512F includes:
➢ Relocate existing MAT (Marines Awaiting Training) trailers that occupy the parking lot being removed as part of the Log Ops School.
The “trailers” are a form of modular building about 40’x60’ or so. See photos attached.
Log Ops School User Move Sequence/Requirements
➢ Relocate MAT (Marines Awaiting Training) Trailers to a new location on base (to be performed by the gov’t under separate contract): Existing Trailers are in the footprint of new Log Ops School. Need to be relocated prior to commencement of new Log Ops
School.
➢ Build New MCSSS Log Ops School (CC17120): New Greenfield Training facility to be built and fully operable prior to vacating existing Log Ops School.
1. Prior to Users Moving Into New MCCSSS Log Ops School (CC17120): FFE &
Tele/Data complete. CO, KTR, PWD, & Users walk areas to check everything complete, Gov’t Partial Acceptance before turning over to User.
2. Users Prepare to Move into New Log Ops School (CC17120): Users review move requirements and set timeframes, stay in contact with CO. Suggestions:
▪ User meetings to provide project updates & ensure on schedule;
▪ User move checklist.
➢ Users Move into New Log Ops School (CC17120): MCCSSS Log Ops School begins operation in new facility (CC17120)
➢ Commence Renovation of Existing Log Ops School (M107): Upon relocation of Log
Ops School to new facility. commence preparation of existing facility for renovation and conversion of the current MCCSSS motor transport training building.