FA520517R0004_Atch6_Construction_Timeline.pdf
PDF 125 KB Posted
- Attached to
- Improve Military Family Housing (IMFH) Phase III, A/C and Weatherization, Misawa Air Base, Japan
- Solicitation number
- FA5205-17-R-0004
About this file
FA520517R0004_Atch6_Construction Timeline
View the file
Other files
Show all 46
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mo. S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J Mo. # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 17 18 19 20 21 22
QKKA 15‐4008 Day 0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 480 510 540 570 600 630 660 690 720 750 780 810 840 870 900 930 960 990 594 900
ELM LOOP
ZELKOVA LN
CAPE COD
YOSEMITE DR.
YELLOWSTONE DR.
CAPE CANAVERAL
DENALI DR.
CASCADE CT.
CUMBERLAND CT.
BLUE RIDGE DR.
FREEDOM CIRCLE
RUSHMORE CT.
ACADIA CT.
SEQUOIA DR.
DEMOCRACY DR.
TOWER 116 (Tower will be empty prior to 1 Oct
18. The first four floors are to be used as swing space for construction.)
NOTE:
1. Contractor to assume 31 days per building
2. Max of 3 days per unit for Asbestos removal & receive Air Sample results. Residents will not be allowed to enter thier housing unit cleared by air samples.
3. Residents to be moved to tower 116 first four floors for 7 Days. Tower 116 will be used as swing space during ACM removal and demo.
No. Of Units
Note: All 526 Units are available during the 870 days of construction
Pre‐Construction
TOWER 116 Work shall be completed at the end of the project (Tower to be available Oct of 2018
Improve Military Family Housing A/C and Weatherization Phase 3, IMFH A/C and Weatherization Phase 3 QKKA 15‐4008 2017 2018 2019 2020
Atch. 6 to RFP No. FA520517R0004 Dated 27 Feb 17