This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to Professional Service Industries, Inc. (Intertek-PSI) under Contract Number HW686. The TA is designated DC015B and covers site assessment activities at Quality Cleaners (ERIC_4771), located at 14837 North Florida Avenue in Tampa, Hillsborough County, Florida. The task assignment was executed on December 15, 2022, with completion scheduled for November 20, 2023. The contractor's project manager is Nana G. Westmark, and the FDEP project manager is Skylar Schwed.

The contract authorizes PSI to conduct comprehensive site assessment activities including pre-project activities (utility clearance, GPR surveys, professional land surveys, and existing monitoring well sampling), initial mobilization work (lithologic boring, piezometer installation, interior soil borings with MAGS well installation, interior and exterior monitoring well installation, MAGS testing, groundwater screenpoint sampling, and sediment sampling), and data evaluation with report preparation. The total task assignment value is $88,088.40 on a fixed unit rate basis, allocated across four subtasks: Subtask 1 (Project Management, $4,337.14), Subtask 2 (GPR, Survey, and Existing Well Sampling, $11,173.79), Subtask 3 (Assessment and Field Logs, $60,639.88), and Subtask 4 (Data Evaluation and Site Assessment Report, $11,937.59). Invoicing is tied to deliverable completion with payments due upon FDEP approval of GPR field notes and survey notes (Subtask 2 by March 25, 2023), field logs and lab results (Subtask 3 by August 10, 2023), and the final Site Assessment Report with IDW manifests (Subtasks 1 & 4 by September 19, 2023). The document includes detailed cost estimates, level of effort worksheets, subcontractor quotes for drilling and surveying services, and IDW disposal pricing from multiple vendors.

View the file

Other files

File Type Posted
CN-370000-HW686-DC001D.pdf PDF
CN-370000-HW686-DC002A.pdf PDF
CN-370000-HW686-DC002F.pdf PDF
CN-370000-HW686-DC002G.pdf PDF
CN-370000-HW686-DC002H.pdf PDF
CN-370000-HW686-DC003A.pdf PDF
CN-370000-HW686-DC003B.pdf PDF
CN-370000-HW686-DC003E.pdf PDF
CN-370000-HW686-DC003G.pdf PDF
CN-370000-HW686-DC004C.pdf PDF
CN-370000-HW686-DC004E.pdf PDF
CN-370000-HW686-DC007A.pdf PDF
CN-370000-HW686-DC007C.pdf PDF
CN-370000-HW686-DC007D.pdf PDF
CN-370000-HW686-DC009C.pdf PDF
CN-370000-HW686-DC009E.pdf PDF
CN-370000-HW686-DC010C.pdf PDF
CN-370000-HW686-DC011A.pdf PDF
CN-370000-HW686-DC012B.pdf PDF
CN-370000-HW686-DC013A.pdf PDF
CN-370000-HW686-DC014A.pdf PDF
CN-370000-HW686-DC016A.pdf PDF
CN-370000-HW686-DC018A.pdf PDF
CN-370000-HW686-DC019B.pdf PDF
CN-370000-HW686-DC01ACO4.pdf PDF
CN-370000-HW686-DC020C.pdf PDF
CN-370000-HW686-DC023A.pdf PDF
CN-370000-HW686-DC024A.pdf PDF
CN-370000-HW686-DC025A.pdf PDF
CN-370000-HW686-DC026B.pdf PDF
CN-370000-HW686-DC028A.pdf PDF
CN-370000-HW686-DC03DCO2.pdf PDF
CN-370000-HW686-DC04ECO1.pdf PDF
CN-370000-HW686-DC07BCO1.pdf PDF
CN-370000-HW686-DC07BCO3.pdf PDF
CN-370000-HW686-DC09DCO1.pdf PDF
CN-370000-HW686-DC11BCO1.pdf PDF
CN-370000-HW686-DC13BCO1.pdf PDF
CN-370000-HW686-DC14BCO3.pdf PDF
CN-370000-HW686-DC14DCO1.pdf PDF
CN-370000-HW686-DC15BCO1.pdf PDF
CN-370000-HW686-DC15DCO1.pdf PDF
CN-370000-HW686-DC16BCO1.pdf PDF
CN-370000-HW686-DC18CCO1.pdf PDF
CN-370000-HW686-DC21BCO1.pdf PDF
CN-370000-HW686-DC27BCO1.pdf PDF
CN-370000-HW686-FIL10.pdf PDF
CN-370000-HW686-FIL6.pdf PDF
CN-370000-HW686-FIL9.pdf PDF
CN-370000-HW686-HW002A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW686

DC015B Completion November 20, 2023

This Task Assignment authorizes Professional Service Industries, Inc. (PSI) to conduct Site Assessment activities in accordance with the PSI scope of work, cost estimate, and schedule received on December 12 2022.

Skylar Schwed 850-245-8795 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Professional Service Industries, Inc. (Intertek-PSI)

Professional Service Industries, Inc. (Intertek-PSI)

Nana G. Westmark 813-886-1075

ERIC_4771

14837 North Florida Avenue Tampa, Hillsborough County, Florida

Quality Cleaners

✔ $ 88,088.40

$ 88,088.40

Scope of Work

Nana Westmark

Senior Geologist / Principal Consultant

Nana G Westmark Digitally signed by Nana G Westmark Date: 2022.12.15 13:24:51 -05'00'

Teresa Booeshaghi

Teresa Booeshaghi Digitally signed by Teresa Booeshaghi Date: 2022.12.15 11:52:47 -05'00'

12/15/2022

N/A

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Subtask 2 GPR Field Notes, Survey Notes & Lab Results of Well Sampling 03/25/2023

Subtask 3 Field Logs AND Lab Results 08/10/2023

Subtasks 1 & 4 Project Management AND Site Assessment Report which include IDW manifests 09/19/2023

Subtask 2 Submittal and FDEP approval of the GPR Field Notes, Survey Notes & Lab Results of Well Sampling $ 11,173.79

Subtask 3 Submittal and FDEP approval of the Field Logs AND Lab Results $ 60,639.88

Subtasks 1 & 4 Submittal and FDEP approval of the Site Assessment Report which include IDW manifests AND Project Management $ 16,274.73

$ 88,088.40

HW686

DC015B

Printed on recycled paper.

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

To: HW686 Contract Negotiation File Quality Cleaners Tampa, Hillsborough County, Florida

ERIC_4771

From: Skylar Schwed, Project Manager Date: December 13, 2022 Subject: Negotiation Summary

HW686 DC015B

This Task Assignment authorizes PSI to conduct groundwater monitoring activities in accordance with the December 12, 2022, Scope of Work, and Cost Estimate.

PSI confirmed on December 12, 2022, that an Access Agreement with the current real property owner of the Quality Cleaners (ERIC_4771) site has been executed.

The original Task Assignment totaled $88,278.32 with 407.5 labor hours but after negotiations and corrections with the contractor costs are reflected below:

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $88,088.40 with 403.1 labor hours.

PSI may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

FDEP COST ESTIMATE

Contractor: Professional Service Industries, Inc. (Intertek-PSI)

Date: Rev 12/12/2022

Task #: SubTask 1 Project Management SubTask 6

Site: Quality Cleaners ERIC_4771 SubTask 2 GPR, Survey, Existing Well Sampling SubTask 7

Activity/Phase: Site Assessment SubTask 3 Assessment SubTask 8

Project Manager: Nana Westmark SubTask 4 Data Evaluation / Report SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$56.99 Project Manager 27.6 27.6 $0.00 Principal Consultant 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0

$60.00 Senior Engineer, MR 3.0 0.0 3.0 0.0 0.0 0 0 0 0 0 $56.99 Senior Geologist, NW 36.0 2.0 8.0 26.0 0.0 0 0 0 0 0 $57.69 Senior Scientist, MR 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0

$0.00 Certified Industrial Hygientist 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $0.00 Certified Hazardous Materials Manager 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $0.00 Florida Licensed Asbestos Consultant 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $0.00 Project Manager 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0

$43.27 Project Engineer, JN 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $43.27 Project Engineer, IK 36.0 0.0 16.0 20.0 0.0 0 0 0 0 0 $40.87 Project Engineer, MK 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0

$0.00 Project Geologist 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $33.74 Project Scientist, SB 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $28.51 Project Scientist, AH 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $29.77 Project Scientist, RF 133.5 8.5 87.5 37.5 0.0 0 0 0 0 0

$0.00 QA Officer 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $31.51 Remediation Specialist, RH 54.5 0.0 54.5 0.0 0.0 0 0 0 0 0 $29.86 GIS / CAD Specialist, DG 16.0 0.0 0.0 16.0 0.0 0 0 0 0 0

$0.00 Staff Engineer 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $0.00 Staff Geologist 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0

$24.95 Staff Scientist, BW 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $30.91 Environmental Specialist, CC 0.0 0.0 0.0 0.0 0.0 0 0 0 0 0 $22.06 Environmental Specialist, MZ 92.5 7.5 85.0 0.0 0.0 0 0 0 0 0 $20.81 Administrative Assistant, BM 4.0 0.0 0.0 4.0 0.0 0 0 0 0 0

Total Hours 403.1 27.6 18.0 254.0 103.5 0.0 0 0 0 0 0

Direct Labor $13,653.25 $1,570.73 $532.48 $7,525.52 $4,024.52 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 151.02% $20,619.14 $2,372.12 $804.15 $11,365.04 $6,077.83 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $34,272.39 $3,942.85 $1,336.63 $18,890.56 $10,102.35 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF PSI Intertek Page 1

FDEP COST ESTIMATE

Contractor: Professional Service Industries, Inc. (Intertek-PSI)

Date: Rev 12/12/2022

Task #: SubTask 1 Project Management SubTask 6

Site: Quality Cleaners ERIC_4771 SubTask 2 GPR, Survey, Existing Well Sampling SubTask 7

Activity/Phase: Site Assessment SubTask 3 Assessment SubTask 8

Project Manager: Nana Westmark SubTask 4 Data Evaluation / Report SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Travel

Vehicle Rental $2,520.00 $360.00 $2,160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,520.00 $360.00 $2,160.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

MAGS well materials $463.33 $0.00 $463.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $463.33 $0.00 $463.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $46.33 $0.00 $46.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $509.66 $0.00 $509.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $12,226.00 $0.00 $12,226.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 SurvTech Solutions, Inc. $6,125.00 $6,125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $750.00 $0.00 $0.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 GeoView Inc. $1,700.00 $1,700.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $20,801.00 $7,825.00 $12,226.00 $750.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $2,080.10 $782.50 $1,222.60 $75.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $22,881.10 $8,607.50 $13,448.60 $825.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $18,598.00 $266.00 $18,332.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $150.00 $0.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $18,748.00 $266.00 $18,482.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $640.00 $80.00 $560.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $5,090.00 $390.00 $4,700.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $5,730.00 $470.00 $5,260.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $84,661.15 $3,942.85 $11,040.13 $58,750.82 $10,927.35 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $3,427.25 $394.29 $133.66 $1,889.06 $1,010.24 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $88,088.40 $4,337.14 $11,173.79 $60,639.88 $11,937.59 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF PSI Intertek Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Quality Cleaners ERIC_4771 SubTask 2 GPR, Survey, Existing Well Sampling DATE: Rev 12/12/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist Tenant, owner notification 1 Technical oversight 1

Total H 2 Project Scientist, R Fetter Field event preparation 1

Travel, roundtrip 1.5 GPR oversight 3 Specific Boundary Survey oversight 3

Total H 8.5

Environmental Specialist, M Zilske Field event preparation 1 Travel, roundtrip 1.5

Existing monitoring well sampling

2 intermediate wells, 1.5 hrs each 3

Pick-up, drop off sample kits 1

Stage IDW drum from existing well purging 1

Total H 7.5

TOTAL LABOR 18

VEHICLE TYPE RATE UNIT USEAGE

Equipment Van / Truck, GPR oversight $120.00 day 1 $120.00 Equipment Van / Truck, boundary survey oversight $120.00 day 1 $120.00 Equipment Van / Truck, monitoring well sampling $120.00 day 1 $120.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

GeoView Inc. Ground penetrating radar 1 $1,700.00 $1,700.00 SurvTech Solutions, Inc. Specific purpose boundary survey 1 $6,125.00 $6,125.00

$0.00 $0.00

TOTAL $7,825.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00

Halocarbons by EPA Method 8260 $73.00 2 $146.00

Aromatics by EPA Method 8260 $60.00 2 $120.00

TOTAL LAB $266.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00

Shallow Groundwater Sampling Kit $290.00 day 1 $290.00 55--gallon drum $100.00 each 1 $100.00

Expendables $40.00 day 2 $80.00

$0.00 $0.00 $0.00

TOTAL EQUIPMENT $470.00

FINAL --7/24/96

Page 4 Rev 3 Quality Cleaners ERIC_4771 SA 0552-384168

SubTask 3 Assessment DATE: Rev 12/12/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Lithologic Profile Senior Geologist, N Westmark Technical Oversight 2

Notification to tenant, owner 1

Project Scientist, R Fetter Field event preparation 1 Travel, (1.5 hr per roundtrip) 1.5 Lithologic profile to ~28 ft 8 Stage IDW drums 1

11.5 Oversight of Piezometer Installation Senior Geologist, N Westmark Flow direction evaluation 1

Project Scientist, R Fetter Oversight of piezometers 2 Oversight of conversation to monitor wells 2 Measure gw elevations 0.5 Evaluate flow direction 1

5.5

Interior Soil Borings, Soil Sampling

Project Scientist, R Fetter Field event preparation 1 Travel, (1.5 hr per roundtrip) 3 Provide documentation of soil borings logs, soil classification 4 Collect soil samples to 8 feet bls at 2 locations 7.5 Prepare SPLP samples for potential analyses 2 Prepare Chain of custody 0 Stage IDW drums 1

18.5

Remediation Specialist, R Hanson Travel, (1.5 hr per roundtrip) 3 Set-up equipment, visqueen inside building 3 Core through concrete inside building 5 Collect soil samples to 8 feet bls at 2 locations 7.5 Prepare SPLP samples for potential analyses 2

20.5

Environmental Specialist, M Zilske Travel, (1.5 hr per roundtrip) 3 Set-up equipment, visqueen inside building 0 Collect soil samples to 8 feet bls at 3 locations 11.5 Prepare SPLP samples for potential analyses 2.5 Prepare Chain of custody 1

MAGS Well Installation Remediation Specialist, R Hanson Travel, (1.5 hr per roundtrip) 3

Set-up equipment, visqueen inside building 2 Install MAGS wells 12

Environmental Specialist, M Zilske Travel, (1.5 hr per roundtrip) 3 Install MAGS wells 12

Page 5 Rev 3 Quality Cleaners ERIC_4771 SA 0552-384168

MAGS Testing Senior Engineer, M Rothenburg Technical Assistance 3

Environmental Specialist, M Zilske Travel, (1.5 hr per roundtrip) 3 Set up existing system for MAGS 3 Well head assembly set-up 1 Operate MAGS event (1 hrs - 6 points) 6 Collect measurements from other wells 3 Dismantle MAGS equipment 1

Remediation Specialist, R Hanson Travel, (1.5 hr per roundtrip) 3 Set up existing system for MAGS 3 Well head assembly set-up 1 Operate MAGS event (1 hrs - 6 points) 6 Site Restoration outside building 3

Dismantle MAGS equipment 1

Project Engineer, I King Travel, (1.5 hr per roundtrip) 3 Technical review of data during testing 3 Collect vacuum and flow readings (1 hrs / point - 6 points) 6 Written documentation of data collection 4

Groundwater Screenpoint Sampling Senior Geologist, N Westmark Screenpoint evaluation and selection 2

Project Scientist, R Fetter Field event preparation 1 Travel, roundtrip 1.5 Groundwater screenpoint sampling, 2 depths 20 Sample kit pick-up, drop-off 2

24.5

Exterior Soil Borings Project Scientist, R Fetter Field event preparation 1

Travel, (1.5 hr per roundtrip) 1.5 Soil boring installation oversight 8 Sample kit pick-up, drop-off 2

12.5

Environmental Specialist, M Zilske Travel, roundtrip 1.5 Soil sampling 10 Sample kit pick-up, drop-off 2

13.5

Equipment area breakdown and

Page 6 Rev 3 Quality Cleaners ERIC_4771 SA 0552-384168

Sediment Sampling Environmental Specialist, M Zilske Sediment sampling 2

Monitoring Well Installation Oversight Senior Geologist, N Westmark Technical Oversight 2

Project Scientist, R Fetter Field event preparation 1 Travel, (1.5 hr per roundtrip) 3 Monitoring well installation oversight 10 Stage IDW drums 1

Monitoring Well Sampling Environmental Specialist, M Zilske Field event preparation 1

Travel, (1.5 hr per roundtrip) 3 Groundwater well sampling 8 shallow wells (1 hr per shallow well) 8 3 intermediate wells (1.5 hrs per intermediate well) 4.5 Stage IDW drums 1 Sample kit pick-up, drop-off 2

19.5

Page 7 Rev 3 Quality Cleaners ERIC_4771 SA 0552-384168

Summary of Total Hours M Rothenburg 3 N Westmark 8 I King 16 R Fetter 87.5 R Hanson 54.5 M Zilske 85

TOTAL LABOR 254

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Lithologic Profile / Piezometer Installation Equipment Van / Truck 1 person, 1 day $120.00 day 1 $120.00

Interior Soil Borings, Soil Sampling Equipment Van / Truck 3 persons, 2 days $120.00 day 4 $480.00

MAGS Well Installation

Equipment Van / Truck 2 persons, 2 days $120.00 day 2 $240.00

MAGS Testing

Equipment Van / Truck 3 persons, 2 days $120.00 day 4 $480.00

Groundwater Screenpoint Sampling

Equipment Van / Truck 1 person, 2 day $120.00 day 2 $240.00

Exterior Soil Borings / Sediment

Equipment Van / Truck 2 persons, 1 days $120.00 day 1 $120.00

Monitoring Well Installation Oversight Equipment Van / Truck 1 persons, 2 days $120.00 day 2 $240.00

Monitoring Well Sampling Equipment Van / Truck 1 persons, 2 days $120.00 day 2 $240.00

$0.00

TOTAL VEHICLE $2,160.00

Page 8 Rev 3 Quality Cleaners ERIC_4771 SA 0552-384168

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

ATI Drilling lithologic profile, screening, direct push, well installation 1 $12,226.00 $12,226.00 $0.00

$0.00

TOTAL $12,226.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00

Halocarbons by EPA Method 8260 $73.00 109 $7,957.00 27 water and 82 soil samples

Aromatics by EPA Method 8260 $60.00 109 $6,540.00 27 water and 82 soil samples

SPLP Extraction by EPA Method 1311 / 1312 $45.00 25 $1,125.00 $0.00

ENCORE samples $16.00 82 $1,312.00 $0.00

TO-15 (VOCs) $200.00 6 $1,200.00

Summa cannisters $33.00 6 $198.00 18332

Shipping, large, overnight (Summa) $150.00 1 $150.00

$0.00

TOTAL LAB $18,482.00

Page 9 Rev 3 Quality Cleaners ERIC_4771 SA 0552-384168

EQUIPMENT PROCUREMEITEM RATE COSTING UNIT USEAGE TOTALS

MAGS Well Supplies

PVC cement $7.96 each 3 23.88 PVC well screen, 2 inch 5 ft screen, 10 $40.00 each 6 240 PVC casing, 5 ft lengths for riser $20.95 each 6 125.7 2 in PVC cap $4.54 each 6 27.24 2 inch PVC SCH 40 adaptor $2.61 each 6 15.66 concrete mix $6.47 each 2 12.94 sand $5.97 each 3 17.91

$463.33

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00

Lithologic Profile / Piezometer Installation Monitoring Well Installation Kit $325.00 day 1 $325.00 Expendables $40.00 day 1 $40.00

Interior Soil Borings, Soil Sampling Soil Sampling through concrete kit $235.00 day 2 $470.00 Expendables $40.00 day 2 $80.00

MAGS Well Installation Soil Assessment Kit $175.00 day 2 $350.00 Expendables $40.00 day 2 $80.00

MAGS Testing Construction Pilot Test Kit $360.00 day 2 $720.00 Portable Generator $70.00 day 2 $140.00 Regen Blower $180.00 day 2 $360.00 GPS $175.00 day 2 $350.00 Expendables $40.00 day 2 $80.00

Groundwater Screenpoint Sampling Shallow Groundwater Monitoring Kit $290.00 day 2 $580.00 Expendables $40.00 day 2 $80.00

Exterior Soil Borings / Sediment Soil Assessment Kit $175.00 day 1 $175.00 Expendables $40.00 day 1 $40.00

Monitoring Well Installation Oversight Monitoring Well Installation Kit $325.00 day 2 $650.00 Expendables $40.00 day 2 $80.00

Monitoring Well Sampling Shallow Groundwater Monitoring Kit $290.00 day 2 $580.00 Expendables $40.00 day 2 $80.00

$5,260.00

TOTAL EQUIPMENT PROCUREMENT

TOTAL EQUIPMENT

Page 10 Rev 3 Quality Cleaners ERIC_4771 SA 0552-384168

SubTask 4 Data Evaluation / Report DATE: Rev 12/12/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist, N Westmark Evaluate Data in report text, raw data, tables, figures 22 Prepare recommendations 3

Sign and seal documents 1 Total Hours: 26

Project Engineer, I King Prepare tables, develop MAGS results 20

Project Scientist, R Fetter Evaluate raw data 12

Develop Report 15

Provide data for map development 10

Submit ADaPT 0.5 Total Hours: 37.5

GIS/CADD Specialist, D Grove Developing drawings for evaluation and reporting 16

Administrative Assistant, B Meynardie Compile documents for report 4

TOTAL LABOR 103.5

VEHICLE TYPE RATE UNIT USEAGE

$0.00

$0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

Petrotech Southeast IDW transport and disposal 6 $125.00 $750.00 $0.00

TOTAL $750.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 $0.00 $0.00 $0.00

TOTAL EQUIPMENT $0.00

Page 11 Rev 3 Quality Cleaners ERIC_4771 SA 0552-384168

PSI Proposal Number: 0552-384168-Rev 3 December 12, 2022

Professional Service Industries, Inc.

5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634

Phone: (813) 886-1075 Fax: (813) 249-4916 www.intertek.com/building

Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

Attention: Ms. Skylar Schwed, Environmental Specialist II Contract Manager Telephone: (850) 245-8705, (850) 245-8795 Email: Skylar.Schwed@FloridaDEP.gov

Re: Site Assessment Cost Estimate and Level of Effort – Revision 3 Quality Cleaners ERIC_4771 14837 North Florida Avenue Tampa, Hillsborough County, Florida

Dear Ms. Schwed:

Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the proposal contained herein to provide a Site Assessment for the Quality Cleaners ERIC_4771, Tampa, Florida.

Included with this proposal is a discussion of project history to date, proposed scope of work, cost estimate and a proposed schedule for completion. According to the property appraiser’s website, the entity who is listed as owner in December 2022 is the same as on the Site Access form signed in May 2022.

PROJECT BACKGROUND

The Quality Cleaners is located at 14837 North Florida Avenue, Tampa, and is currently in use as a restaurant, Shelley’s Café. The site is located in Action Plaza on the east side of Florida Avenue approximately 1,500 feet south of Bearss Avenue in Tampa, Hillsborough County, Florida.

The site was also known as Premier Cleaners at one time. Documents available in OCULUS have used both Quality Cleaners as well as Premier Cleaners at various times. The site is more formally known as ERIC_4771, and for purposes of this report will be called Quality Cleaners. The drycleaning business started in 1983 using PERC, the year the strip plaza was constructed. According to the current owner of the property, all the dry equipment was removed by 2004.

The FDER(P) Site Investigation Section (SIS) conducted a groundwater study in the vicinity of Bearss Avenue and Florida Avenue in 1989 through 1991 to identify source(s) of volatile organic halogens (VOHs) detected in several area private wells.

mailto:Skylar.Schwed@FloridaDEP.gov

FDEP – Quality Cleaners, ERIC_4771

Four monitoring wells were installed by SIS to evaluate Quality Cleaners as a source of VOH groundwater contamination, labeled as NF-27S, NF-28S, NF-1S and NF-1D. Groundwater flow at the time of the SIS study was evaluated to be generally towards the south-southeast. A mounding effect was present at the Action Plaza which could be interpreted as localized radial flow.

The study concluded that VOH concentrations likely originated from Quality Cleaners. The study also concluded that VOHs present in the New Life Church supply well and other private wells located down gradient originated from Quality Cleaners. The study additionally presented documentation that a second VOH plume in the area originated from the McNatt’s Cleaners located in the Bearss Plaza, north north-west of the Quality Cleaners, located upgradient from the Quality Cleaners.

During the site visit in 2022 in preparation for the Site Assessment Work Plan, PSI identified two existing monitoring wells present at Action Plaza (NF-27S and NF-28S). Depth to water in NF-28S was measured in August 2022 at 8.35 feet below top of casing. An attempt was made to locate the monitoring wells (NF- 1S and NF-1D), installed at the New Life Church (currently La Verdad Church) located southeast of Action Plaza, however they could not be located. The water supply well present at La Verdad Church was observed to be out of service. Based on a review of the SIS soil boring logs depth to groundwater is estimated to range from 5 to 8 feet bls.

A Site Assessment Work Plan was submitted by PSI, revised per FDEP suggestions, resubmitted and approved in August 2022, and follows the guidelines presented in the July 2022 FDEP Contractor’s Workshop

PSI, therefore, proposes to conduct the Site Assessment at the Quality Cleaners, as presented below.

1. Pre-Project Activities

• Utility Clearance/ Well Permits/ GPR Survey

• Professional Land Survey

• Existing Monitoring Well Sampling

2. Initial Mobilization

• Lithologic Boring

• Piezometer Installation

• Interior Soil Borings / Soil Sampling/ MAGS Well Installation

• Interior Monitoring Well Installation

• MAGS Testing

• Groundwater Screenpoint Sampling- Geoprobe (Direct Push)

• Exterior Soil Boring Installation / Soil Sampling

• Monitoring Well Installation

• Monitoring Well Sampling and Analysis (including PFAS analytes to be submitted separately)

PROPOSED SCOPE OF WORK

Subtask 1. Project Management

This scope is provided for in the template worksheets.

Subtask 2. Notification/ Utility Locate / GPR Survey / Land Survey / Existing Monitoring Well

Sampling

Prior to mobilizing field crews, PSI will provide several site assessment preparation elements.

2.1 Notification - The tenant and/or owner of the property will be notified of the planned field activities.

2.2 Utility locates - Utility locates will be called in using 811 Sunshine.

2.3 GPR – A ground penetrating radar (GPR) survey will be performed to determine the presence and location of subsurface utilities leading up to the building.

2.4 Land Survey – A Specific Purpose Survey with locations of improvements will be performed by a

Florida Licensed Surveyor and Mapper. T

2.5 Existing Well Sampling - Two existing monitoring wells, NF-27S and NF-28S, will be sampled and analyzed for VOHs and VOAs by EPA Method 8260.

Subtask 3. Initial Mobilization

PSI will perform the following elements during the initial mobilization.

3.1 Lithologic Boring Installation - Continuous lithologic profile to 28 feet bls or the top of Hawthorn

Clay will be performed utilizing a DPT rig equipped with a macrocore soil sampling system.

3.2 Piezometer Installation – Two sets of piezometers will be installed.

One set of piezometers will be installed in a cluster configuration at the rear door to 16 feet bls.

The piezometers will then be converted to monitoring wells for later use in obtaining groundwater quality information.

3.3 Interior Soil Borings / Soil Sampling/ MAGS Well Installation – Seven soil borings will be installed inside the building near the former drycleaning machine, storage area and floor drain and will be hand-installed with a core drill and hand auger to the water table. Field screening will be conducted with an OVA-PID. Sample depth intervals will follow FDEP protocols and include 0-0.5 feet, 0.5 - 2 feet, 2-4 feet, 4-6 feet bls and 6-8 feet bls. Additional depth intervals may be added if the depth to water is deeper than the current estimate of 8 feet bls. Soil samples will be analyzed for VOHs by EPA Method 8260 and VOAs.

Five MAGS wells will be installed inside soil borings advanced inside the building and one outside the front door and positioned as close as possibly to the inside of the tenant space where the dryclean machine was formerly located. The MAGS wells will be installed approximately 1-foot above the groundwater table. Each MAGS well will be installed to approximately 7 feet bls and constructed with 2-inch diameter 5-foot lengths of screen (0.01-inch slot size) and 2 feet of casing.

The MAGS wells will be completed at the surface with a 2-inch bronze metal cleanout plug. The MAGS wells will be installed as permanent for later use as SVE wells, if necessary.

3.4 Interior Monitoring Well Installation - A two-inch diameter monitoring well will be installed in one of the soil borings inside the building near the former drycleaning machine location. The well be installed to approximately 13 feet bls (if possible) with 5 to 10 feet of screen (0.01-inch slot size). The well will be completed at the surface with a 2-inch bronze metal cleanout plug.

3.5 MAGS Testing - A well head assembly will be constructed to allow for vacuum, flow and temperature measurements from each MAGS point, and for each portion of the test. During each MAG point test, flow rate, well-head vacuum, and vacuum influence (measured from other MAG points, existing vacuum monitoring points and the horizontal SVE wells) will be measured approximately every 15- minute interval. The vacuum will be varied at the well head, starting from a low applied vacuum and incrementally increasing the vacuum. During each applied vacuum, the vapor flow rate will be measured for the purpose of determining the relationship of applied vacuum to flow rate. During this test, at each vacuum level, the vacuum influence will be measured from the nearby MAGs points or vapor monitoring points to assess the Radius of Influence (ROI). This test will also provide an indication of the maximum well head vacuum without excessive water entrainment. Vapor samples will be collected using SUMMA® canisters for analysis of volatile organic compounds using EPA Method TO-15. It is anticipated that one vapor sample will be collected for each well head test. The sample will be collected at the end of the test.

3.6 Groundwater Screenpoint Sampling- Geoprobe (Direct Push) - Based on groundwater sampling data provided from the existing on-site monitoring wells, soil assessment and MAGS testing data, groundwater screenpoint sampling will be used to determine additional horizontal and vertical groundwater contaminant plume configuration. A Direct Push (DPT) drilling rig will be used to evaluate vertical migration of potential contamination from the former drycleaner at up to eight locations. It is anticipated that two depth intervals will be evaluated from site lithology and the intervals will be determined from continuous macrocore samples at each location. Based on previous assessment information, the depth intervals will be anticipated at 10-14 feet bls and 24-

28 feet bls. The groundwater samples will be submitted to a fixed-base laboratory for VOH and VOA analysis on a standard turnaround time.

3.7 Exterior Soil Boring Installation/ Soil & Sediment Sampling – Exterior soil borings will be performed near the rear door, the stormwater inlet at the rear of the former Quality Cleaners and the dumpster.

Sediment samples will be collected from the stormwater sewer inlet basin and the stormwater outfall located west of the former Quality Cleaners. Soil samples will be collected from hand augered soil samples and macrocore sleeves and screened with an OVA-PID. As previously discussed, the water table is estimated to be approximately 8 feet bls. Soil samples will be retained for laboratory analysis from depth intervals 0 – 0.5 feet, 0.5-2 feet bls, 2-4 feet bls, 4-6 feet bls and 6-8 feet bls. Soil samples will be analyzed for VOHs and VOAs by EPA Method 8260.

3.8 Monitoring Well Installation – Five additional shallow monitoring wells will be installed, of which the locations and specifications will be based on field conditions. For budgetary purposes, it is anticipated that five shallow wells (about 15 feet deep) and one deep well (about 28 feet deep) will be installed. Each shallow monitoring well will be installed with a DPT drilling rig and will be constructed with 1-inch diameter 10-foot lengths of pre-packed screen (0.01-inch slot size) and packed with 20/30 silica sand followed by a 30/65 silica sand seal and grouted to surface. The deep well will be constructed with 1-inch diameter 5-foot lengths of pre-packed screen (0.01-inch slot size) and packed with 20/30 silica sand followed by a 30/65 sand seal and grouted to surface.

The wells will be completed at the surface with an 8-inch manway and a 2 ft by 2 ft concrete pad.

Each well will be developed until the discharge water is visually clear. All drill cuttings and development fluids will be containerized for later transport and disposal.

3.9 Monitoring Well Sampling and Analysis – The newly installed monitoring wells will be sampled using protocols in accordance with FDEP Standard Operating Procedures. The samples will be collected for laboratory analysis for parameters in EPA Method 8260 for VOAs and VOHs. The laboratory will use protocols approved by the National Environmental Laboratory Analytical Conference (NELAC). Equipment blanks and duplicates will not be collected for Quality Assurance/Quality Control purposes, per recent FDEP Guidelines. Top of casing elevations will be measured for all located wells to an established benchmark. Depth to groundwater will be recorded at each well so that a groundwater iso-contour flow map can be generated. Four newly installed monitoring wells will be sampled for the potential presence of PFAS compounds. We anticipate selecting a source area inside the building, outside the back door and two sidegradient or downgradient wells with subsequent analysis by the FDEP Central laboratory in Tallahassee.

3.10 Investigative Derived Waste (IDW) – All soil cuttings, development water and purge water will be containerized in 55-gallon drums, labeled and staged on-site for characterization. Once the results are received, the drums will be transported for disposal / treatment at an approved facility.

It is estimated a total of 6 drums will be utilized for the assessment.

Subtask 4. Data Evaluation

The data collected from the activities described above will be evaluated and recommendations for additional assessment will be presented to the FDEP for approval prior to proceeding with more field activities, potentially consisting of additional permanent monitor wells and subsequent sampling to complete the Site Assessment process.

Deliverables – The following deliverables will be submitted to the FDEP upon completion of the above described subtasks:

• Field notes, boring logs, construction logs, groundwater sampling logs submittal.

• Site Assessment Report which will include a conceptual site model.

• A separate email deliverable will be submitted upon receipt of the PFAS results if the analytical data reveals concentrations above the Health Advisory Level (HAL) or Provisional Groundwater criteria of 70 nanograms per liter (ng/L = parts per trillion). If the levels are below the HAL, the results will be submitted to the FDEP concurrent with the SAR.

• ADaPT deliverable - The laboratory data will be validated using the FDEP’s Automated Data Processing Tool (ADaPT) program to ensure that all required quality control targets were met.

The data will be uploaded to the FDEP portal.

• Investigative Derived Wastes (IDW) manifests.

Quality Assurance / Quality Control – All field work will be performed in accordance with the most current version of the FDEP Standard Operating Procedures guidelines. In addition, an FDEP approved fixed-base laboratory will perform all analyses associated with the horizontal and vertical extents of the associated potential contaminant plume at the subject site. According to 2022 Waste Site Cleanup Section guidelines, no field blanks, equipment blanks, or duplicates will be collected or analyzed.

Health and Safety – Drilling and sampling operations will be directed by a PSI field supervisor, and field personnel will be OSHA trained in accordance with 29 CFR 1910.120. Prior to subsurface drilling activities, PSI will notify the utility service alert in accordance with local practices.

COST ESTIMATE AND SCHEDULE

The estimated cost to perform the Site Assessment is shown on the attached Cost Estimate and Level of Effort sheets, which includes sampling and analysis and the report deliverable. The deliverable and invoice schedule is presented as follows.

Quality Cleaners ERIC_4771 Deliverables Deliverable Due Date SubTask 1 Project Management Upon completion of Task

Assignment SubTask 2 GPR, Survey, Existing Well Sampling March 25, 2023

SubTask 3 Assessment August 10, 2023

SubTask 4 Data Evaluation / Report September 19, 2023

Invoice Schedule

Requirements for Invoice Submittal Amount to be Invoiced SubTask 1 Project Management $4,337.14

SubTask 2 GPR Field Notes, Survey Notes & Lab Results of Well Sampling

$11,173.79

SubTask 3 Field Logs, Lab Results $60,639.88

SubTask 4 Site Assessment Report, IDW manifests $11,937.59

Total: $88,088.40

All PSI services will be conducted in accordance with the terms and conditions contained within DEP Contract No. HW686, Bureau of Waste Cleanup, dated December 21, 2021. A copy of IDW manifests will be provided upon receipt.

PSI appreciates the opportunity to be of service to the FDEP. If you have any questions, please feel free to contact us at (813) 886-1075 or (813) 267-2519.

Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.

Douglas Coleman, PMP, CHMM, REM Nana Westmark, PG, CHMM Department Manager, Environmental Services Senior Geologist / Contract Manager

Enclosure: Cost Estimate Level of Effort Drilling Bids Subcontractor Quotes IDW Bids

Z:\552-Env\FDEP HW 686 Drycleaning, Main Contract\0552------Quality Cleaners SA\Proposals SA\Rev 3 Dec 12, 2022\Rev 3 Quality Cleaners ERIC_ 4771 SA 0552-384168.docx

Professional Service Industries, Inc. (Intertek-PSI) Request for Quotation

Facility Name Quality Cleaners Facility Location 14837 North Florida Avenue, Tampa Hillsborough County Facility ID ERIC_4771 FDEP Drycleaning Solvent Cleanup Program

Units Unit Rate Extended Price

1 575.00$ 575.00$

4 1,580.00$ 6,320.00$

Utility Locate - 811 and Private GPR (Geoview) 1 1,400.00$ 1,400.00$

Lithologic Boring with macrocores, per foot 28 2.00$ 56.00$

Piezometers, shallow, convert to monitor well 3 235.00$ 705.00$

Soil Borings with macrocores to 8 foot 3 20.00$ 60.00$

Groundwater screenpoints, 2 depths per boring 9 25.00$ 225.00$

5 235.00$ 1,175.00$

1 260.00$ 260.00$

Well development 9 -$

Well pad construction 9 125.00$ 1,125.00$

55-gallon DOT approved drums (each) 5 65.00$ 325.00$

Total: 12,226.00$

Former drycleaners is now a café, ashalt surface .

Signed PSI Purchase Order with General Conditions (attached) is required before working.

All equipment to be decontaminated prior to boring / well installation.

OSHA HazWOPER trained crew required.

Include per diem in cost, if necessary.

Estimated start date: Preferred to be in October or November 2022, please provide availability.

PFAS-free water is required for decontamination.

Address: 5709 1st Aven S, St Pete, FL

Phone: 727 328-0268

Email: marcelo@ambienttech.com

Contact: Marcelo Reis

Proposal #: 22209025

Marcelo Reis - V.P.

Name, Title.

One deeper well to 28 feet

Proposed Scope of Work: Lithologic Profiling, Piezometer Installation, Direct Push Soil Borings, Direct Push Groundwater

Screening, Monitoring Well.

1. One Lithologic Boring with marcrocores to ~28 feet

2. Three (3) piezometers to ~15 feet to be converted to shallow monitor wells.

3. Three (3) direct push soil borings to water table (~8 feet) with soil sampling and macrocores from

0.0 - 0.5 feet

0.5 - 2 feet

2 - 4 feet

4 - 6 feet

6 - 8 feet.

4. Nine (9) screenpoint for groundwater sampling at two depths per screenpoint boring:

groundwater samples from 8 - 12 feet groundwater samples from 24 - 28 feet

5. Five (5) additional shallow monitor wells (pre-pack is fine) to ~15 feet. 10 foot screen.

6. One (1) deep monitor wells to 28 feet (5 foot of screen)

Mobilization (lump sum)

Shallow monitor wells

Rig Charge (per day)

Page 1 of 3 22209025 INtertek Tampa, FL

ATI Companies

Sonic Auger DPT Injection Well Abandonment

DATE: 9/20/2022

ESTIMATE #: 922060

PFAS Protocals

ID QTY Unit Rate TOTAL

1 1 ls 600.00$ 600.00$

2 Per Diem 3 night 250.00$ 750.00$

3 DPT Rig and Crew 4 day 1,600.00$ 6,400.00$

3a 420 M Indoor Rig (Indoor Well) 1 each 450.00$ 450.00$

4 Materials: Water Sampling Expendables 18 each 12.00$ 216.00$

5 Materials: Macrocore Liners 11 each 3.00$ 33.00$

6 Materials: Borehole Grouting w/Concrete Cap 13 each 20.00$ 260.00$

7 Materials:1" Sch 40 PVC Well Installation 148 foot 4.00$ 592.00$

8 Materials: 1" x 5' PVC .010 Prepack Screen, 3" Exp Point 1 each 95.00$ 95.00$

9 Materials:(2) 1" x 5' PVC .010 Prepack Screen, 3" Exp Point 8 each 175.00$ 1,400.00$

10 2' x 2' Concrete Pad w/8" BD Completion 9 each 125.00$ 1,125.00$

11 Well Development (Up to 1/2 hour with pump) 9 each 50.00$ 450.00$

12 Refurbished Drums (Soil) As Needed 0 each 65.00$ -$

13 Refurbished Drums (Water) Estimated 4 each 95.00$ 380.00$

14 Decon Pit 1 each 250.00$ 250.00$

15 Concrete Coring Machine/Generator (Indoor Work) 1 each 250.00$ 250.00$

16 Permits (N/A for FDEP Projetcs) -$

Subtotal 13,251.00$

Todd Hodgson

Todd Hodgson TOTAL 13,251.00$ Partner

(1) 1" x 28' PVC MW w/5' of .010 Prepack Screen, 8" BD Completion, No Soil Sampling

(3) DPT Soil Borings to 8' w/Macrocores and Lab Sample, Grout Borehole/Patch

Nana Westmark, PG, CHMM

(1) 1" x 15' PVC MW w/10' of .010 Prepack Screen, 5" BD Completion w/Donut Pad, Soil Sampling (Indoors)

Drum Purge and Decon Water

Project Description:

(4) 1" x 15' PVC MW w/10' of .010 Prepack Screen, 8" BD Completion, No Soil Sampling

(1) DPT Litho Boring to ~28'. Borehole Abandonment

(9) DPT GW Profiling to 28' BLS at 2 Intervals (8-12' and 24-28'), Grout Borehole/Patch

(3) 1" x 15' PVC PZW w/10' of .010 Prepack Screen, 8" BD Completion.

Tampa, Florida 33634 Tampa, Florida 5801 Benjamin Center Drive, Ste. 112

THANK YOU FOR YOUR BUSINESS!

DESCRIPTION

"Actual quantities used and days onsite will be invoiced"

Completion: 4 days

Mobilization

Locations must be accessible with track mounted Sonic Rig

Damage to utilities on private property are the responsibility of the client Utility Locates on Private Property are the responsibility of the client

Borehole Clearance to 5’ bgs beyond 20 minutes may require a change order for additional time and costs.

(813) 353-5755 DPT Soil/GW Sampling/Well Installation

PROJECT

Quality Cleaners 14837 N Florida Avenue

CUSTOMER

Intertek PSI

2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586

If you have any questions concerning this proposal contact Todd Hodgson at (407) 426-7885 at Todd@drillprollc.com.

2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586

Professional Service Industries, Inc. (Intertek-PSI) Request for Quotation

Facility Name Quality Cleaners Facility Location 14837 North Florida Avenue, Tampa Hillsborough County Facility ID ERIC_4771 FDEP Dry-cleaning Solvent Cleanup Program

Units Unit Rate Extended Price

1 1,150.00$ 1,150.00$

0 1,875.00$ -$

Utility Locate 1 100.00$ 100.00$

Lithologic Boring with macrocores, per foot 28 25.00$ 700.00$

Piezometers, shallow, convert to monitor well 3 450.00$ 1,350.00$

Soil Borings with macrocores to 8 foot 3 18.00$ 54.00$

Groundwater screen points, 2 depths per boring 9 700.00$ 6,300.00$

5 675.00$ 3,375.00$

1 900.00$ 900.00$

Well development 9 150.00$ 1,350.00$

Well pad construction 9 225.00$ 2,025.00$

55-gallon DOT approved drums (each) 5 70.00$ 350.00$

Total: 17,654.00$

Former drycleaners is now a café, asphalt surface .

Signed PSI Purchase Order with General Conditions (attached) is required before working.

All equipment to be decontaminated prior to boring / well installation.

OSHA HazWOPER trained crew required.

Include per diem in cost, if necessary.

Estimated start date: Preferred to be in October or November 2022, please provide availability.

PFAS-free water is required for decontamination.

Address: Preferred Drilling Solutions, Inc.

Phone: 727-561-7477 Email: kevin@pdsflorida.com Contact: Kevin Bonacum

Name, Title.

One deeper well to 28 feet

Proposed Scope of Work: Lithologic Profiling, Piezometer Installation, Direct Push Soil Borings, Direct Push Groundwater Screening, Monitoring Well.

1. One Lithologic Boring with marcrocores to ~28 feet

2. Three (3) piezometers to ~15 feet to be converted to shallow monitor wells.

3. Three (3) direct push soil borings to water table (~8 feet) with soil sampling and macrocores from

0.0 - 0.5 feet

0.5 - 2 feet 2 - 4 feet 4 - 6 feet 6 - 8 feet.

4. Nine (9) screen point for groundwater sampling at two depths per screen point boring:

groundwater samples from 8 - 12 feet groundwater samples from 24 - 28 feet

5. Five (5) additional shallow monitor wells (pre-pack is fine) to ~15 feet. 10 foot screen.

6. One (1) deep monitor wells to 28 feet (5 foot of screen)

Mobilization (lump sum)

Shallow monitor wells

Rig Charge (per day)

Page 1 of 3 Intertek-PSI, Quality Cleaners, Tampa, FL

10220 U.S. Highway 92 East Phone: 813-621-4929 Tampa, Florida 33610 Fax: 813-621-7194 Web: www.survtechsolutions.com Email: Sales@survtechsolutions.com

Tuesday, September 20, 2022

Nana Westmark Intertek-PSI 5801 Benjamin Center Dr., Suite 112, Tampa, FL 33634

RE: Proposal for Services for Quality Cleaners Subsurface Utility Designation located at 14837 N Florida Ave, Tampa, FL, 33613; Folio No.: N/A; Estimate No.: 222021

Dear Nana, SurvTech Solutions, Inc. is pleased to submit the following information for your consideration in selecting a firm to perform the necessary services, as noted above. We feel that you will find SurvTech Solutions, Inc. is well qualified to accomplish all services set forth in the request for proposal. Our outstanding staff of professional, technical, and support personnel has extensive and varied qualifications.

The lump-sum cost for the project will be $4,380.00, with an estimated time frame of 49 days from notice to proceed. Please see attached scope of work for a detailed breakdown of costs and services. If a quicker schedule is needed, please contact us, and we will try to accommodate your schedule.

If this proposal is acceptable, please sign the attached contract and send it to SurvTech Solutions via fax, email, or U.S. Mail. SurvTech cannot start said project without having a signed contract in place. If your firm wishes to use its own in-house contract or purchase order, then please forward them to SurvTech for review and signatures. SurvTech Solutions, Inc. appreciates this opportunity to submit this proposal for services. We look forward to serving Intertek-PSI on this project.

Respectfully submitted, SurvTech Solutions, Inc.

Florida Licensed Business No. 7340

Anthony Smith SUE Project Manager http://www.survtechsolutions.com/

PROPOSAL 222021

Subsurface Utility Designation $1,920.00

Utility Survey Collection $1,310.00

SUE PM, QA/QC Field Check, and Clerical $1,150.00

TOTAL $4,380.00

Scope of Services:

Subsurface Utility Designation with Utility Survey Collection

All SurvTech SUE services abide by the standards set forth by ASCE under (CI/ASCE 38-02)

A. Subsurface Utility Designation:

1. By use of Ground Penetrating Radar (GPR) and Electromagnetic Induction (EM), Attempt to horizontally locate and field mark (paint & flags) all public subsurface utilities found excluding service lines, gravity sewer lines and irrigation the areas encompassed by the blue polygons on the attached Exhibit “B”.

Deliverables shall be surface marking (paint and/or flags) of horizontal location of found subsurface utilities and a utility designation field sketch(s) of the project area reflecting all obtained relevant data for your use.

B. Utility Survey Collection:

1. Survey collect all utility data using GPS or conventional surveying equipment.

2. Survey control will be furnished by client unless otherwise negotiated and stated hereon.

3. SurvTech shall only locate and map found utilities. Utilities will be overlaid on a rectified ortho-photo from LABINS.org. No other mapping is included unless specifically noted below.

4. Elevation and depth data is NOT included in this proposal.

5. Final survey shall be made available to client in electronic format, AutoCAD version 2018(or older if requested) and Adobe PDF format. File will be sent by email unless the client specifically requests a CD of the drawing file.

Exhibit "A" SurvTech Solutions, Inc. Short Form Agreement

General Terms of Agreement for Consulting (Surveying and Mapping) Services

1. Client hereby agrees to retain SurvTech Solutions, Inc. to perform professional land surveying services as described herein. This Agreement applies only to the specific project identified herein.

2. General Responsibility: SurvTech Solutions, Inc. agrees that we shall act as an independent contractor and shall perform the services provided for in this Agreement in accordance with the generally accepted standard of care of SurvTech Solutions, Inc.'s profession.

3. SurvTech Solutions, Inc. agrees to perform the services set forth in attached “Proposal of Services” ("services").

4. Payment: Client shall be invoiced upon completion of the project . . Client agrees to pay invoice(s) within thirty (30) days of its receipt. Client further agrees to pay interest on all amounts invoiced and not paid or objected to for valid cause in writing within said thirty (30) day period at the rate of eighteen (18) percent per annum (or the maximum interest rate permitted under applicable law), until paid. Client agrees to pay SurvTech Solutions, Inc.'s cost of collection of all amounts due and unpaid after ninety

(90) days, including court costs and reasonable attorney's fees. SurvTech Solutions, Inc. shall not be bound by any provision or agreement requiring or providing for arbitration of disputes or controversies arising out of this agreement, any provision wherein SurvTech Solutions, Inc. waives any rights to a mechanics' lien, or any provision conditioning SurvTech Solutions, Inc.’s right to receive payment for its work upon payment to Client by any third party. These General Conditions are notice where required, that SurvTech Solutions, Inc. shall file a lien whenever necessary to collect past due amounts. Failure to make payment within 30 days of invoice shall constitute a release of SurvTech Solutions, Inc. from any and all claims which Client may have whether in tort, contract or otherwise and whether known or unknown at the time.

5. Insurance: For any services provided…