CN-370000-HW686-DC002A.pdf

PDF 1 MB Posted

Attached to
Master Agreement FL|HW686|26652fe61cf76d14a6798f2369f5dddb
Contract number
HW686
Issued by
Florida

About this file

This is a Task Assignment (TA) document executed between the State of Florida Department of Environmental Protection (FDEP) and Professional Service Industries, Inc. (PSI), an Intertek company, pursuant to Contract Number HW686. The Task Assignment Number is DC002A and was effective through June 30, 2023. The primary contact for FDEP was Walsta Jean-Baptiste (Department Project Manager) and for PSI was Nana G. Westmark (Contractor Project Manager).

The Task Assignment authorizes PSI to manage remedial equipment used by the Drycleaning Solvent Cleanup Program housed at the Lakeland storage facility, including coordination of equipment delivery and pickup, monthly maintenance of equipment, and quarterly equipment storage oversight. The scope of work consists of six subtasks: project management, contractor changeover, and quarterly equipment storage facility oversight for Quarters 1-4. PSI is responsible for motor inspections upon equipment receipt and monthly motor maintenance using manual means, maintaining equipment transfer documentation, providing quarterly Excel spreadsheets and photographs, and coordinating contractor access to the facility. The total Task Assignment value is $50,428.57, distributed as follows: Quarter 1 ($13,634.68), Quarter 2 ($11,336.28), Quarter 3 ($11,336.28), and Quarter 4 ($14,121.33). Payment is based on FDEP approval of quarterly Equipment Storage Status Reports. The cost estimate includes 251 hours of labor, equipment storage rental of $19,350.00 annually, vehicle rental costs, and field expenses. PSI assumes no liability for stolen property or vandalism and is responsible for paying facility rent to the property owner.

View the file

Other files

File Type Posted
CN-370000-HW686-DC001D.pdf PDF
CN-370000-HW686-DC002F.pdf PDF
CN-370000-HW686-DC002G.pdf PDF
CN-370000-HW686-DC002H.pdf PDF
CN-370000-HW686-DC003A.pdf PDF
CN-370000-HW686-DC003B.pdf PDF
CN-370000-HW686-DC003E.pdf PDF
CN-370000-HW686-DC003G.pdf PDF
CN-370000-HW686-DC004C.pdf PDF
CN-370000-HW686-DC004E.pdf PDF
CN-370000-HW686-DC007A.pdf PDF
CN-370000-HW686-DC007C.pdf PDF
CN-370000-HW686-DC007D.pdf PDF
CN-370000-HW686-DC009C.pdf PDF
CN-370000-HW686-DC009E.pdf PDF
CN-370000-HW686-DC010C.pdf PDF
CN-370000-HW686-DC011A.pdf PDF
CN-370000-HW686-DC012B.pdf PDF
CN-370000-HW686-DC013A.pdf PDF
CN-370000-HW686-DC014A.pdf PDF
CN-370000-HW686-DC016A.pdf PDF
CN-370000-HW686-DC018A.pdf PDF
CN-370000-HW686-DC019B.pdf PDF
CN-370000-HW686-DC01ACO4.pdf PDF
CN-370000-HW686-DC020C.pdf PDF
CN-370000-HW686-DC023A.pdf PDF
CN-370000-HW686-DC024A.pdf PDF
CN-370000-HW686-DC025A.pdf PDF
CN-370000-HW686-DC026B.pdf PDF
CN-370000-HW686-DC028A.pdf PDF
CN-370000-HW686-DC03DCO2.pdf PDF
CN-370000-HW686-DC04ECO1.pdf PDF
CN-370000-HW686-DC07BCO1.pdf PDF
CN-370000-HW686-DC07BCO3.pdf PDF
CN-370000-HW686-DC09DCO1.pdf PDF
CN-370000-HW686-DC11BCO1.pdf PDF
CN-370000-HW686-DC13BCO1.pdf PDF
CN-370000-HW686-DC14BCO3.pdf PDF
CN-370000-HW686-DC14DCO1.pdf PDF
CN-370000-HW686-DC15BCO1.pdf PDF
CN-370000-HW686-DC15DCO1.pdf PDF
CN-370000-HW686-DC16BCO1.pdf PDF
CN-370000-HW686-DC18CCO1.pdf PDF
CN-370000-HW686-DC21BCO1.pdf PDF
CN-370000-HW686-DC27BCO1.pdf PDF
CN-370000-HW686-FIL10.pdf PDF
CN-370000-HW686-FIL6.pdf PDF
CN-370000-HW686-FIL9.pdf PDF
CN-370000-HW686-HW002A.pdf PDF
CN-370000-HW686-HW011A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW686

DC002A Completion June 30, 2023

This Task Assignment authorizes Professional Service Industries, Inc. (PSI) to manage remedial equipment used by the Drycleaning Solvent Cleanup Program currently housed at the Lakeland storage facility including coordination of delivery and pick up of equipment and monthly maintenance of equipment in accordance with the PSI Scope of Work, cost estimate, and schedule received on February 8, 2022.

Walsta Jean-Baptiste 850-245-8973 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

PSI

PSI

Nana G. Westmark 813-886-1075

NA

NA

NA

$ 0.00 ✔ $ 50,428.57

$ 0.00

$ 50,428.57

Scope of Work

Nana Westmark

Contract Manager

Nana G Westmark Digitally signed by Nana G Westmark Date: 2022.02.14 09:45:32 -05'00'

Jennifer A. Farrell

Digitally signed by Jennifer Farrell Date: 2022.02.11 13:14:48 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Quarter 1 Equipment Storage Status Report - Subtasks 2 and 3 07/20/2022

Quarter 2 Equipment Storage Status Report - Subtask 4 10/20/2022

Quarter 3 Equipment Storage Status Report - Subtask 5 01/20/2023

Quarter 4 Equipment Storage Status Report and Project Management - Subtasks 1 and 6 04/20/2023

FDEP approval of Quarter 1 Equipment Storage Status Report - Subtasks 2 and 3 $ 13,634.68

FDEP approval of Quarter 2 Equipment Storage Status Report - Subtask 4 $ 11,336.28

FDEP approval of Quarter 3 Equipment Storage Status Report - Subtask 5 $ 11,336.28

FDEP approval of Quarter 4 Equipment Storage Status Report and Project Management - Subtasks 1 and 6 $ 14,121.33

$ 50,428.57

HW686

DC002A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton

Secretary

Memorandum

TO: HW686 Contract File FROM: Walsta Jean-Baptiste, Contract Manager

SUBJECT: Annual Equipment Storage Oversight

DC002A

DATE: February 10, 2022

This Task Assignment authorizes Professional Service Industries, Inc. (PSI) to manage remedial equipment used by the Drycleaning Solvent Cleanup Program currently housed at the Lakeland storage facility including coordination of delivery and pick up of equipment and monthly maintenance of equipment in accordance with the PSI Scope of Work, cost estimate, and schedule received on February 8, 2022.

PSI has been selected to take over equipment storage facility oversight under the new contract.

Changes to the cost estimate include an adjustment so that the monthly lease is between PSI and the subcontractor. There was no change in costs related to the adjustment.

The cost related to this Task Assignment is $50,428.57 with 251 hours.

PSI Proposal Number: 0552-364986-Rev 1

February 1, 2022, Revised February 8, 2022 www.intertek.com/building

Professional Service Industries, Inc.

5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634

Phone: (813) 886-1075 Fax: (813) 249-4916

Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

Attention: Mr. Billy Hessman, Environmental Consultant Phone: (850) 245-8705 main, or (850) 245-8972 direct Email: Billy.Hessman@FloridaDEP.gov

Re: Proposal for FDEP Bureau of Waste Cleanup Equipment Storage Facility Management – Rev 1 State Road 33 Lakeland, Polk County, Florida Contract No. HW686

Dear Mr. Hessman:

Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the revised proposal contained herein to provide for management of the Florida Department of Environmental Protection’s Bureau of Waste Cleanup (FDEP BWC) Equipment Storage Facility in Lakeland, Florida. Included with this proposal is a discussion of proposed scope of work, cost estimate and a proposed schedule for completion.

PROJECT BACKGROUND

PSI understands that the FDEP BWC routinely houses remediation equipment for use under the Drycleaning Solvent Cleanup Program and other state funded programs. Various remediation equipment is stored at an existing facility located off State Road 33, in Lakeland, which is maintained and housed on behalf of the FDEP. The property is owned by the Fountain RV Park, which is located adjacent to the FDEP BWC Lakeland Equipment Storage Facility. The property is enclosed with a padlocked fence and currently has no utilities connected to the property (i.e. no power or water is available on-site). The FDEP requests that the facility be manned approximately five days per quarter to allow other contractors under the Waste Cleanup Program to test the remediation equipment and to access, collect and transport that equipment to various cleanup sites.

PSI proposes to provide yard/equipment management services to the FDEP and assumes the following:

mailto:Billy.Hessman@FloridaDEP.gov

FDEP – Equipment Storage Facility PSI Proposal No. 0552-364986-Rev 1

1. Equipment Storage Facility property is owned by the Fountain RV Park, which is approximately 1

– 2-acre property, with a 6-foot chain link fence and locked padlock.

2. No power, water, or office trailer is available on-site.

3. Mowing or keeping vegetation down is the responsibility of others.

4. PSI will be available with an approximately one-week notification to receive incoming equipment and allow contractors to return FDEP-owned equipment as directed by the BWC.

5. Contractors will arrange with PSI to visit the site and inspect existing FDEP-owned remediation equipment.

6. PSI will spin the motors upon receiving equipment using manual (screwdriver or similar) means to determine if motors are free spinning.

7. PSI will spin the motors on all stored equipment monthly with a screwdriver.

8. No repairs of any equipment in the Storage Yard are required to be conducted by PSI.

9. PSI assumes no liability for stolen property or vandalism.

10. PSI will pay rent fee as outlined in the FDEP Task Assignment to property owner.

11. PSI will provide the following Deliverables on a quarterly basis.

a. Excel spreadsheet of equipment on site.

b. Photos of equipment when received.

c. Maintain chain of custody (equipment transfer forms) to be provided by FDEP for removal or receiving equipment, and submit to FDEP.

12. Trailer license tags are to remain with equipment.

13. Signage on existing equipment remains with equipment (store in trailer, if possible).

PROPOSED SCOPE OF WORK

The proposal contained herein consists of annual management for the equipment storage family.

Specifically, the proposed scope of work consists of the following subtasks:

Subtask 1 - Project Management

This scope is provided for in the template worksheets.

Subtask 2 - Contractor Changeover

PSI will work with the property owner/ management to transfer information from Earth Systems to PSI.

PSI will also conduct a site reconnaissance to review existing property and equipment conditions, fencing, locks, and parking availability.

Subtask 3 - Quarter 1, Equipment Storage Facility Oversight

PSI will coordinate remediation equipment transfers into and out of the Lakeland facility with other contractors. This will include providing a flexible schedule for routine equipment deliveries, providing personnel to access the site for system inspection and testing, and providing direction for parking system to minimize site disruption. Five days per quarter are proposed.

PSI will also open the motors of incoming remediation systems to provide documentation of system conditions prior to entry into the equipment facility.

The deliverable for the Quarter consists of a current equipment availability spreadsheet to include:

• Equipment delivery dates,

• Contractors visiting facility,

• Remediation system equipment components,

• Photographs of incoming equipment.

Subtask 4 - Quarter 2, Equipment Storage Facility Oversight

PSI will provide similar services as described above in Quarter 1, Subtask 3.

Subtask 5 - Quarter 3, Equipment Storage Facility Oversight

PSI will provide similar services as described above in Quarter 1, Subtask 3.

Subtask 6 - Quarter 4, Equipment Storage Facility Oversight

PSI will provide similar services as described above in Quarter 1, Subtask 3.

COST ESTIMATE AND SCHEDULE

The estimated cost to perform the above described services is shown on the attached Cost Estimate and Level of Effort sheets. PSI services will be conducted in accordance with the terms and conditions contained within the State of Florida Department of Environmental Protection Standard Contract, Contract No. HW686, dated December 21, 2021. According to our understanding, the current Earth Systems’ Task Assignment runs through March 2022, therefore, PSI proposed to initiate work in March 2022 to allow turnover to be complete by April 2022 to minimize any disruption to facility operations.

• First Quarter Deliverable Equipment List for April – June 2022, due July 20, 2022

• Second Quarter Deliverable Equipment List for July- September 2022, due October 20, 2022

• Third Quarter Deliverable Equipment List for October – December 2022, due January 20, 2022

• Fourth Quarter Deliverable Equipment List for January – March 2023, due April 20, 2023.

PSI appreciates the opportunity to be of service to the FDEP. We look forward to working with you on this important project. If you have any questions, please feel free to contact us at (813) 886-1075.

Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.

Michael Rothenburg, PE, CIH Nana Westmark, PG, CHMM Senior Engineer / Department Manager Senior Geologist / Contract Manager

Enclosure: Cost Estimate Level of Effort

Z:\552-Env\FDEP HW 686 Drycleaning, Main Contract\0552------Equipment Storage Management\Proposal\PSI Equipment Storage 0552-364986.docx

FDEP COST ESTI MATEContractor: Professional Service Industries, Inc. (Intertek-PSI)

Date: 2/1/2022 Revised 2/8/2022

Task #: SubTask 1 Project Management SubTask 6 Quarter 4 - Equipment Storage Management

Site: Equipment Storage Facility SubTask 2 Contractor Turnover SubTask 7

Activity/Phase: SubTask 3 Quarter 1 - Equipment Storage Management SubTask 8

Project Manager: Nana Westmark SubTask 4 Quarter 2 - Equipment Storage Management SubTask 9

SubTask 5 Quarter 3 - Equipment Storage Management SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$55.84 Project Manager 18 18.1 $0.00 Principal Consultant 0 0 0 0 0 0 0 0 0 0

$62.64 Senior Engineer, MR 0 0 0 0 0 0 0 0 0 0 $55.84 Senior Geologist, NW 25 9 4 4 4 4 0 0 0 0

$0.00 Senior Scientist 0 0 0 0 0 0 0 0 0 0 $0.00 Certified Industrial Hygientist 0 0 0 0 0 0 0 0 0 0 $0.00 Certified Hazardous Materials Manager 0 0 0 0 0 0 0 0 0 0 $0.00 Florida Licensed Asbestos Consultant 0 0 0 0 0 0 0 0 0 0 $0.00 Project Manager 0 0 0 0 0 0 0 0 0 0

$36.06 Project Engineer, MM 0 0 0 0 0 0 0 0 0 0 $38.20 Project Engineer, IK 0 0 0 0 0 0 0 0 0 0 $30.56 Project Engineer, MK 0 0 0 0 0 0 0 0 0 0 $0.00 Project Geologist 0 0 0 0 0 0 0 0 0 0

$32.44 Project Scientist, SB 0 0 0 0 0 0 0 0 0 0 $29.86 Project Scientist, EL 0 0 0 0 0 0 0 0 0 0

$0.00 Project Scientist, RF 0 0 0 0 0 0 0 0 0 0 $0.00 QA Officer 0 0 0 0 0 0 0 0 0 0

$30.59 Remediation Specialist, RH 208 8 50 50 50 50 0 0 0 0 $24.84 GIS / CAD Specialist, CF 0 0 0 0 0 0 0 0 0 0

$0.00 Staff Engineer 0 0 0 0 0 0 0 0 0 0 $0.00 Staff Geologist 0 0 0 0 0 0 0 0 0 0

$24.27 Staff Scientist, BW 0 0 0 0 0 0 0 0 0 0 $30.30 Environmental Specialist, CC 0 0 0 0 0 0 0 0 0 0 $21.21 Environmental Specialist, MZ 0 0 0 0 0 0 0 0 0 0 $0.00 Administrative Assistant, BM 0 0 0 0 0 0 0 0 0 0

Total Hours 251 18 17 54 54 54 54 0 0 0 0

Direct Labor $8,767.35 $1,008.63 $747.28 $1,752.86 $1,752.86 $1,752.86 $1,752.86 $0.00 $0.00 $0.00 $0.00

Overhead 151.02% $13,240.45 $1,523.23 $1,128.54 $2,647.17 $2,647.17 $2,647.17 $2,647.17 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $22,007.80 $2,531.86 $1,875.82 $4,400.03 $4,400.03 $4,400.03 $4,400.03 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $2,520.00 $120.00 $600.00 $600.00 $600.00 $600.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $2,520.00 $120.00 $600.00 $600.00 $600.00 $600.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF PSI Intertek Page 1

FDEP COST ESTI MATEContractor: Professional Service Industries, Inc. (Intertek-PSI)

Date: 2/1/2022 Revised 2/8/2022

Task #: SubTask 1 Project Management SubTask 6 Quarter 4 - Equipment Storage Management

Site: Equipment Storage Facility SubTask 2 Contractor Turnover SubTask 7

Activity/Phase: SubTask 3 Quarter 1 - Equipment Storage Management SubTask 8

Project Manager: Nana Westmark SubTask 4 Quarter 2 - Equipment Storage Management SubTask 9

SubTask 5 Quarter 3 - Equipment Storage Management SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment Storage rental $19,350.00 $0.00 $4,837.50 $4,837.50 $4,837.50 $4,837.50 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $19,350.00 $0.00 $4,837.50 $4,837.50 $4,837.50 $4,837.50 $0.00 $0.00 $0.00 $0.00 Handling Fee $1,935.00 $0.00 $483.75 $483.75 $483.75 $483.75 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $21,285.00 $0.00 $5,321.25 $5,321.25 $5,321.25 $5,321.25 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $840.00 $40.00 $200.00 $200.00 $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $1,575.00 $75.00 $375.00 $375.00 $375.00 $375.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $2,415.00 $115.00 $575.00 $575.00 $575.00 $575.00 $0.00 $0.00 $0.00 $0.00

Subtotal $48,227.80 $2,531.86 $2,110.82 $10,896.28 $10,896.28 $10,896.28 $10,896.28 $0.00 $0.00 $0.00 $0.00 Completion Fee $2,200.77 $253.19 $187.58 $440.00 $440.00 $440.00 $440.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $50,428.57 $2,785.05 $2,298.40 $11,336.28 $11,336.28 $11,336.28 $11,336.28 $0.00 $0.00 $0.00 $0.00

REV: 02/03 CEF PSI Intertek Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Equipment Storage Facility SubTask 2 Contractor Turnover DATE: 2/1/2022 Revised 2/8/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist Contractor turnover documentation 4 Coordinate with property owner / leasee 4 Submit current equipment list provided by contractor 1

Remediation Specialist Site visit to document current conditions 6 travel, roundtrip 2

TOTAL LABOR 17

VEHICLE TYPE RATE UNIT USEAGE

Truck, site visit $120.00 day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00 $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 $75.00 day 1 $75.00

$0.00 Expendables $40.00 day 1 $40.00

$0.00 $0.00 $0.00

TOTAL EQUIPMENT $115.00

Construction / O&M Supplies

FINAL --7/24/96

SubTask 3 Quarter 1 - Equipment Storage Management DATE: 2/1/2022 Revised 2/8/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist Compile equipment list, photographs 3 Submit current equipment list to FDEP 1

Remediation Specialist Quarterly site visits 50

TOTAL LABOR 54

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Truck, site visit $120.00 day 5 $600.00 $0.00

TOTAL VEHICLE $600.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

Equipment Storage rental 3 monthly $1,612.50 $4,837.50 $0.00

TOTAL $4,837.50

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 Construction / O&M Supplies $75.00 day 5 $375.00

$0.00 Expendables 0 0 $40.00 day 5 0 $200.00

$0.00 $0.00 $0.00

TOTAL EQUIPMENT $575.00

SubTask 4 Quarter 2 - Equipment Storage Management DATE: 2/1/2022 Revised 2/8/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist Compile equipment list, photographs 3 Submit current equipment list to FDEP 1

Remediation Specialist Quarterly site visits 50

TOTAL LABOR 54

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Truck, site visit $120.00 day 5 $600.00 $0.00

TOTAL VEHICLE $600.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

Equipment Storage rental 3 monthly $1,612.50 $4,837.50 $0.00

TOTAL $4,837.50

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 Construction / O&M Supplies $75.00 day 5 $375.00

$0.00 Expendables 0 0 $40.00 day 5 0 $200.00

$0.00 $0.00 $0.00

TOTAL EQUIPMENT $575.00

SubTask 5 Quarter 3 - Equipment Storage Management DATE: 2/1/2022 Revised 2/8/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist Compile equipment list, photographs 3 Submit current equipment list to FDEP 1

Remediation Specialist Quarterly site visits 50

TOTAL LABOR 54

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Truck, site visit $120.00 day 5 $600.00 $0.00

TOTAL VEHICLE $600.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

Equipment Storage rental 3 monthly $1,612.50 $4,837.50 $0.00

TOTAL $4,837.50

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 Construction / O&M Supplies $75.00 day 5 $375.00

$0.00 Expendables 0 0 $40.00 day 5 0 $200.00

$0.00 $0.00 $0.00

TOTAL EQUIPMENT $575.00

SubTask 6 Quarter 4 - Equipment Storage Management

DATE: 2/1/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist Compile equipment list, photographs 3 Submit current equipment list to FDEP 1

Remediation Specialist Quarterly site visits 50

TOTAL LABOR 54

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Truck, site visit $120.00 day 5 $600.00 $0.00

TOTAL VEHICLE $600.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

Equipment Storage rental 3 monthly $1,612.50 $4,837.50 $0.00

TOTAL $4,837.50

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 Construction / O&M Supplies $75.00 day 5 $375.00

$0.00 Expendables 0 0 $40.00 day 5 0 $200.00

$0.00 $0.00 $0.00

TOTAL EQUIPMENT $575.00

Rev 1 PSI Equipment Storage 0552-364986.pdf
COST ESTIMATE AND SCHEDULE
Rev 1 PSI Equipment Storage 0552-364986 cost.pdf
Cost Estimate
Formula Sheet
LOE 2 Contractor Turnover
LOE 3-Qtr 1
LOE 4-Qtr 2
LOE 5-Qtr 3
LOE 6-Qtr 4
Rev 1 PSI Equipment Storage 0552-364986.pdf
Cost Estimate
LOE 2 Contractor Turnover
LOE 3-Qtr 1
LOE 4-Qtr 2
LOE 5-Qtr 3
LOE 6-Qtr 4

File details come from the government source that posted it. Updated .