CN-370000-HW686-DC003B.pdf

PDF 5 MB Posted

Attached to
Master Agreement FL|HW686|26652fe61cf76d14a6798f2369f5dddb
Contract number
HW686
Issued by
Florida

About this file

This document is a Task Assignment (TA) issued under Contract Number HW686 between the State of Florida Department of Environmental Protection (FDEP) and Professional Service Industries, Inc. (Intertek-PSI). The Task Assignment DC003B, effective through August 30, 2024, authorizes the contractor to perform 12 months of operation and maintenance services for a remediation system at Pugh's Dry Cleaners located at 215 South Bay Street in Eustis, Lake County, Florida (ERIC_4814).

The contract provides for fixed unit rate and cost reimbursement compensation with a total Task Assignment value of $72,444.14, comprising $64,404.14 in fixed unit rate services and $8,040.00 in cost reimbursement. Services include monthly operation and maintenance of a soil vapor extraction (SVE) system, quarterly email summaries, system repairs (well refurbishment and hose replacement), two Remedial Action System Status Reports, annual groundwater monitoring of 11 monitoring wells, and utility costs. Deliverables are scheduled across four quarters with payments tied to specific milestones: $26,570.86 for Q1 and Q2 services; $37,353.28 for Q3 and Q4 services; and $8,520.00 for utilities. The work encompasses 434 labor hours allocated across nine subtasks, including project management, quarterly operations and maintenance activities, system repairs, groundwater sampling and analysis, and remediation reporting in accordance with the FDEP Drycleaning Solvent Cleanup Program guidelines.

View the file

Other files

File Type Posted
CN-370000-HW686-DC001D.pdf PDF
CN-370000-HW686-DC002A.pdf PDF
CN-370000-HW686-DC002F.pdf PDF
CN-370000-HW686-DC002G.pdf PDF
CN-370000-HW686-DC002H.pdf PDF
CN-370000-HW686-DC003A.pdf PDF
CN-370000-HW686-DC003E.pdf PDF
CN-370000-HW686-DC003G.pdf PDF
CN-370000-HW686-DC004C.pdf PDF
CN-370000-HW686-DC004E.pdf PDF
CN-370000-HW686-DC007A.pdf PDF
CN-370000-HW686-DC007C.pdf PDF
CN-370000-HW686-DC007D.pdf PDF
CN-370000-HW686-DC009C.pdf PDF
CN-370000-HW686-DC009E.pdf PDF
CN-370000-HW686-DC010C.pdf PDF
CN-370000-HW686-DC011A.pdf PDF
CN-370000-HW686-DC012B.pdf PDF
CN-370000-HW686-DC013A.pdf PDF
CN-370000-HW686-DC014A.pdf PDF
CN-370000-HW686-DC016A.pdf PDF
CN-370000-HW686-DC018A.pdf PDF
CN-370000-HW686-DC019B.pdf PDF
CN-370000-HW686-DC01ACO4.pdf PDF
CN-370000-HW686-DC020C.pdf PDF
CN-370000-HW686-DC023A.pdf PDF
CN-370000-HW686-DC024A.pdf PDF
CN-370000-HW686-DC025A.pdf PDF
CN-370000-HW686-DC026B.pdf PDF
CN-370000-HW686-DC028A.pdf PDF
CN-370000-HW686-DC03DCO2.pdf PDF
CN-370000-HW686-DC04ECO1.pdf PDF
CN-370000-HW686-DC07BCO1.pdf PDF
CN-370000-HW686-DC07BCO3.pdf PDF
CN-370000-HW686-DC09DCO1.pdf PDF
CN-370000-HW686-DC11BCO1.pdf PDF
CN-370000-HW686-DC13BCO1.pdf PDF
CN-370000-HW686-DC14BCO3.pdf PDF
CN-370000-HW686-DC14DCO1.pdf PDF
CN-370000-HW686-DC15BCO1.pdf PDF
CN-370000-HW686-DC15DCO1.pdf PDF
CN-370000-HW686-DC16BCO1.pdf PDF
CN-370000-HW686-DC18CCO1.pdf PDF
CN-370000-HW686-DC21BCO1.pdf PDF
CN-370000-HW686-DC27BCO1.pdf PDF
CN-370000-HW686-FIL10.pdf PDF
CN-370000-HW686-FIL6.pdf PDF
CN-370000-HW686-FIL9.pdf PDF
CN-370000-HW686-HW002A.pdf PDF
CN-370000-HW686-HW011A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW686

DC003B Completion August 30, 2024

This Task Assignment authorizes Professional Service Industries, Inc. (PSI) to conduct 12 months of operation and maintenance in accordance with the PSI scope of work, cost estimate, and schedule received on March 27th, 2023.

Skylar Schwed 850-245-8795 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Professional Service Industries, Inc. (Intertek-PSI)

Professional Service Industries, Inc. (Intertek-PSI)

Nana G. Westmark 813-886-1075

ERIC_4814

215 South Bay Street Eustis, lake county

Pugh's Dry Cleaners

✔ $ 64,404.14 ✔ $ 8,040.00

$ 72,444.14

Scope of Work

Nana Westmark

Senior Geologist / Principal Consultant

Nana G Westmark Digitally signed by Nana G Westmark Date: 2023.03.29 11:42:57 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2023.03.29 10:56:21 -04'00'

N/A

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Murphy_SL Highlight

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number: HW686 Task Assignment #: DC003B

Deliverables:

Deliverable Deliverable Due Date Q1 - Quarterly operation and maintenance (O&M) email submittal including field documentation, laboratory reports, and tables AND photo docs of system repair - Subtask 2

7/20/2023

Q2 - Quarterly operation and maintenance (O&M) email submittal including field documentation, laboratory reports, and tables - Subtask 3

10/20/2023

Remedial Action Status Report - Subtask 4 10/30/2023

Q3 - Quarterly operation and maintenance (O&M) email submittal including field documentation, laboratory reports, and tables - Subtask 5

1/20/2024

Q4 - Quarterly operation and maintenance (O&M) email submittal including field documentation, laboratory reports, and tables - Subtask 6

4/20/2024

Annual Remedial Action Status Report including GWM data report & PM Subtasks 1,7,9

4/30/2024

Subtask 8 utility invoices for 12 months; Utilities (Cost Plus Fixed Fee) = not to exceed $8,040; Utilities Handling Fee = $480 5/30/2024

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced Q1 and Q2 - Quarterly O&M email submittals including field documentation, laboratory reports, and tables AND photo docs of system repair - Subtasks 2 and 3; AND Remedial Action Status Report - Subtask 4

$26,570.86

Q3 and Q4 - Quarterly O&M email submittals including field documentation, laboratory reports, and tables - Subtasks 5 and 6; AND Remedial Action Status Report incuding GWM Data report- Subtask 7&9 AND PM Subtask 1

$37,353.28

FDEP receipt of utility invoices for 12 months; Utilities (Cost Plus Fixed Fee) = not to exceed $8,040; Utilities Handling Fee = $480 - Subtask 8

$8,520.00

TOTAL COST $72,444.14

BWC TAFORM 01_18

Printed on recycled paper.

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

To:

From:

Date:

HW686 Contract Negotiation File Pugh’s Dry Cleaners 215 South Bay Street Eustis, lake county Skylar Schwed, Project Manager March 27, 2023

Subject: Negotiation Summary

HW686 DC003B

This Task Assignment authorizes Professional Service Industries, Inc. (PSI) to conduct 12 months of operation and maintenance in accordance with the PSI scope of work, cost estimate, and schedule received on March 27th, 2023.

FDEP confirmed on March 20th, 2023 that an Access Agreement with the current real property owner of the Westwood Cleaners (ERIC_4706) site has been executed.

The original Task Assignment totaled $72,444.14 with 434 labor hours but after negotiations and corrections with contractor costs are reflected as below:

The FDEP Project Manager agrees to the scope of work and final cost associated with this Task Assignment. The final cost for this Task Assignment is $72,444.14 with 434 labor hours.

PSI may invoice following the schedule established in the Deliverables and Invoice Schedule Attachment, which accompanies the Task Assignment Notification Form.

FDEP COST ESTI MATEContractor: Professional Service Industries, Inc. (Intertek-PSI)

Date: 2/27/2023 revised 3/27/2023

Task #: SubTask 1 Project Management SubTask 6 4th Qtr Monthly O&M

Site: Pugh's Drycleaners ERIC_4814 SubTask 2 1st Qtr Monthly O&M w/System Repairs SubTask 7 RASS

Activity/Phase: SubTask 3 2nd Qtr Monthly O&M SubTask 8 Utilities

Project Manager: Nana Westmark SubTask 4 RASS SubTask 9 Groundwater Monitoring

SubTask 5 3rd Qtr Monthly O&M SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$56.99 Project Manager 34 34.0 $64.90 Principal Consultant, DC 0 0 0 0 0 0 0 0 0 0 $60.00 Senior Engineer, MR 25 3 3 5 3 3 8 0 0 0 $56.99 Senior Geologist, NW 3 0 0 0 0 0 0 0 3 0 $40.87 Project Engineer, MK 0 0 0 0 0 0 0 0 0 0 $34.62 Certified Industrial Hygientist 0 0 0 0 0 0 0 0 0 0 $56.50 Certified Hazardous Materials Manager 0 0 0 0 0 0 0 0 0 0 $57.69 Senior Geologist, MR 0 0 0 0 0 0 0 0 0 0 $48.08 Project Manager 0 0 0 0 0 0 0 0 0 0 $43.27 Project Engineer, JN 146 21 19 32 19 19 36 0 0 0 $37.00 Project Geologist, SAM 0 0 0 0 0 0 0 0 0 0 $29.77 Project Scientist, RF 0 0 0 0 0 0 0 0 0 0 $33.74 Project Scientist, SB 0 0 0 0 0 0 0 0 0 0 $25.00 Staff Scientist, QH 32 10 0 0 0 0 0 0 22 0 $29.86 GIS Specialist, DG 10 0 0 2 0 0 8 0 0 0 $24.04 Staff Scientist, OG 0 0 0 0 0 0 0 0 0 0 $28.85 Staff Scientist, RP 0 0 0 0 0 0 0 0 0 $31.51 Remediation Coordinator, RH 184 47 39 0 37 39 0 0 22 0 $30.91 Environmental Specialist, CC 0 0 0 0 0 0 0 0 0 0 $22.06 Environmental Specialis, MZ 0 0 0 0 0 0 0 0 0 0 $21.26 Environmental Specialist, DK 0 0 0 0 0 0 0 0 0 0 $20.81 Administrative Assistant, BM 0 0 0 0 0 0 0 0 0 0 $15.50 Secretary 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 434 34 81 61 39 59 61 52 0 47 0

Direct Labor $16,819.86 $1,935.03 $2,819.64 $2,231.02 $1,744.36 $2,168.00 $2,231.02 $2,276.60 $0.00 $1,414.19 $0.00

Overhead 151.02% $25,401.35 $2,922.28 $4,258.22 $3,369.29 $2,634.33 $3,274.11 $3,369.29 $3,438.12 $0.00 $2,135.71 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $42,221.21 $4,857.31 $7,077.86 $5,600.31 $4,378.69 $5,442.11 $5,600.31 $5,714.72 $0.00 $3,549.90 $0.00

REV: 02/03 CEF PSI-Intertek Page 1

Task #: SubTask 1 Project Management SubTask 6 4th Qtr Monthly O&M

Site: Pugh's Drycleaners ERIC_4814 SubTask 2 1st Qtr Monthly O&M w/System Repairs SubTask 7 RASS

Activity/Phase: SubTask 3 2nd Qtr Monthly O&M SubTask 8 Utilities

Project Manager: Nana Westmark SubTask 4 RASS SubTask 9 Groundwater Monitoring

SubTask 5 3rd Qtr Monthly O&M SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Travel Vehicle Rental $1,800.00 $480.00 $360.00 $0.00 $360.00 $360.00 $0.00 $0.00 $240.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $1,800.00 $480.00 $360.00 $0.00 $360.00 $360.00 $0.00 $0.00 $240.00 $0.00

Subcontractor (Equipment Procurement) Well Materials $709.37 $709.37 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $709.37 $709.37 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $70.94 $70.94 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $780.31 $780.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $125.00 $0.00

Utilities $8,040.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $8,040.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $8,165.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $8,040.00 $125.00 $0.00 Handling Fee $492.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $480.00 $12.50 $0.00 Total Subcontractor Cost $8,657.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $8,520.00 $137.50 $0.00

Laboratory Analytical Costs $6,248.00 $466.00 $2,097.00 $0.00 $466.00 $2,097.00 $0.00 $0.00 $1,122.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $750.00 $150.00 $150.00 $0.00 $150.00 $150.00 $0.00 $0.00 $150.00 $0.00 Total Laboratory $6,998.00 $616.00 $2,247.00 $0.00 $616.00 $2,247.00 $0.00 $0.00 $1,272.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $600.00 $160.00 $120.00 $0.00 $120.00 $120.00 $0.00 $0.00 $80.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $7,165.00 $1,740.00 $1,305.00 $0.00 $1,305.00 $1,305.00 $0.00 $0.00 $1,510.00 $0.00 Total Field Expenses $7,765.00 $1,900.00 $1,425.00 $0.00 $1,425.00 $1,425.00 $0.00 $0.00 $1,590.00 $0.00

Subtotal $68,222.02 $4,857.31 $10,854.17 $9,632.31 $4,378.69 $7,843.11 $9,632.31 $5,714.72 $8,520.00 $6,789.40 $0.00 Completion Fee $4,222.12 $485.73 $707.79 $560.03 $437.87 $544.21 $560.03 $571.47 $0.00 $354.99 $0.00

Total Estimated Cost $72,444.14 $5,343.04 $11,561.96 $10,192.34 $4,816.56 $8,387.32 $10,192.34 $6,286.19 $8,520.00 $7,144.39 $0.00

REV: 02/03 CEF PSI-Intertek Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Pugh's Drycleaners ERIC_4814 SubTask 2 1st Qtr Monthly O&M w/System Repairs DATE: 2/27/2023 revised 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer, M Rothenburg System evaluation (1 hr/month), 3 Total hours: 3

Project Engineer, J Newell Telemetry check (3 times per week = 2 hours per month) 6 Provide oversight and technical support (2 hr/monthly, 6 hrs/quarterly) 6 O&M checklists (1 hr/month) 3 review and submit quarterly deliverable 4 Oversight of Repairs 2

Total hours: 21

Remediation Coordinator, R Hanson Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Additional hours to collect vapor analytical samples 1

Remediation Coordinator, R Hanson SVE004 Refurbishment and SVE Hose Removal and Replacement Field preparation 1 Mobilization 5 Well Refurbishment 2 Assist with Hose Replacement 2

Total hours: 47

Staff Scientist, Q Haydon SVE004 Refurbishment and SVE Hose Removal and Replacement Mobilization 5 Remove/Replace SVE hose with PVC 4 Assist with Hose Replacement 1

Total hours: 10

TOTAL LABOR 81

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Equipment Van / Truck $120.00 day 4 $480.00

TOTAL VEHICLE $480.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$200.00 2 $400.00

Summa cannisters $33.00 2 $66.00 $466.00

Shipping, large, overnight $150.00 1 $150.00

TOTAL LAB $616.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Construction/O&M/Pilot Test Kit $360.00 day 4 $1,440.00 Construction/O&M supplies $75.00 day 4 $300.00

$1,740.00 Expendables $40.00 day 4 $160.00

TOTAL EQUIPMENT $1,900.00

EQUIPMENT PROCUREMENT RATE COSTING UNIT USEAGE TOTALS

Repair Materials $2,490.00 Home Depot and Ace Hardware $709.37 see attached price quote from website

TOTAL EQUIPMENT $709.37

TO-15 (VOCs) (Qtr infl and eff)

FINAL --7/24/96

Page 4 Rev 1 Pugh's ERIC_4814 0552-394017

SubTask 3 2nd Qtr Monthly O&M DATE: 2/27/2023 revised 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer, M Rothenburg System evaluation (1 hr/month), review and submittal 3

Total hours: 3

Project Engineer, J Newell Telemetry check (3 times per week = 2 hours per month) 6 Provide oversight and technical support (2 hr/monthly, 6 hrs/quarterly) 6 O&M checklists (1 hr/month) 3 review and submit quarterly deliverable 4

Total hours: 19

Remediation Coordinator, R Hanson Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Additional hours to collect vapor analytical samples 3

Total hours: 39

TOTAL LABOR 61

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Equipment Van / Truck $120.00 day 3 $360.00

$0.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

$0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

$0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TO-15 (VOCs) (infl and eff per Qtr, 7 SVE wells) $200.00 9 $1,800.00

Summa cannisters $33.00 9 $297.00 $2,097.00

Shipping, large, overnight $150.00 1 $150.00

TOTAL LAB $2,247.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Construction/O&M/Pilot Test Kit $360.00 day 3 $1,080.00 Construction/O&M supplies $75.00 day 3 $225.00

$1,305.00 Expendables $40.00 day 3 $120.00

TOTAL EQUIPMENT $1,425.00

Page 5 Rev 1 Pugh's ERIC_4814 0552-394017

SubTask 4 RASS DATE: 2/27/2023 revised 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer, M Rothenburg Evaluate data 2 Review Final RASS 2 Sign and Seal RASS 1

Total hours: 5

Project Engineer, J Newell Data reduction/evaluation 12 Preparation of remediation report 8 Create figures 4 Report - Prepare final tables and figure 8

Total hours: 32

CADD / GIS Specialist, D Grove Prepare figures for RASS 2

TOTAL LABOR 39

VEHICLE TYPE RATE UNIT USEAGE

$0.00

$0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

$0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00 $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL EQUIPMENT $0.00

Page 6 Rev 1 Pugh's ERIC_4814 0552-394017

SubTask 5 3rd Qtr Monthly O&M DATE: 2/27/2023 revised 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer, M Rothenburg System evaluation (1 hr/month), review and submittal 3

Total hours: 3

Project Engineer, J Newell Telemetry check (3 times per week = 2 hours per month) 6 Provide oversight and technical support (2 hr/monthly, 6 hrs/quarterly) 6 O&M checklists (1 hr/month) 3 review and submit quarterly deliverable 4

Total hours: 19

Remediation Coordinator, R Hanson Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Additional hours to collect vapor analytical samples 1

Total hours: 37

TOTAL LABOR 59

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Equipment Van / Truck $120.00 day 3 $360.00

$0.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

$0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

$0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$200.00 2 $400.00

Summa cannisters $33.00 2 $66.00 $466.00

Shipping, large, overnight $150.00 1 $150.00

TOTAL LAB $616.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Construction/O&M/Pilot Test Kit $360.00 day 3 $1,080.00 Construction/O&M supplies $75.00 day 3 $225.00

$1,305.00 Expendables $40.00 day 3 $120.00

TOTAL EQUIPMENT $1,425.00

TO-15 (VOCs) (infl and eff)

Page 7 Rev 1 Pugh's ERIC_4814 0552-394017

SubTask 6 4th Qtr Monthly O&M DATE: 2/27/2023 revised 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer, M Rothenburg System evaluation (1 hr/month), review and submittal 3

Total hours: 3

Project Engineer, J Newell Telemetry check (3 times per week = 2 hours per month) 6 Provide oversight and technical support (2 hr/monthly, 6 hrs/quarterly) 6 O&M checklists (1 hr/month) 3 review and submit quarterly deliverable 4

Total hours: 19

Remediation Coordinator, R Hanson Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Monthly Field preparation 1 Mobilization 5 Conduct O&M, optimize performance 2 Collect vacuum influence / vacuum flow measurements 1 Collect vapor samples for PID screening 1 Monthly preparation, recording of system data to ongoing operational tables 1 O&M checklists (1 hr/month) 1

Additional hours to collect vapor analytical samples 3

Total hours: 39

TOTAL LABOR 61

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Equipment Van / Truck $120.00 day 3 $360.00

$0.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

$0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00

$0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TO-15 (VOCs) (infl and eff per Qtr, 7 SVE wells) $200.00 9 $1,800.00

Summa cannisters $33.00 9 $297.00 $2,097.00

Shipping, large , overnight $150.00 1 $150.00

TOTAL LAB $2,247.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Construction/O&M/Pilot Test Kit $360.00 day 3 $1,080.00 Construction/O&M supplies $75.00 day 3 $225.00

$1,305.00 Expendables $40.00 day 3 $120.00

TOTAL EQUIPMENT $1,425.00

Page 8 Rev 1 Pugh's ERIC_4814 0552-394017

SubTask 7 RASS DATE: 2/27/2023 revised 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Engineer, M Rothenburg Evaluate data 2 Review Final RASS/ Groundwater Report 5 Sign and Seal RASS 1

Total hours: 8

Project Engineer, J Newell Data reduction/evaluation 12 Preparation of remediation/ groundwater monitoring report 12 Create Final figures 4 Report - Prepare final tables and figure 8

Total hours: 36

CADD / GIS Specialist, D Grove Prepare figures for RASS, Groundwater 8

TOTAL LABOR 52

VEHICLE TYPE RATE UNIT USEAGE

$0.00 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00 $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL EQUIPMENT $0.00

Page 9 Rev 1 Pugh's ERIC_4814 0552-394017

SubTask 8 Utilities DATE: 2/27/2023 revised 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

TOTAL LABOR

VEHICLE TYPE RATE UNIT USEAGE

$0.00 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Duke Energy Electric $550.00 Month 12 $6,600.00

Century Link Phone $120.00 Month 12 $1,440.00 $8,040.00

Handling fee Electric $20.00 Month 12 $240.00 Handling fee phone $20.00 Month 12 $240.00

$480.00

$0.00 $0.00 $0.00

TOTAL $8,520.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

TOTAL EQUIPMENT $0.00

Page 10 Rev 1 Pugh's ERIC_4814 0552-394017

SubTask 9 Groundwater Monitoring DATE: 2/27/2023 revised 3/27/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Senior Geologist, N Westmark Technical Oversight 3

Remediation Coordinator, R Hanson Field preparation 2 Travel (2 roundtrips for gw sampling) 10 Collect groundwater samples 1 shallow wells @ 1 hour each 1 3 deep well @ 2 hours each 6 Documentation of groundwater sampling & measurements 2 stage IDW drum 1

Total hours: 22

Staff Scientist, Q Haydon Travel (2 roundtrips for gw sampling) 10 Collect groundwater samples 7 intermediate wells @ 1.5 hr each 11 pickup, drop off sample kits 1

Total hours: 22

TOTAL LABOR 47

VEHICLE TYPE RATE UNIT USEAGE

$0.00

Equipment Van / Truck $120.00 day 2 $240.00

$0.00

TOTAL VEHICLE $240.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

$0.00

Petrotech Southeast, Inc. IDW transport & disposal 1 $125.00 $125.00 $0.00 $0.00

TOTAL $125.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC IDW

$0.00

EPA Method 8260 $73.00 11 1 $876.00 Sulfate, EPA Method 300.0 $21.00 3 $63.00 TDS by EPA Method 2011 $16.00 3 $48.00 Iron by EPA Method 6020, ICP / MS $15.00 3 $45.00 Sodium by EPA Method 6020, ICP / MS $15.00 3 $45.00 Manganese by EPA Method 6020, ICP / MS $15.00 3 $45.00

$1,122.00 $0.00 Sample Shipping, Large, Overnight $150.00 1 $150.00

$0.00 $0.00

TOTAL LAB $1,272.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 Shallow Groundwater Sampling Kit $290.00 day 2 $580.00 Deep Groundwater Sampling Kit $415.00 day 2 $830.00 Drum for IDW $100.00 each 1 $1,410.00 $100.00

$1,510.00 Expendables $40.00 day 2 $80.00

TOTAL EQUIPMENT $1,590.00

Page 11 Rev 1 Pugh's ERIC_4814 0552-394017

PSI Proposal: 0552-394017-Rev 1 February 27, 202, revised March 27, 2023

MMMM DD,

www.intertek.com/building

Professional Service Industries, Inc.

5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634

Phone: (813) 886-1075 Fax: (813) 249-4916

Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

Attention: Ms. Skylar Schwed

Environmental Specialist III Email: Skylar.Schwed@FloridaDEP.gov

Re: Proposal for 12 Months O&M / RASS Report / Groundwater Monitoring Pugh’s Dry Cleaners 215 South Bay Street Eustis, Lake County, Florida

FDEP Facility ID# 35 9500385 / ERIC_4814

Dear Ms. Schwed:

Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the proposal contained herein to provide remediation system Operation & Maintenance (O&M) services for twelve

(12) months, summary updates via email on a quarterly basis, documentation of the remediation system performance with the development of two Remedial Action System Status Reports, and groundwater monitoring for the Pugh’s Dry Cleaners at 215 South Bay Street, Eustis, Florida. Included with this proposal is a discussion of project history to date, proposed scope of work, cost estimate and a proposed work schedule.

PROJECT BACKGROUND

Drycleaning operations at the Pugh’s Dry Cleaners began in 1948 and utilized petroleum solvent. In 1965, Pugh’s switched to tetrachloroethene (PCE) as the drycleaning solvent, which was stored in an AST located inside the building. Based on documented impact from the drycleaner, the facility was accepted into the Florida Drycleaning Solvent Cleanup Program in August 1998, and assessment activities commenced in December 2002 by Earth Tech.

Additional assessment wells were installed at the Pugh’s Dry Cleaners in January 2015 by PSI which revealed a high concentration of PCE (2630 ug/L) under the drycleaning machine beneath the building at a depth of 37-41 feet below land surface (bls). Two additional monitor wells were installed in March 2018, along with soil sampling for Soil Oxidant Demand (SOD) to assist in evaluating a groundwater remediation strategy.

mailto:Skylar.Schwed@FloridaDEP.gov

FDEP – Pugh’s Dry Cleaners

February 27, 2023, revised March 27, 2023

An SVE system was installed in October 2009 by others and has operated intermittently since that time.

PSI has operated the system at varying cycling times since April 2012 to July 2016. The system was shut down due to the drycleaning business remaining in operation and use of PCE as their solvent. The property / tenant changed ownership in 2016 and switched from PCE to a non-chlorinated solvent fluid.

The SVE system was subsequently re-started in October 2016 and operated until June 2021, then turned off in preparation for shutdown, along with confirmation soil sampling in June 2021. The results revealed soil impact inside the building that exceeded SCTLs (2480 mg/kg at SB016). The system was restarted in October 2021 and continues to exhibit contaminant mass recovery. A groundwater remediation strategy consisting of ISCO using Persulfox in 22 injection wells targeting 30 – 40 feet , then 58 – 68 feet deep, was completed in 2020 – 2021. Groundwater performance monitoring indicates groundwater contaminant reduction with a rebound in select wells.

Per discussions with the FDEP, PSI recommends continued operation of the SVE system for the next 12 months along with groundwater monitoring in accordance with the RAP schedule.

PROPOSED SCOPE OF WORK

The proposal contained herein consists of utilities service and twelve-monthly O&M events with two report deliverables for the existing SVE system, quarterly email summaries, groundwater monitoring along with reporting. The results will be used to confirm system operations and evaluate mass recovery rates as compared to remedial design. Annual groundwater monitoring will also be conducted with the results incorporated into a RASS report. Specifically, the proposed scope of work consists of the following subtasks:

1. Project Management

This scope is provided for in the template worksheets.

2. Three Months of O&M (First Quarter)

Operations and Maintenance will be conducted on the SVE system. The work will be conducted as follows:

a. Mobilization to the site on a monthly basis.

b. Collect monthly vacuum and air flow readings from the SVE wells.

c. Collect monthly PID readings from SVE wells and system effluent.

d. Optimize system performance and recollect system readings as necessary to confirm enhanced system operation.

e. Collect quarterly system influent and effluent samples for analysis by Method TO-15.

f. Document system readings in the site specific O&M checklist.

g. Review and submit quarterly deliverable.

As previously reported, there appears to be significant sediment buildup in SVE004, which may account for persistently low air flow rates in that well. During the May 2019 O&M visit, the total depth was measured at 2.85 feet, which indicates significant sediment buildup and occlusion of the well screen.

Vacuum to SVE004 was closed in June 2021 and the well remains in an inactive state.

In order to return SVE004 to service and increase contaminant recovery, PSI recommended that the well be refurbished to remove the sediment. PSI proposes to utilize air compression/jetting, vacuum, and/or manual cleaning to remove sediment from the well followed by returning the system to service.

Additionally, during the January 2023 O&M event, holes were observed within sections of hose connecting SVE wells to the SVE manifold. These hoses were installed on the roof and were exposed to ultraviolet light leading to their deterioration and subsequent failure. PSI recommends removal and replacement of deteriorated portions of the hose with PVC hard pipe. It is estimated that three (3) sections of hose, measuring approximately 60-ft each and one (1) section of hose measuring 40-ft, will be replaced with 2-inch diameter schedule 40 PVC pipe. Hoses subject to replacement are shown in the below photo collected in January of 2023.

A list of items proposed to replace the sections of hose has been included. Quantities and prices provided are based on prices obtained from Home Depot’s website. Removed hose will remain on-site pending disposal during site decommissioning efforts.

The Level of Effort for system repairs and the first quarter O&M is detailed in Subtask 2.

3. Three Months of O&M (Second Quarter)

O&M will be conducted once a month for three months as specified above. Air samples will be collected from five of the individual wells and the influent and effluent and analyzed by TO-15. A summary of system conditions will be submitted to the FDEP each quarter.

The Level of Effort is detailed in Subtask 3.

4. Semi-Annual RASS Report

A Semi-Annual Remedial Action System Status Report will be developed which will include an evaluation of the collected information and data. The report will detail and summarize the monthly O&M information, along with summary tables, figures and a graphical depiction of the system performance.

Vapor sampling results will be submitted in the RASS report. The report will be prepared in accordance with the Technical Worksheets or similar guidance documents, developed by the FDEP Drycleaning Solvent Cleanup Program.

Conclusions and recommendations will be made, which will include a summary of modifications made to the system to enhance the recovery rates or decrease system time to achieve targeted goals. The report will incorporate specific recommendations and provide opinions based on professional experience in order to achieve the most efficient cleanup endpoints. We understand that the Department’s goal is to achieve aggressive contaminant reduction in an efficient and cost-effective method.

The Level of Effort is detailed in Subtask 4.

5. Three Months of O&M (Third Quarter)

O&M will be conducted once a month for three months as specified above. Air samples will be collected from the influent and effluent at the end of the third quarter of the year and analyzed by TO-15. A summary of system conditions will be submitted via email to the FDEP.

The Level of Effort is detailed in Subtask 5.

6. Three Months of O&M (Fourth Quarter)

O&M will be conducted once a month for three months as specified above. Air samples will be collected from five of the individual wells and the influent and effluent and analyzed by TO-15. A summary of system conditions will be submitted via email to the FDEP.

The Level of Effort is detailed in Subtask 6.

7. Annual RASS Report

An Annual Remedial Action System Status Report will be developed which will include an evaluation of the collected information and data for the entire year. The report will detail and summarize the monthly O&M information, along with summary tables, figures and a graphical depiction of the system performance. Vapor sampling results will be submitted in the RASS report. Groundwater monitoring data will also be included and consist of site conditions, recent groundwater sampling data, and figures of flow direction and plume configuration. The report will be prepared in accordance with the Technical Worksheets or similar guidance documents, developed by the FDEP Drycleaning Solvent Cleanup Program.

Conclusions and recommendations will be made, which will include a summary of modifications made to the system to enhance the recovery rates or decrease system time to achieve targeted goals. The report will incorporate specific recommendations and provide opinions based on professional experience in order to achieve the most efficient cleanup endpoints. We understand that the Department’s goal is to achieve aggressive contaminant reduction in an efficient and cost-effective method.

The Level of Effort is detailed in Subtask 7.

8. Utilities for remediation system operation

PSI used the previous utility costs at this project as well as from similar equipment at other sites as a basis for the annual costs.

The Level of Effort for utilities is detailed in Subtask 8.

9. Groundwater Monitoring and Reporting

PSI will conduct the annual groundwater monitoring to evaluate current groundwater quality at the site.

The following will be conducted to facilitate the groundwater evaluation.

a. Mobilization to the site.

b. Collect groundwater elevation measurements at the 11 wells proposed for sampling.

c. Collect groundwater samples from monitor wells:

i. Shallow: MW011.

ii. Intermediate: MW013, MW015, MW016, MW018, MW019, MW020, and

MW022.

iii. Deep: MW004, MW005, and MW021.

d. Submit groundwater samples to a NELAC approved laboratory for analysis of VOHs via EPA Method 8260 and injection parameters (sulfate, TDS, Iron, Sodium, Manganese) from 3 wells (MW015, MW016, and MW018).

e. Incorporate groundwater analytical data, physical parameters and groundwater elevation data into the RASS report.

The investigative derived waste (IDW) that will be generated during the annual groundwater monitoring includes the purge water from the monitoring wells which will be containerized in a 55-gallon drum for transport and disposal at an approved facility.

COST ESTIMATE AND SCHEDULE

The estimated cost to perform the O&M for twelve months along with two RASS report deliverables, email summaries, and groundwater monitoring is shown on the attached Cost Estimate. All PSI services will be conducted in accordance with the terms and conditions contained within DEP Contract No. HW 686, Waste Cleanup Program Services, dated December 21, 2021. The services will be completed on a monthly basis upon authorization.

The O&M will start in April 2023 and continue for 12 months until March 2024 with the quarterly brief summaries as a deliverable. One RASS report will be submitted at the end of October 2023 (for the months April through September 2023) and the Annual RASS report will be submitted at the end of April 2024 (months October 2023 through March 2024). Groundwater monitoring is proposed to occur in November or December 2023 with the results incorporated into the RASS report in April 2024.

A deliverable schedule is presented below.

Pugh's Drycleaners ERIC_4814 Task Proposed

Cost Schedule / Deliverable

SubTask 1 Project Management $5,343.04 May 30, 2024 SubTask 2 1st Qtr Monthly O&M w/System Repairs $11,561.96 July 20, 2023 - Email Summary of 1st Qtr O&M

(April, May, June) SubTask 3 2nd Qtr Monthly O&M $10,192.34 October 20, 2023 - Email Summary of O&M 2nd

Qtr (July, Aug, Sept) SubTask 4 RASS $4,816.56 October 30, 2023 - RASS (for 1st and 2 Qtr) SubTask 5 3rd Qtr Monthly O&M $8,387.32 January 20, 2024 - Email Summary of 3rd O&M

(Oct, Nov, Dec) SubTask 6 4th Qtr Monthly O&M $10,192.34 April 20, 2024 - Email Summary of 4th Qtr O&M

(Jan, Feb, March ) SubTask 7 RASS $6,286.19 April 30, 2024 - RASS with Groundwater Report SubTask 8 Utilities $8,520.00 May 30, 2024 - Utility Invoices SubTask 9 Groundwater

Monitoring $7,144.39 April 30, 2024 - Groundwater data, manifest to be included in RASS

Total Estimated Cost

$72,444.14

PSI appreciates the opportunity to be of service to the FDEP. We look forward to working with you on this important project. If you have any questions, please feel free to contact us at (813) 886-1075 or (813) 267-2519.

Respectfully submitted, PROFESSIONAL SERVICE INDUSTRIES, INC.

Joshua S. Newell, PE Nana Westmark, PG, CHMM Project Engineer Senior Geologist / Contract Manager

Enclosure: Cost Estimate Level of Effort Quotes for Equipment Procurement

Z:\552-Env\FDEP HW 686 Drycleaning, Main Contract\0552-3451 Pugh's\Proposal\Proposal for Continued O&M 2023- 2024\Pugh's ERIC_4814 0552-394017.docx

From: Nana Westmark To: Schwed, Skylar L Cc: Joshua Newell Subject: RE: Pugh"s Drycleaners ERIC_4814 CE / LOE for continued O&M, and groundwater monitoring Date: Monday, March 27, 2023 12:07:42 PM Attachments: image001.png

Rev 1 Pugh"s ERIC_4814 0552-394017.pdf Pugh"s Supplies - Home Depot and Ace.pdf Rev 1 Pugh"s ERIC_4814 0552-394017.xlsx

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Good Morning Skylar – Please see highlighted responses below.

From: Schwed, Skylar L <Skylar.Schwed@FloridaDEP.gov> Sent: Monday, March 27, 2023 9:03 AM To: Nana Westmark <nana.westmark@intertek.com> Cc: Joshua Newell <joshua.newell@intertek.com> Subject: [External] RE: Pugh's Drycleaners ERIC_4814 CE / LOE for continued O&M, and groundwater monitoring Importance: High

Nana, After review, there are several issues with this proposal.

1. Please change the wording of “Quarterly email summary to FDEP” to “ review and submit quarterly deliverable” the number of hours are OK. Will do.

2. Under subtask 2 there are hours allocated to system repair; when you resubmit please include documentation (email or memo) from when this issue occurred and/or if we have anything from Robert saying it needs to be done. Language from the Work Scope is copied below, We also included a photo of the hoses that need replacement.

As previously reported, there appears to be significant sediment buildup in SVE004, which may account for persistently low air flow rates in that well. During the May 2019 O&M visit, the total depth was measured at 2.85 feet, which indicates significant sediment buildup and occlusion of the well screen. Vacuum to SVE004 was closed in June 2021 and the well remains in an inactive state.

In order to return SVE004 to service and increase contaminant recovery, PSI recommended that the well be refurbished to remove the sediment. PSI proposes to utilize air compression/jetting, vacuum, and/or manual cleaning to remove sediment from the well followed by returning the system to service.

Additionally, during the January 2023 O&M event, holes were observed within sections of hose connecting SVE wells to the SVE manifold. These hoses were installed on the roof and were exposed to ultraviolet light leading to their deterioration and subsequent failure. PSI recommends removal and replacement of deteriorated portions of the hose with PVC hard pipe. It is estimated that three mailto:nana.westmark@intertek.com mailto:joshua.newell@intertek.com

February 27, 202, revised March 27, 2023

MMMM DD,

Professional Service Industries, Inc.

5801 Benjamin Center Drive, Suite 112, Tampa, FL 33634

Phone: (813) 886-1075 Fax: (813) 249-4916

Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blair Stone Road, MS 4520 Tallahassee, FL 32399-2400

Attention: Ms. Skylar Schwed

Environmental Specialist III Email: Skylar.Schwed@FloridaDEP.gov

Re: Proposal for 12 Months O&M / RASS Report / Groundwater Monitoring Pugh’s Dry Cleaners 215 South Bay Street Eustis, Lake County, Florida

FDEP Facility ID# 35 9500385 / ERIC_4814

Dear Ms. Schwed:

Professional Service Industries, Inc. (PSI), an Intertek company, is pleased to provide the proposal contained herein to provide remediation system Operation & Maintenance (O&M) services for twelve

(12) months, summary updates via email on a quarterly basis, documentation of the remediation system performance with the development of two Remedial Action System Status Reports, and groundwater monitoring for the Pugh’s Dry Cleaners at 215 South Bay Street, Eustis, Florida. Included with this proposal is a discussion of project history to date, proposed scope of work, cost estimate and a proposed work schedule.

PROJECT BACKGROUND

Drycleaning operations at the Pugh’s Dry Cleaners began in 1948 and utilized petroleum solvent. In 1965, Pugh’s switched to tetrachloroethene (PCE) as the drycleaning solvent, which was stored in an AST located inside the building. Based on documented impact from the drycleaner, the facility was accepted into the Florida Drycleaning Solvent Cleanup Program in August 1998, and assessment activities commenced in December 2002 by Earth Tech.

Additional assessment wells were installed at the Pugh’s Dry Cleaners in January 2015 by PSI which revealed a high concentration of PCE (2630 ug/L) under the drycleaning machine beneath the building at a depth of 37-41 feet below land surface (bls). Two additional monitor wells were installed in March 2018, along with soil sampling for Soil Oxidant Demand (SOD) to assist in evaluating a groundwater remediation strategy.

An SVE system was installed in October 2009 by others and has operated intermittently since that time.

PSI has operated the system at varying cycling times since April 2012 to July 2016. The system was shut down due to the drycleaning business remaining in operation and use of PCE as their solvent. The property / tenant changed ownership in 2016 and switched from PCE to a non-chlorinated solvent fluid.

The SVE system was subsequently re-started in October 2016 and operated until June 2021, then turned off in preparation for shutdown, along with confirmation soil sampling in June 2021. The results revealed soil impact inside the building that exceeded SCTLs (2480 mg/kg at SB016). The system was restarted in October 2021 and continues to exhibit contaminant mass recovery. A groundwater remediation strategy consisting of ISCO using Persulfox in 22 injection wells targeting 30 – 40 feet , then 58 – 68 feet deep, was completed in 2020 – 2021. Groundwater performance monitoring indicates groundwater contaminant reduction with a rebound in select wells.

Per discussions with the FDEP, PSI recommends continued operation of the SVE system for the next 12 months along with groundwater monitoring in accordance with the RAP schedule.

PROPOSED SCOPE OF WORK

The proposal contained herein consists of utilities service and twelve-monthly O&M events with two report deliverables for the existing SVE system, quarterly email summaries, groundwater monitoring along with reporting. The results will be used to confirm system operations and evaluate mass recovery rates as compared to remedial design. Annual groundwater monitoring will also be conducted with the results incorporated into a RASS report. Specifically, the proposed scope of work consists of the following subtasks:

1. Project Management

This scope is provided for in the template worksheets.

2. Three Months of O&M (First Quarter)

Operations and Maintenance will be conducted on the SVE system. The work will be conducted as follows:

a. Mobilization to the site on a monthly basis.

b. Collect monthly vacuum and air flow readings from the SVE wells.

c. Collect monthly PID readings from SVE wells and system effluent.

d. Optimize system performance and recollect system readings as necessary to confirm enhanced system operation.

e. Collect quarterly system influent and effluent samples for analysis by Method TO-15.

f. Document system readings in the site specific O&M checklist.

g. Review and submit quarterly deliverable.

As previously reported, there appears to be significant sediment buildup in SVE004, which may account for persistently low air flow rates in that well. During the May 2019 O&M visit, the total depth was measured at 2.85 feet, which indicates significant sediment buildup and occlusion of the well screen.

Vacuum to SVE004 was closed in June 2021 and the well remains in an inactive state.

In order to return SVE004 to service and increase contaminant recovery, PSI recommended that the well be refurbished to remove the sediment. PSI proposes to utilize air compression/jetting, vacuum, and/or manual cleaning to remove sediment from the well followed by returning the system to service.

Additionally, during the January 2023 O&M event, holes were observed within sections of hose connecting SVE wells to the SVE manifold. These hoses were installed on the roof and were exposed to ultraviolet light leading to their deterioration and subsequent failure. PSI recommends removal and replacement of deteriorated portions of the hose with PVC hard pipe. It is estimated that three (3) sections of hose, measuring approximately 60-ft each and one (1) section of hose measuring 40-ft, will be replaced with 2-inch diameter schedule 40 PVC pipe. Hoses subject to replacement are shown in the below photo collected in January of 2023.

A list of items proposed to replace the sections of hose has been included. Quantities and prices provided are based on prices obtained from Home Depot’s website. Removed hose will remain on-site pending disposal during site decommissioning efforts.

The Level of Effort for system repairs and the first quarter O&M is detailed in Subtask 2.

3. Three Months of O&M (Second Quarter)

O&M will be conducted once a month for three months as specified above. Air samples will be collected from five of the individual wells and the influent and effluent and analyzed by TO-15. A summary of system conditions will be submitted to the FDEP each quarter.

The Level of Effort is detailed in Subtask 3.

4. Semi-Annual RASS Report

A Semi-Annual Remedial Action System Status Report will be developed which will include an evaluation of the collected information and data. The report will detail and summarize the monthly O&M information, along with summary tables, figures and a graphical depiction of the system performance.

Vapor sampling results will be submitted in the RASS report. The report will be prepared in accordance with the Technical Worksheets or similar guidance documents, developed by the FDEP Drycleaning Solvent Cleanup Program.

Conclusions and recommendations will be made, which will include a summary of modifications made to the system to enhance the recovery rates or decrease system time to achieve targeted goals. The report will incorporate specific recommendations and provide opinions based on professional experience in order to achieve the most efficient cleanup endpoints. We understand that the Department’s goal is to achieve aggressive contaminant reduction in an efficient and cost-effective method.

The Level of Effort is detailed in Subtask 4.

5. Three Months of O&M (Third Quarter)

O&M will be conducted once a month for three months as specified above. Air samples will be collected from the influent and effluent at the end of the third quarter of the year and analyzed by TO-15. A summary of system conditions will be submitted via email to the FDEP.

The Level of Effort is detailed in Subtask 5.

6. Three Months of O&M (Fourth Quarter)

O&M will be conducted once a month for three months as specified above. Air samples will be collected from five of the individual wells and the influent and effluent and analyzed by TO-15. A summary of system conditions will be submitted via email to the FDEP.

The Level of Effort is detailed in Subtask 6.

7. Annual RASS Report

An Annual Remedial Action System Status Report will be developed which will include an evaluation of the collected information and data for the entire year. The report will detail and summarize the monthly O&M information, along with summary tables, figures and a graphical depiction of the system performance.

This is the start of the file's text. The full file is on GovTribe.