CN-370000-HW686-DC014D.pdf
PDF 1006 KB Posted
- Contract number
- HW686
- Issued by
- Florida
About this file
This is a Task Assignment (TA) document issued under Contract Number HW686 between the State of Florida Department of Environmental Protection (FDEP) and Professional Service Industries, Inc. (Intertek-PSI). The assignment is numbered DC014D and is effective through February 27, 2026. The project involves environmental remediation services at the Classic Cleaners facility located at 2291 East Bearss Avenue in Tampa, Hillsborough County, Florida (ERIC Project #4750). Key personnel include Mary Uribe as the FDEP Project Manager and Joshua Newell as the Contractor's Project Manager.
The scope of work consists of developing an Interim Source Removal Plan (ISRP) utilizing Soil Vapor Extraction (SVE) technology to address volatile organic compound (VOH) contamination in soil and groundwater resulting from historical drycleaning operations. The project includes two subtasks: Project Management and preparation of the ISR Plan, with a combined deliverable due date of January 31, 2026. The total task value is $12,974.96 on a fixed unit rate basis, covering PSI's labor, subcontractor costs, and equipment expenses. Payment is contingent upon FDEP approval of both the Project Management and ISR Plan deliverables. The cost estimate reflects 83 labor hours distributed across multiple staff positions (Senior Engineer, Project Engineer, Project Scientist, GIS/CADD Specialist, and Administrative Assistant), one equipment van rental ($120.00), and expendable equipment and construction test kit ($400.00).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW686
DC014D February 27, 2026
SVE Interim Source Removal Plan
Mary Uribe 850-245-8990 Professional Service Industries, Inc. (Intertek-PSI)
Joshua Newell 863-712-4342
ERIC_4750
2291 East Bearss Avenue Tampa, Hillsborough County
Classic Cleaners
$ 12,974.96
$ 12,974.96
Scope of Work
Professional Service Industries, Inc. (Intertek-PSI)
Douglas Coleman PMP, CHMM, REM
Contract Manager
Douglas Coleman Digitally signed by Douglas Coleman Date: 2025.09.19 09:13:17 -04'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2025.09.11 08:17:20 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Classic Cleaners ERIC_4750 SubTask 2 ISR Plan
DATE: 9/5/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Activities
Senior Engineer, G Robinson Coordinate with tenant, property owner 2 Review bid documents for subcontractors 2 Review calculations 2 Review text 3 Review tables 1 Review figures 1 Sign and seal documents 1
Total Hours 12
Project Engineer, J Newell Travel to Site, roundtrip 3 Meet on-site with tenant/owner to evaluate equipment locations 3 Evaluate electrical requirements with power company 3 Prepare remediation calculations (SV & AI - flow rates and friction loss) 6 Equipment specifications - SVE/AI blowers 8 Prepare ISRP text 12 Develop tables 4
Prepare ISR checklist 2 Develop bid documents for subcontractors 6
Total Hours 59
Project Scientist, J Daugherty Obtain subcontractor quotes 6 Total Hours 6
GIS/CADD Specialist, D Grove Create and prepare final figures 3
Administrative Assistant, B Meynardie Compile documents 3
TOTAL LABOR 83.00
VEHICLE TYPE RATE UNIT USEAGE
$0.00 Equipment Van / Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC IDW
$0.00 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
$0.00 Expendables $40.00 day 1 $40.00 Construction Test Kit $360.00 day 1 $360.00
#REF!
TOTAL EQUIPMENT $400.00
Develop figures (trench details, SVE cross sections, treatment system layout, P&ID, equipment list, and components)
FINAL --7/24/96
Page 4 Classic Cleaners ERIC_4750 ISR Plan SVE 0552-446314r1
FDEP – Classic Cleaners ERIC_4750 PSI Proposal 0552-446314r1
September 5, 2025 www.intertek.com/building
Classic Cleaners began drycleaning operations utilizing PCE solvents following the construction of Meridia Square Shopping Center in 1990 until approximately 2012 when it was converted to a drop-off facility only. A site screening report dated May 30, 1997 identified PCE in a soil sample collected near the drycleaning machine at 20 mg/kg, which exceeds SCTL’s. On October 9, 1997, the FDEP determined that the site was eligible for the Drycleaning Solvent Cleanup Program with a site score of 78. A Rapid Risk Screening was performed for this site in October 2011 which confirmed the current owner and the status of the facility was drop-off only. Currently, no PCE-drycleaning equipment remains on site.
PSI completed Site Assessment activities in April 2023 through April 2024, with soil analytical results revealing no volatile organic aromatic or halocarbon (VOA or VOH) concentrations in the soil above the SCTL’s but did find VOH concentrations in the groundwater above the Groundwater Target Cleanup Level (GCTL) and in soil vapors in excess of FDEP Waste Site Cleanup Section (WSCS) guidance for soil remediation. Additionally, groundwater samples were submitted during the initial site assessment activities for PFAS compounds, however, no PFAS compounds were detected at concentrations above the provisional GCTL of 70 nanograms/liter (ng/L).
PSI’s recommendations, with FDEP concurrence, was to develop and implement an interim source removal plan utilizing Soil Vapor Extraction to remove chlorinated solvent contaminants from the vadose zone. The FDEP has requested that any newly constructed SVE system include a 1 horsepower air injection blower for active venting.
PSI, therefore, has developed this scope of work, cost estimate and level of effort to prepare an ISR Plan consisting of SVE remedial technology with an optional air injection blower if a newly constructed system is recommended.
PROPOSED SCOPE OF WORK
This proposal consists of preparing the Interim Source Removal Plan (Soil Vapor Extraction) at the referenced site.
Specifically, the proposed scope of work consists of the following subtasks:
1. Project Management
This scope is provided for in the template worksheets.
2. Interim Source Removal Plan (ISR Plan)
The design of the ISRP will address VOH concentrations in the soil and will not directly address groundwater quality. The presumptive remedy for remediation of impacted soil at the Classic Cleaners site is soil vapor extraction, based on previous experience, feasibility, ease of implementation, reliability, operations and maintenance (O&M) requirements, and cost. PSI will also coordinate with the building tenant, property management company, and the property owner for suggested locations of piping, lines, and equipment compound.
File details come from the government source that posted it. Updated .