Task Assignment Notification and Scope of Work

This document is a Task Assignment Notification Form issued by the Florida Department of Environmental Protection (FDEP) to Taylor Engineering, Inc. for planning phase services related to the Anastasia State Park Beach/Dune Restoration Project in St. Johns County, Florida. The contract is identified as FDEP Contract No. CN335, Task Assignment No. 19, with Project No. ARPSJ1. Ralph Perkins serves as the FDEP Contract Manager, while Kenneth R. Craig represents Taylor Engineering. The project is owned by FDEP's Division of Resource Planning, with Garland Sandel identified as the Project Manager or Successor.

The scope of work comprises three fixed-price tasks totaling $58,340.34. Task 1 (Data Collection and Analysis, $23,130.72) involves obtaining historical permit and design data, collecting wading depth surveys across 18 beach profiles, obtaining UAS aerial photographs, and analyzing sediment samples to document post-hurricane beach conditions. Task 2 (Coordination with USACE and State Park/Tallahassee Personnel, $12,041.28) includes consulting with U.S. Army Corps of Engineers regarding inlet maintenance dredging and sand placement authorities, and presenting findings to FDEP staff with discussion of project options, funding, and permitting implications. Task 3 (Project Concept Report, $23,168.34) requires development of a comprehensive project feasibility report presenting alternative designs at various scales with preliminary designs and impact analysis. The project execution date is February 6, 2023, with completion scheduled for June 30, 2024. All costs are charged to FDEP grant funding (CSFRF) under the specified FLAIR code, with payment contingent upon FDEP approval of deliverables for each task.

View the file

Other files

File Type Posted
CN-370000-CN335-CMC2.pdf PDF
CN-370000-CN335-T12.pdf PDF
CN-370000-CN335-T13.pdf PDF
CN-370000-CN335-T16.pdf PDF
CN-370000-CN335-T17.pdf PDF
CN-370000-CN335-T17CO1.pdf PDF
CN-370000-CN335-T1CO1.pdf PDF
CN-370000-CN335-T2.pdf PDF
CN-370000-CN335-T22.pdf PDF
CN-370000-CN335-T23.pdf PDF
CN-370000-CN335-T24.pdf PDF
CN-370000-CN335-T5CO5.pdf PDF
CN-370000-CN335-T6CO2.pdf PDF
CN-370000-CN335-T8CO6.pdf PDF
CN-370000-CN335-CMC1.pdf PDF
CN-370000-CN335-T10CO2.pdf PDF
CN-370000-CN335-T14.pdf PDF
CN-370000-CN335-T14CO1.pdf PDF
CN-370000-CN335-T14CO3.pdf PDF
CN-370000-CN335-T15.pdf PDF
CN-370000-CN335-T17CO4.pdf PDF
CN-370000-CN335-T18.pdf PDF
CN-370000-CN335-T20.pdf PDF
CN-370000-CN335-T20CO1.pdf PDF
CN-370000-CN335-T21.pdf PDF
CN-370000-CN335-T21CO3.pdf PDF
CN-370000-CN335-T25.pdf PDF
CN-370000-CN335-T5.pdf PDF
CN-370000-CN335-T5CO1.pdf PDF
CN-370000-CN335-T5CO3.pdf PDF
CN-370000-CN335-T6.pdf PDF
CN-370000-CN335-T6CO4.pdf PDF
CN-370000-CN335-T8.pdf PDF
CN-370000-CN335-TA4.pdf PDF
CN-370000-CN335-TA5 CO4.pdf PDF
CN-370000-CN335-CMC3.pdf PDF
CN-370000-CN335-CMC4.pdf PDF
CN-370000-CN335-T10.pdf PDF
CN-370000-CN335-T11.pdf PDF
CN-370000-CN335-T11CO4.pdf PDF
CN-370000-CN335-T14CO2.pdf PDF
CN-370000-CN335-T16CO1.pdf PDF
CN-370000-CN335-T1CO3.pdf PDF
CN-370000-CN335-T5CO2.pdf PDF
CN-370000-CN335-T6CO3.pdf PDF
CN-370000-CN335-T9.pdf PDF
CN-370000-CN335-TA3.pdf PDF
PC-370000-CN335.pdf PDF
CN-370000-CN335-A1.pdf PDF
CN-370000-CN335-CMC5.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN335 19 FDEP-DRP ARPSJ1

Anastasia State Park Beach Re-nourishment

Taylor Engineering

Kenneth R. Craig 904.731.7040 kcraig@taylorengineering.com>

Ralph Perkins 850.245.2460 Ralph.Perkins@FloridaDEP.gov

The proposal consist of: Data Collection and Analysis, Coordination with USACE and State Park/Tallahassee FDEP Personnel and project report for direction of the project. See proposal 1/13/23.

Garland Sandel or Successor

Execution date $ 58,340.34

6.30.24 $ 0.00

$ 58,340.34

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.02.06 10:44:19 -05'00'

Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2023.02.06 12:32:58 -05'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.02.06 13:27:30 -05'00'

Kenneth R. Craig, P.E Digitally signed by Kenneth Craig Date: 2023.02.07 09:14:35 -05'00'

Michael W. Foster Jr., P.E Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.02.08 10:08:38 -05'00'

ARPSJ1 CSFRF 37536060000 085176/22 000286 U1671 131500 AD $ 58,340.34

$ 58,340.3437101000286375004000008517622

Anastasia State Park Beach/Dune Restoration Project Planning Phase

Contract CN 335 TA19 January 13, 2023

Project Understanding The Florida Department of Environmental Protection (FDEP) requested Taylor Engineering provide a scope to determine the concepts to conduct a beach/dune restoration project along the Atlantic shoreline of Anastasia State Park in St. Johns County.

Scope of Services CONSULTANT Taylor Engineering Inc. will provide the following services:

Task 1 – Data Collection and Analysis Taylor Engineering will obtain and review permit authorizations, designs, and operational data for past maintenance dredging in and around St. Augustine Inlet with a focus on projects that placed sand on Anastasia State Park beaches. We will provide a letter report summarizing the findings.

Taylor Engineering will collect wading depth surveys of the dune and nearshore project beach (R-124 to R- 141 [18 total profiles]). This survey will serve to document post-hurricane beach conditions. Taylor will perform all work activities and produce deliverables in accordance with the May 2014 (or later) Bureau of Beaches and Coastal Systems (BBCS) Monitoring Standards for Beach Erosion Control Projects; Section 01000, Beach Profile Topographic Surveying, and Section 01100, Offshore Profile Surveying. (Document available on the web at https://floridadep.gov/sites/default/files/PhysicalMonitoringStandards.pdf). Taylor will also collect UAS-based aerial photographs of the project beach to use as an updated base map. Finally, Taylor will also collect sand samples from the dune, berm, and approximate MHW locations along five transects to determine existing sediment characteristics. We will develop grain size curves and Munsell color for each of the samples.

We understand that the U.S. Army Corps of Engineers (USACE) has collected pre- and post-Nicole LiDAR data for St. Johns, Flagler, and Volusia Counties which should include the project area. If available, we will incorporate these data into the analyses discussed below.

Taylor Engineering will transform the beach profile data from northing/easting/elevation to range/elevation profiles, develop profile plots, and perform profile-based analyses for each reference monument to help assess recent hurricane impacts on the state park shoreline. We will make the following comparisons at the appropriate profile locations:

• post-hurricane data versus summer 2021 monitoring survey (most recent available)

For the above comparisons, we will calculate and tabulate the mean high water positions, volume changes, and estimated volume to fill the specified template. We will calculate beach volumes across two compartments: dune to mean high water (MHW) and below MHW.

https://floridadep.gov/sites/default/files/PhysicalMonitoringStandards.pdf

Anastasia State Park Beach/Dune Project – Planning Phase

In addition, we will incorporate the results from past monitoring reports for the federal shore protection project at St. Augustine Beach. The Anastasia State Park shoreline is part of the northern control area referenced in these reports.

We will provide a letter report summarizing the work performed, locations and pictures of the benchmarks, monuments, baseline data, and sediment results.

Deliverables Taylor Engineering will provide the following deliverables to the FDEP:

Letter report summarizing past project information ............................................ 1 copy via email (PDF file) Summary letter of survey and sediment data and procedures ............................ 1 copy via email (PDF file) Survey data in FDEP digital format ........................................................... data uploaded to FDEP FTP site Sediment data in gINT digital format ......................................................... data uploaded to FDEP FTP site

Performance Measures Deliverables will be reviewed by the FDEP to confirm they are complete, accurate, and timely.

Fixed Price Cost Task 1 – Data Collection and Analysis

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Taylor Engineering Principal $200.94 16 $3,215.04 Taylor Engineering Senior Advisor/QC $202.53 8 $1,620.24 Taylor Engineering Project Professional $116.58 68 $7,927.44 Taylor Engineering Staff Professional $86.40 120 $10,368.00 Task 1 Total $23,130.72

Task 2 – Coordination with USACE and State Park/Tallahassee FDEP Personnel Taylor Engineering will consult with the USACE program managers to obtain information regarding the next scheduled St. Augustine Inlet maintenance dredging event. In addition, Taylor Engineering will determine existing USACE authorities to place sand along the park’s beaches and what, if any, additional authorizations are required for future work. We will also obtain information on how the State should coordinate with USACE on sand placement in the park for future events.

Taylor Engineering will meet with and present the results of Task 1 to FDEP staff from both Anastasia State Park and Tallahassee. At this meeting, we will discuss

1) existing condition of the state park shoreline,

2) compare existing conditions to historic conditions,

3) options for potential projects

Taylor Engineering will prepare a PowerPoint presentation to guide discussion during the meeting. Topics for consideration include the project scale (targeted dune restoration vs more expansive beach restoration), sand source (truck haul vs estuarine dredging vs offshore dredging), permitting implications, and funding options. We will prepare summary notes from the meeting.

Deliverables Taylor Engineering will provide the following deliverables to the FDEP:

Task summary and PowerPoint ........................................................................... 1 copy via email (PDF file)

Performance Measures Deliverables will be reviewed by the FDEP to confirm they are complete, accurate, and timely.

Fixed Price Cost Task 2 – Coordination with USACE and State Park/Tallahassee FDEP Personnel

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Taylor Engineering Principal $200.94 26 $5,224.44 Taylor Engineering Project Professional $116.58 48 $5,595.84 Taylor Engineering Senior Tech Support $139.23 8 $1,113.84 Taylor Engineering Administrative $53.58 2 $107.16 Task 2 Total $12,041.28

Task 3 – Project Concept Report Based on the findings from Tasks 1 and 2, Taylor Engineering develop a project concept report. The report will summarize all findings to date and present the pros and cons of alternative project designs. We will include preliminary designs that identify the alongshore locations and profile characteristics (dune/berm elevations, widths, and slopes) for up to three project designs of various magnitudes. Most likely these will include a targeted project of limited scope to address specific areas with compromised dunes, a more extensive dune restoration focusing on placement above MHW, and a larger project seeking to extend the MHW line seaward. Following Tasks 1 and 2, we will seek FDEP concurrence regarding the project characteristics that we will include in the concept report.

Deliverables Taylor Engineering will provide the following deliverables to the FDEP:

Draft project concepts report ................................................................................ 1 copy via email (PDF file) Final project concepts report ................................................................................ 1 copy via email (PDF file)

Fixed Price Cost

Task 3 – Project Feasibility Report

Firm Name Position Classification Hourly Rate Hours Total Fixed

Price Cost

Taylor Engineering Principal $200.94 28 $5,626.32 Taylor Engineering Project Professsional $116.58 88 $10,259.04 Taylor Engineering Senior Tech Support $139.23 50 $6,961.50 Taylor Engineering Administrative $53.58 6 $321.48 Task 3 Total $23,168.34

Project Schedule The following table presents the expected duration for each task. The proposed durations assume a two-week review time by the FDEP for each submittal. The actual duration of each task will depend upon when we receive relevant information from the FDEP, schedules, weather and mutually agreed-upon dates for meetings.

Task No. Task Name *Duration (Calendar Days)

Task 1 Data Collection and Analysis 60

Task 2 Coordination with State Park and Tallahassee Personnel 90

Task 3 Project Feasibility Report 120 *Days following the execution of an agreement

Summary of Fees The following table is a summary of the proposed fees.

Task Task Name Task Fixed Price Cost Task 1 Data Collection and Analysis $23,130.72

Task 2 Coordination with State Park and Tallahassee Personnel

$12,041.28

Task 3 Project Feasibility Report $23,168.34

Total Fixed Price Cost $58,340.34

Overall Total Cost $58,340.34

Payment will be made upon approval of deliverables for each task by the FDEP in the amount specified.

Attachment: Wage Rates

Labor Category Direct Labor

Rate Burdened Rate

President 98.38 295.14

Principal 66.98 200.94

Senior Advisor/QC 67.51 202.53

Director 59.34 178.02

Senior Professional 54.07 162.21

Project Manager 48.51 145.53

38.86 116.58

28.80 86.40

46.41 139.23

33.87 101.61

37.95 113.85

17.86 53.58

Project Professional

Staff Professional

Senior Technical Support (CAD/GIS) Technical Support (CAD/GIS) Technical Editor

Administrative

Multiplier:

Direct Labor 100.00% Fringe Benefit (applied to direct labor) 60.41% Overhead (applied to direct labor) 115.90%

Subtotal 276.31% Profit (9% applied to Direct Labor + Fringe + Overhead) 24.87%

Total Multiplier (max of 3.00) 3.0000

Revised rates effective June 1, 2021 REVISED Schedule of Hourly Rates

Florida Department of Environmental Protection Statewide Professional Coastal Engineering Services

Bid Number RFSOQBDC02-15/16

10 19 9 SO UT HS I DE BLVD , S U IT E 31 0 | J ACK SONV ILLE , F L 3 2 25 6 | TEL 9 0 4 . 73 1 . 70 4 0

WWW .T AYLO RENG INE ER I NG.C OM

06/02/2021

CN 335 19 TA.pdf
CN335 TA19 Anastasia State Park-Dune Restoration.pdf

File details come from the government source that posted it. Updated .