About this file

This document is a Task Assignment Change Order Form (Change Order No. 02) issued by the Florida Department of Environmental Protection (FDEP) for contract CN230. The change order involves Weiler Engineering Corporation, a consulting firm providing engineering services for the Dr. Von D. Mizell - Eula Johnson State Park Restroom Improvements project located in Florida. The contract manager is Ralph Perkins of FDEP, and the consultant representative is Robin Palmer of Weiler Engineering Corporation.

The change order is a time-only extension at no additional cost to FDEP. The original task end date of November 30, 2024, is extended by 146 days to April 25, 2025, to allow for completion of permitting and construction administration services. The total contract amount remains $107,212.12, with reimbursement costs of $2,823.20 and fixed fees of $104,388.92. No changes to the financial terms are included in this modification. The change order was approved and digitally signed by authorized representatives from both FDEP and Weiler Engineering Corporation in November 2024.

View the file

Other files

File Type Posted
CN-370000-CN230-CMC3.pdf PDF
CN-370000-CN230-T14CO1.pdf PDF
CN-370000-CN230-T14CO2.pdf PDF
CN-370000-CN230-T15.pdf PDF
CN-370000-CN230-T16.pdf PDF
CN-370000-CN230-T1CO1.pdf PDF
CN-370000-CN230-T20.pdf PDF
CN-370000-CN230-T21.pdf PDF
CN-370000-CN230-T24.pdf PDF
CN-370000-CN230-T25.pdf PDF
CN-370000-CN230-T2CO2.pdf PDF
CN-370000-CN230-T3.pdf PDF
CN-370000-CN230-T34CO2.pdf PDF
CN-370000-CN230-T35.pdf PDF
CN-370000-CN230-T36CO1.pdf PDF
CN-370000-CN230-T36CO2.pdf PDF
CN-370000-CN230-T39.pdf PDF
CN-370000-CN230-T3CO1.pdf PDF
CN-370000-CN230-T45.pdf PDF
CN-370000-CN230-T45CO2.pdf PDF
CN-370000-CN230-T49.pdf PDF
CN-370000-CN230-T51.pdf PDF
CN-370000-CN230-T56.pdf PDF
CN-370000-CN230-T62.pdf PDF
CN-370000-CN230-T64CO1.pdf PDF
CN-370000-CN230-T76.pdf PDF
CN-370000-CN230-T79.pdf PDF
CN-370000-CN230-T7CO1.pdf PDF
CN-370000-CN230-T9.pdf PDF
CN-370000-CN230-T92.pdf PDF
CN-370000-CN230-TA33.pdf PDF
CN-370000-CN230-CMC5.pdf PDF
CN-370000-CN230-T1.pdf PDF
CN-370000-CN230-T12.pdf PDF
CN-370000-CN230-T13.pdf PDF
CN-370000-CN230-T14.pdf PDF
CN-370000-CN230-T18.pdf PDF
CN-370000-CN230-T19CO1.pdf PDF
CN-370000-CN230-T19CO2.pdf PDF
CN-370000-CN230-T22.pdf PDF
CN-370000-CN230-T25CO1.pdf PDF
CN-370000-CN230-T25CO3.pdf PDF
CN-370000-CN230-T26.pdf PDF
CN-370000-CN230-T2CO1.pdf PDF
CN-370000-CN230-T37CO2.pdf PDF
CN-370000-CN230-T45CO1.pdf PDF
CN-370000-CN230-T4CO1.pdf PDF
CN-370000-CN230-T52.pdf PDF
CN-370000-CN230-T53.pdf PDF
CN-370000-CN230-T53CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN230 53 02 61397C

Dr. Von D. Mizell - Eula Johnson State Park Restroom Improvements

Weiler Engineering Corporation

Robin Palmer 941-505-1700 rpalmer@weilerengineering.org

Ralph Perkins 850-245-2640 Ralph.Perkins@FloridaDEP.gov

This is a no cost time only extension request to allow for the completion of permitting and construction administration services. Please see the attached back up dated 11/08/2024.

$ 2,823.20 $ 94,173.12 $ 96,996.32 $ 2,823.20 $ 104,388.92 $ 107,212.12

$ 0.00 $ 0.00 $ 0.00 $ 2,823.20 $ 104,388.92 $ 107,212.12

1/23/23

11/30/24

11/30/24

04/25/2025

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.11.12 10:17:48 -05'00'

Jim McGuire Jim McGuire Digitally signed by Jim McGuire Date: 2024.11.15 09:31:01 -05'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.11.15 09:36:11 -05'00'

R. Jeff Weiler, PE Jeff Weiler Digitally signed by Jeff Weiler Date: 2024.11.22 16:03:47 -05'00'

Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2024.11.26 13:46:08 -05'00'

$ 0.00

PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG

November 8, 2024

Michele Mitchell Assistant Project Manager

Bureau of Design and Construction Florida Department of Environmental Protection

Re: Dr. Von D. Mizell-Eula Johnson State Park- Restroom Improvements FDEP Contract No: CN230 Task Assignment No: 53, Project No: 61397C

Ms. Mitchell, We are requesting a time extension for the Dr. Von D. Mizell-Eula Johnson State Park- Restroom Improvements project. This extension would be at no additional cost to the FDEP. The current contract expires on 11/30/2024. We are requesting an extension until 4/25/2025 to allow enough time for the construction to be completed.

If you have any questions, or require additional information, please do not hesitate to contact me at (941) 505-1700 or electronically at rpalmer@weilerengineering.org.

Sincerely, Robin Palmer, P.E.

Project Manager Weiler Engineering Corporation

File details come from the government source that posted it. Updated .