This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for a project managed by Weiler Engineering Corporation. The change order pertains to the John Pennekamp Coral Reef State Park Restroom Replacement project (FDEP Contract No. CN230, Task Assignment No. 64, Project No. 61213). The document was executed on February 13-20, 2024, and approved by authorized representatives from FDEP including Budget Representative Tamika Bass, Project Manager Theresa Carron, and Contract Manager Ralph Perkins, along with Consultant Jeff Weiler, P.E., and Contract Authority Michael W. Foster Jr., P.E.
The change order extends the project timeline at no additional cost to FDEP. The task amount remains unchanged at $35,502.80, comprising $835.30 in reimbursable expenses and $34,667.50 in fixed fees. The original task execution date was April 7, 2023, with an original end date of March 20, 2024. The change order extends the completion deadline by 405 days to April 29, 2025, to allow sufficient time for the bidding and construction phases to be completed. No modification to contract pricing was required, as the extension was requested solely to accommodate the construction timeline while maintaining the existing contract value and terms.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN230 64 01 61213
John Pennekamp Coral Reef State Park Restroom Replacement
Weiler Engineering
Jeff Weiler, P.E. 941-505-1700 weiler7@mac.com
Ralph Perkins 850-245-2460 Ralph.Perkins@FloridaDEP.gov
Time extension to complete bidding and construction phase tasks per the attached request dated 02/12/2024.
$ 835.30 $ 34,667.50 $ 35,502.80 $ 835.30 $ 34,667.50 $ 35,502.80 $ 0.00 $ 0.00 $ 0.00
$ 835.30 $ 34,667.50 $ 35,502.80
04/07/2023
03/20/2024
03/20/2024
04/29/2025
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.02.13 09:52:58 -05'00'
Theresa Carron T.Carron Digitally signed by T.Carron Date: 2024.02.13 09:54:43 -05'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.02.13 11:31:00 -05'00'
Jeff Weiler, P.E. Jeff Weiler Digitally signed by Jeff Weiler Date: 2024.02.16 09:05:11 -05'00'
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2024.02.20 12:50:12 -05'00'
$ 0.00
PUNTA GORDA OFFICE: 201 WEST MARION AVENUE - SUITE 1306 | PUNTA GORDA | FL 33950 | TEL 941-505 -1700 | FAX 941-505 -1702 MARATHON OFFICE: 6805 OVERSEAS HIGHWAY | MARATHON | FL 33050 | TEL 305 -289-4161 | FAX 305 -289-4 1 6 2 WE INVITE YOU TO VISIT OUR WEB SITE AT WWW.WEILERENGINEERING.ORG OR EMAIL US AT INFO@WEILERENGINEERING.ORG
February 12, 2024
Theresa Carron Project Manager
Division of Recreation & Parks Florida Department of Environmental Protection
Re: John Pennekamp Coral Reef State Park Restroom Replacement FDEP Contract No: CN230 Task Assignment No: 64, Project No: 61213
Ms. Carron, We are requesting a time extension for the John Pennekamp Coral Reef State Park Restroom Replacement project. This extension would be at no additional cost to the FDEP. The current contract expires on 3/20/2024. We are requesting an extension until the end of our continuing services contract on April 29, 2025, to allow enough time for the construction to be completed.
If you have any questions, or require additional information, please do not hesitate to contact me at (941) 505-1700 or electronically at rpalmer@weilerengineering.org.
Sincerely, Robin Palmer, P.E.
Project Manager Weiler Engineering Corporation
File details come from the government source that posted it. Updated .