This is a Task Assignment Notification Form from the Florida Department of Environmental Protection (FDEP) for a design and engineering services contract. The contract is between FDEP and CPH, LLC, with Universal Engineering Sciences providing geotechnical services as a subcontractor. The project is located at De Leon Springs State Park in Florida and involves bulkhead and sidewalk repairs. The task assignment was executed on April 25, 2023, with a completion date of April 7, 2026.
The scope of work comprises eleven subtasks spanning preliminary site surveys and geotechnical evaluations, 60%, 90%, and 100% design development plans, environmental permitting services, bid phase support, preconstruction meetings, construction administration including shop drawing reviews and three site inspections, substantial and final walk-throughs, and project closeout services. The contract is structured entirely as a fixed-price engagement with no cost reimbursement component. The total contract value is $71,059.56, consisting of individual subtask costs ranging from $449.56 for preconstruction and walk-through meetings to $20,306.12 for permitting services. Payment is made upon FDEP approval of deliverables for each subtask. The project schedule spans multiple phases with critical activities including site survey and geotechnical evaluation (90-50 calendar days), 60% design plans (90 days), permitting coordination (150 calendar days), plan development progression (60-30 days), and construction administration services (265 calendar days).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT NOTIFICATION FORM
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description of Task:
Project Manager:
Schedule Start Date: Fixed Price Cost:
Completion Date: Cost Reimbursement not to exceed:
Total Task Amount:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 digit FLAIR Code: Total:
CN210 TA40 FDEP-DRP 61486C
De Leon Springs State Park Bulkhead & Sidewalk Repairs
CPH, Inc.
Joseph LoFaso Jr. P.E./Jason Toole, P.E. (407) 322-6841 jlofaso@cphcorp.com
Ralph Perkins, or Successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov
Bulkhead & Sidewalk Repairs @ De Leon Springs State Park per attached proposal dated 4/7/2023.
Del Cobb, or Successor
Upon Execution $ 71,059.56 4/7/2026
$ 71,059.56
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.04.25 13:13:29 -04'00'
Del Cobb Del Cobb Digitally signed by Del Cobb Date: 2023.04.21 08:56:26 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.04.26 09:02:54 -04'00'
Jason Toole, P.E.
Digitally signed by Jason L Toole DN: C=US, O=Florida, dnQualifier=A01410C0000017E5468FDBE00018735, CN=Jason L Toole Reason: I am the author of this document Location: your signing location here Date: 2023.04.26 21:42:29-05'00' Foxit PhantomPDF Version: 10.1.0
Jason L Toole
Michael W. Foster Jr., P.E. Michael W. Foster Jr., P.E.
Digitally signed by Michael W.
Foster Jr., P.E.
Date: 2023.04.28 11:28:17 -04'00'
61486C 37503000145 080039/23 423001 U3200 131500 QK $ 71,059.56
$ 71,059.56
April 7th, 2023
Del Cobb
Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard, MS 520 Tallahassee, FL 32399
RE: De Leon Bulkhead and Sidewalk Repair
Dear Del Cobb;
For your review, CPH LLC, has provided a proposal summary and man-hour documentation for the services tasks identified below:
Please review the attached Proposal Summary and deliverables.
Sincerely, Joseph LoFaso, Jr., P.E.
CPH, LLC
Robinson_MS Typewritten Text
CN210 TA40
De Leon Bulkhead and Sidewalk Repair
De Leon Springs State Park
CN210, TA40
Subtask 1: Preliminary
Description:
1A – Site Survey – Topographic Survey to be conducting along the existing bulkhead within the project limits along the riverbank between the swimming pool and the boat dock, as well as upon and adjacent to the existing ramp within the swimming pool which is to be replaced (see
“Survey Site Exhibit” for limits).
1B – Geotechnical Evaluation – Geotechnical data to be collected and a report compiled regarding the existing site soil conditions for the design and permitting of the foundations for the new bulkhead and concrete steps.
Deliverable:
1A – PDF of the Signed and Sealed Site Survey
1B – PDF of the Signed and Sealed Geotechnical Report
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 1
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
CPH, Inc. Survey Party Chief $ 54.62 20 $1092.40
CPH, Inc. Survey Instrument Man $ 48.10 20 $962.00
CPH, Inc. Sr. Survey CADD Technician $ 72.96 2 $145.92
CPH, Inc. Survey Project Manager/CADD $80.47 14 $1126.58
CPH, Inc. GPS (1 Man) $114.40 4 $457.60
CPH, Inc. Field Crew Coordinator $62.43 4 $249.72
CPH, Inc. Principal Surveyor $121.41 2 $242.82
CPH, Inc. Senior Professional Surveyor $98.89 4 $395.56
CPH, Inc. Field Technician/Designer $59.76 4 $239.04
Total for Subtask 1A: $4,911.64
SURVEY SITE EXHIBIT
Subtask 1B
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
Universal Engineering Sciences Principal Engineer $230.00 6 $1380.00
Universal Engineering Sciences Senior Project Engineer $129.99 10 $1299.90
Universal Engineering Sciences CADD Tech $69.99 38 $2659.62
Universal Engineering Sciences Clerical $60.00 20 $1200.00
Total for Subtask 1B: $6,539.52
Subtask 2: 60% documents
Description: The 60% documents shall consist of a set of plans and an engineer’s opinion of probable construction cost. The 60% plans shall be comprised of a Cover sheet, General Notes, SWPPP E&S
Control Plans, Plan Sheets, Grading Plan Sheets, and General Structural Details.
Deliverable: Digital Copies in PDF/CAD format of the 60% plans, engineer’s opinion of probable construction cost, and comment’s response letter, as described above.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 2
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
CPH, LLC Principal $178.23 10 $1782.30
CPH, LLC Sr. Project Manager $132.61 14 $1856.54
CPH, LLC Senior Structural Engineer $112.39 40 $4495.60
CPH, LLC Senior Design Technician $73.34 80 $5867.20
CPH, LLC Clerical $47.36 22 $1041.92
Total for Subtask 2: $15,043.56
Subtask 3: Permitting
Description: CPH shall prepare ecological elements of the SWERP Permit application and prepare an environmental report. CPH shall prepare the SWERP Report to address federal permitting requirements.
It is assumed the project will be permitted under 62-330.05 (5)(e)2 and 62-330.05 (12)(b)2 for minor replacement/repair within jurisdictional areas. CPH shall prepare and submit a permit application to process State and Federal authorization. Process applications with SJRWMD and FDEP 404. Further, it is assumed that the improvements will be designed to minimize impacts to wetlands but work within wetlands or regulated wetland buffers will be unavoidable but mitigation for minor impacts will not be required.
Subtask 3A - Site Evaluation & SJRMWD Preapplication Meeting - Internal project meeting to review scope requirements, permitting strategy and project deliverables. Conduct a site investigation to observe the existing conditions and to determine the environmental concerns with wetlands and/or threatened and endangered species. Document existing site conditions to prepare for environmental permit report and application. Prepare a Location Map, USGS Map, Soils Map, Preliminary Vegetation and Land Use Map and Approximate Wetland and Surface
Water Location Map covering the project site. Request, prepare for, and attend an electronic pre-application meeting with SJRWMD. Prepare a memorandum summarizing the SJRWMD meeting.
Subtask 3B – Permitting – The following permitting operations shall be conducted as part of this contract:
o Permitting Report: Coordinate with the Project Engineer to produce Dredge & Fill permit sketches (up to 4 plan views and cross sections) and for the preparation of the ecological elements of the Statewide Environmental Resource Permit (SWERP) application (Sections A and C) to SJRWMD and FDEP 404.
o Prepare a permitting Report detailing the environmental characteristics of the project area and the proposed improvements.
o Unified Mitigation Assessment Methodology (UMAM): An analysis will be prepared of pre- & post-development wetland impacts and functional value following the UMAM as required by SJRWMD and FDEP 404.It is assumed mitigation will not be required for the minor repair/replacement improvements. This scope does not include mitigation coordination or design of a mitigation that includes earthwork, hydrology modeling and preparation of construction plans.
o Address manatee protection during project construction.
o Permit Application – Prepare and submit permit applications to the SJRWMD and FDEP
404.
o Respond to up to two (2) request for additional information (RAI) from the SJRWMD and FDEP 404.
o SJRWMD Permit Issuance – Issuance of approved SJRWMD Permit. Review permit conditions and provide an email confirmation to the Client regarding receipt of permit and permit condition requirements.
o FDEP 404 Permit Issuance – Issuance of FDEP authorization or “No Permit Required” letter. Provide SJRWMD permit to FDEP 404. Review permit conditions and provide an email confirmation to the Client regarding receipt of permit and permit condition requirements.
Deliverable:
Subtask 3A: Draft Maps (as described above) and SJRWMD Pre-application Meeting Minutes notes
Subtask 3B: Permitting: Environmental Permitting Report, Responses to RAI’s (if applicable), copy of SJRMWD permit, copy of FDEP 404 authorization or NPR letter.
accurate, and timely. (Please do not alter this language)
Subtask 3A
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
CPH, LLC Principal Environmental Scientist $120.51 5 $602.55 CPH, LLC Senior Environmental Scientist $101.64 22 $2236.08 CPH, LLC Environmental Scientist $71.45 14 $1000.30 CPH, LLC GIS Analyst $76.67 14 $1073.38 Subtask 3B
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
CPH, LLC Principal Environmental Scientist $120.51 14 $1687.14 CPH, LLC Senior Environmental Scientist $101.64 70 $7114.80 CPH, LLC Environmental Scientist $71.45 47 $3358.15 CPH, LLC GIS Analyst $76.67 36 $2760.12 CPH, LLC Clerical $47.36 10 $473.60
Total for Subtask 3: $20,306.12
Subtask 4: 90% Plans
Description: The 90% documents shall consist of a set of plans, a letter responding to all comments from the 60% plans, and an engineer’s opinion of probable construction cost. The 90% plans shall be comprised of a Cover sheet, General Notes, SWPPP E&S Control Plans, Plan Sheets, Grading Plan Sheets, and General Structural Details.
Deliverable: Digital Copies in PDF/CAD format of the 90% plans, engineer’s opinion of probable construction cost, and comment’s response letter, as described above.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 4
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
CPH, LLC Principal $178.23 4 $712.92
CPH, LLC Sr. Project Manager $132.61 8 $1060.88
CPH, LLC Senior Structural Engineer $112.39 24 $2697.36
CPH, LLC Senior Design Technician $73.34 60 $4400.40
CPH, LLC Clerical $47.36 24 $1136.64
Total for Subtask 4: $10,008.20
Subtask 5: 100% Plans
Description: The 100% documents shall consist of a set of plans, a letter responding to all comments from the 90% plans, and an engineer’s opinion of probable construction cost. The 100% plans shall be comprised of a Cover sheet, General Notes, SWPPP E&S Control Plans, Plan Sheets, Grading Plan Sheets, and General Structural Details.
Deliverable:
Digital Copies in PDF/CAD format of the 100% plans, engineer’s opinion of probable construction cost, and comment’s response letter, as described above.
Three (3) Hard Copy Signed and Sealed sets of 100% plans
CD containing the final CAD files for the 100% plans.
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Fixed Price Cost:
Subtask 5
Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost
CPH, LLC Principal $178.23 4 $712.92
CPH, LLC Sr. Project Manager $132.61 8 $1060.88
CPH, LLC Senior Structural Engineer $112.39 16 $1798.24
CPH, LLC Senior Design Technician $73.34 24 $1760.16
CPH, LLC Clerical $47.36 16 $757.76
Total for Subtask 5: $6,089.96
Subtask 6: Bid Phase Services
Description: The Bid Phase services are as follows:
Attend one (1) Pre-Bid Meeting and respond to Bid RFI’s regarding the project. CPH assumes 3 Bid RFI’s.
Deliverable:
Attend one (1) Pre-Bid Meeting and provide PDF copies of Bid RFI responses (if applicable)
Subtask 6 – Bidding Phase Services
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC Sr. Structural Engineer $112.39 8 $899.12
CPH, LLC Clerical $47.36 16 $757.76
Total for Subtask 6: $1,656.88
Subtask 7: Preconstruction Meeting
Description: CPH shall attend one (1) Preconstruction Meeting
Attendance of one (1) Preconstruction Meeting
Subtask 7 – Preconstruction Meeting
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC Senior Structural Engineer $112.39 4 $449.56
Total for Subtask 7: $449.56
Subtask 8: Construction Administration Services
Description: The Construction Administration services are as follows:
Respond to construction RFI’s, review shop drawings and materials submittals, conduct up to three (3) site inspections during construction, at the request of FDEP. CPH assumes four (4) Construction RFI’s.
Subtask 8A – Shop Drawing, Material Submittal, and RFI responses: CPH to review and respond to all shop drawing, material submittal, and construction RFI’s issued by the contractor. CPH assumes all of these will be electronic documents for review (PDF format). CPH assumes four (4) construction RFI’s.
Subtask 8B – First Site Inspection: At the request of FDEP, CPH shall attend one (1) site inspection during construction.
Subtask 8C – Second Site Inspection: At the request of FDEP, CPH shall attend one (1) site inspection during construction.
Subtask 8D – Third Site Inspection: At the request of FDEP, CPH shall attend one (1) site inspection during construction.
Subtask 8A: PDF copies of all shop drawings and material submittals and construction RFI responses (if applicable)
Subtask 8C: Attendance of one (1) site inspection and provide meeting summary
Subtask 8D: Attendance of one (1) site inspection and provide meeting summary
Subtask 8D: Attendance of one (1) site inspection and provide meeting summary
Subtask 8A – Shop Drawing, Material Submittal, and RFI responses
Rate
Hours Total Fixed Price Cost
CPH, LLC Sr. Project Manager $132.61 4 $530.44
CPH, LLC Senior Structural Engineer $112.39 10 $1123.90
CPH, LLC Clerical $47.36 8 $378.88
Subtask 8B – First Site Inspection
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC Senior Structural Engineer $112.39 4 $449.56
Subtask 8C – Second Site Inspection
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC Senior Structural Engineer $112.39 4 $449.56
Subtask 8D – Third Site Inspection
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
Total for Subtask 8: $3,381.90
Subtask 9: Substantial Walk- Thru
Description: CPH shall attend one (1) substantial walk-thru and assist in preparation of the punch list for the project.
Attendance of one (1) substantial walk-thru meeting
PDF copy of the final punch list.
Subtask 9 – Substantial Walk-Thru
Rate
Hours Total Fixed Price Cost
CPH, LLC Clerical $47.36 2 $94.72
Total for Subtask 9: $544.28
Subtask 10: Final Walk- Thru
Description: CPH shall attend one (1) final walk-thru meeting of the project.
Attendance of one (1) final walk-thru meeting
Subtask 10 – Final Walk-Thru
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC Sr. Project Manager $132.61 4 $530.44
Total for Subtask 10: $980.00
Subtask 11: Project Closeout
Description: The Project Closeout services are as follows:
Review and certify the as-built drawing and perform project closeout.
One Reviewed and Certified As-Built Drawing and final project closeout.
Subtask 11 – Project Closeout
Firm Name Position Classification Hourly Rate
Hours Total Fixed Price Cost
CPH, LLC Senior Structural Engineer $112.39 6 $674.34
CPH, LLC Clerical $47.36 10 $473.60
Total for Subtask 11: $1,147.94
Project Schedule:
Activity Duration (Calendar Days)
Subtask 1A 90
Subtask 1B 50
Subtask 2: 60% plans 90
Subtask 3A: Site Evaluation & SJRMWD Preapplication Meeting
Subtask 3B: Permitting 120
Subtask 4: 90% Plans 60
Subtask 5: 100% Plans 30
Subtask 6: Bid Phase Services 30
Subtask 7: Preconstruction Meeting 1
Subtask 8A: Shop Drawing, Material Submittal and RFI responses
Subtask 8B: First Site Inspection 1
Subtask 8C: Second Site Inspection 1
Subtask 8D: Third Site Inspection 1
Subtask 9: Substantial Walk-Thru 30
Subtask 10: Final Walk-Thru 1
Subtask 11: Project Closeout 30
Summary of Fees:
Subtask Subtask Fixed Price Cost Subtask Reimbursable
Subtask 1A $4,911.64
Subtask 1B $6,539.52
Subtask 2: 60% plans $15,043.56
Subtask 3A: Site Evaluation & SJRMWD Preapplication Meeting
$4,912.31
Subtask 3B: Permitting $15,393.81
Subtask 4: 90% Plans $10,008.20
Subtask 5: 100% Plans $6,089.96
Subtask 6: Bidding $1,656.88
Subtask 7: Preconstruction Meeting $449.56
Subtask 8A: Shop Drawing, Material Submittal, and RFI Responses
$2,033.22
Subtask 8B: First Site Inspection $449.56
Subtask 8C: Second Site Inspection $449.56
Subtask 8D: Third Site Inspection $449.56
Subtask 9 Substantial Walk-Thru $544.28
Subtask 10: Final Walk-Thru $980.00
Subtask 11: Project Closeout $1,147.94
Total Fixed Price Cost: $71,059.56
Total Reimbursable Cost:
Overall Total Cost: $71,059.56
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.