This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract CN210, Task Assignment 29, involving the consultant firm CPH, Inc. The project is located at Honeymoon Island and concerns Entrance Area Improvements (Project 61199C). Key personnel include Ariel Elvambuena, P.E. as the Consultant Representative, and Jeffrey Whitfield as the FDEP Contract Manager. The change order was executed in May 2022 and reflects an extension request initiated by CPH, Inc. to allow for project completion and close-out activities.
The change order provides a time-only extension of 180 days, extending the task end date from June 10, 2022 to December 6, 2022 (subsequently referenced as January 10, 2023 in correspondence). The original task amount remains unchanged at $41,037.00 in reimbursements and $40,165.20 in fixed fees, for a total of $81,202.20. No increase in task amount was authorized with this change order. The extension was justified by the need to allow construction completion by the end of July with consultant close-out activities continuing through December, as documented in supporting correspondence dated May 16, 2022.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .