CN-370000-CN210-T8CO3.pdf
PDF 125 KB Posted
- Contract number
- CN210
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for contract CN210 with consultant CPH, Inc. The change order, numbered 03, pertains to Project No. 61199C for entrance area improvements at Honeymoon Island State Park. The contract manager is Jack Brady of FDEP, and the consultant representative is Ariel Elvambuena of CPH, Inc.
Change Order 03 extends the task completion timeline by 404 calendar days to allow for construction administration tasks. The original task was scheduled to end on December 31, 2019, with a present end date of March 21, 2020, and a new end date of April 29, 2021. The change order maintains the original task amount with no increase to costs. The total task amounts remain $99,448.27, consisting of $184.00 in reimbursement and $99,264.27 in fixed fees. The time extension is contingent upon actual construction start date, duration, and project-related contingencies, with an estimated 30-day preconstruction phase, approximately 180 days for construction, and 30 days for project certification and closeout.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .