Summary
This is a Task Assignment Change Order Form (Change Order No. 3) issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN210, Task Assignment No. 4, Project No. 61109C. The project involves St Andrews State Park campground reinvestment services and is administered by CPH, Inc., with FDEP Contract Manager Adam Browne and Consultant Representative Jason Toole, P.E. overseeing the work. The change order was executed on August 14-17, 2018, with an original task execution date of March 7, 2017, and an extended task end date of March 30, 2020.
The change order modifies Subtask 11B (Electrical Redesign/Replacement) by dividing it into two separate subtasks to align with actual milestone submissions and billing. Subtask 11B-1 covers 60% Electrical Redesign/Replacement services totaling $23,955.36 in fixed costs plus $55.50 in reimbursable expenses, while Subtask 11B-2 covers Final Electrical Redesign/Replacement totaling $15,877.24 in fixed costs plus $28.80 in reimbursable expenses. The overall combined cost is $39,832.60 with no change to the total contract fee or schedule. Payment will be made upon FDEP approval of deliverables for each subtask. The original task amount of $8,889.38 (reimbursable) plus $214,665.12 (fixed fee) remains unchanged, with the total contract amount maintained at $298,775.69.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .