This is a Task Assignment Change Order Form (Change Order No. 5) issued by the Florida Department of Environmental Protection (FDEP) for the Fort Zachary Taylor Historic State Park Administration Building Replacement project. The contract involves FDEP and CPH, LLC, an engineering and construction services firm based in Tampa, Florida. The contract number is CN210, Task Assignment number is 35, and the project number is 61390C. Kyle Bechtelheimer, P.E., serves as the consultant representative for CPH, LLC, while Ralph Perkins serves as the FDEP Contract Manager.

The change order adds construction administration and observation services to the existing task assignment, as requested in proposals dated August 16, 2024, and a time extension request dated August 19, 2024. The scope of work includes six construction-related subtasks: pre-construction meeting, review of shop drawings, RFI analysis and response, four site visits with observation reports (civil, architectural, structural for piling certification, and structural), initial punch list preparation, and final punch list with certification of completion. The net increase for this change order is $1,348.00 in reimbursable costs and $17,317.93 in fixed fees, bringing the total change order amount to $18,665.93. The total contract amount with all change orders is now $67,765.02. The original task end date of July 29, 2022, has been extended by 65 days to March 3, 2025. Payment will be made upon FDEP approval of deliverables for each subtask. The project is funded through two FLAIR codes with EO amounts of $263.41 and $18,402.52, respectively.

View the file

Other files

File Type Posted
CN-370000-CN210-T13.pdf PDF
CN-370000-CN210-T14.pdf PDF
CN-370000-CN210-T14CO2.pdf PDF
CN-370000-CN210-T15.pdf PDF
CN-370000-CN210-T22.pdf PDF
CN-370000-CN210-T23CO1.pdf PDF
CN-370000-CN210-T25CO1.pdf PDF
CN-370000-CN210-T26.pdf PDF
CN-370000-CN210-T33.pdf PDF
CN-370000-CN210-T35.pdf PDF
CN-370000-CN210-T35CO2.pdf PDF
CN-370000-CN210-T35CO3.pdf PDF
CN-370000-CN210-T38CO2.pdf PDF
CN-370000-CN210-T41.pdf PDF
CN-370000-CN210-T43.pdf PDF
CN-370000-CN210-T44.pdf PDF
CN-370000-CN210-T44CO6.pdf PDF
CN-370000-CN210-T46CO2.pdf PDF
CN-370000-CN210-T47.pdf PDF
CN-370000-CN210-T47CO2.pdf PDF
CN-370000-CN210-T48CO1.pdf PDF
CN-370000-CN210-T48CO2.pdf PDF
CN-370000-CN210-T49.pdf PDF
CN-370000-CN210-T49CO2.pdf PDF
CN-370000-CN210-T4CO3.pdf PDF
CN-370000-CN210-T4CO5.pdf PDF
CN-370000-CN210-T6.pdf PDF
CN-370000-CN210-T8CO3.pdf PDF
CN-370000-CN210-TA28.pdf PDF
CN-370000-CN210-A1.pdf PDF
CN-370000-CN210-CMC2.pdf PDF
CN-370000-CN210-CMC3.pdf PDF
CN-370000-CN210-CMC4.pdf PDF
CN-370000-CN210-CMC5.pdf PDF
CN-370000-CN210-T14CO3.pdf.crdownload CRDOWNLOAD file
CN-370000-CN210-T18CO3.pdf PDF
CN-370000-CN210-T1CO2.pdf PDF
CN-370000-CN210-T23.pdf PDF
CN-370000-CN210-T23CO3.pdf PDF
CN-370000-CN210-T25.pdf PDF
CN-370000-CN210-T3.pdf PDF
CN-370000-CN210-T30CO1.pdf PDF
CN-370000-CN210-T30CO2.pdf PDF
CN-370000-CN210-T31.pdf PDF
CN-370000-CN210-T32.pdf PDF
CN-370000-CN210-T35CO1.pdf PDF
CN-370000-CN210-T36CO1.pdf PDF
CN-370000-CN210-T37CO2.pdf PDF
CN-370000-CN210-T38.pdf PDF
CN-370000-CN210-T39.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

( ) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN210 35 5 61390C

Administration Building Replacement

CPH, LLC.

Kyle Bechtelheimer, P.E. (305) 274-4805 kbechtelheimer@cphcorp.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

Addition of construction administration services to the task assignment per attached proposal dated August 16, 2024, as well as a time extension per attached request dated August 19, 2024.

$ 2,000.00 $ 47,099.09 $ 49,099.09 $ 2,000.00 $ 47,099.09 $ 49,099.09 $ 1,348.00 $ 17,317.93 $ 18,665.93 $ 3,348.00 $ 64,417.02 $ 67,765.02

03/21/2022

07/29/2022

12/28/2024

03/03/2025

Tamika Bass

Terry McCullum, Jr.

Ralph Perkins

Kyle Bechtelheimer, P.E.

Michael W. Foster Jr., P.E.

61390C 37505000125 080039/22 423001 U3100 131500 QK $ 263.41

61390C 37505000125 080039/25 408001 U3100 131500 PF $ 18,402.52

$ 18,665.93

August 16, 2024

Terry McCullum, Jr.

Project Manager Florida Department of Environmental Protection Bureau of Design and Construction Division of Recreation and Parks

RE: Fort Zachary Taylor Admin Building Replacement Change Order 5

Dear Terry;

For your review, CPH, LLC., has provided a Revised Change Order to add Administration / Construction Observation Services to the contract to ensure the project is built according to specifications. The Change Order include additional time and fees associated with the work.

Please review the attached revised Proposal Summary and deliverables.

Sincerely, CPH, LLC.

Kyle Bechtelheimer Client Services Manager Engineering

5601 Mariner Street Suite 105

Tampa, FL 33609 Phone: 813.288.0233

Fax: 813.288.0433

Fort Zachary Taylor Admin Building August 12, 2024

Tasks:

Construction Services

Subtask 6 Pre-Construction Meeting

Subtask 7 Review of Shop drawings

Subtask 8 RFIs Analysis and response

Subtask 9 Site visits including visit observation reports and Pilling Certification

Substantial Completion

Subtask 10 Initial Punch list including Site Visit

Final Completion

Subtask 11 Final Punch List including site visit and Certification of Completion

Task 1 - Construction Services

Subtask 6 Pre-Construction Meeting

Description:

Attend a Virtual pre-construction meeting for the project to discuss: Project scope, project goal, schedule, key milestones, and deliverables to develop a consistent project approach. Including preparing the meeting minutes.

Deliverables:

Meeting Minutes in PDF Format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 6: Pre-Construction Meeting

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Sr. Project Manager $132.61 2 $ 265.22

CPH, LLC Project Manager $ 98.73 4 $ 394.92 Total $ 660.14

Subtask 7: Review of Shop drawings

Description:

Review of Shop drawings and follow-up with the contractor and other disciplines

Deliverables:

Shop Drawings reviewed in PDF format.

Shop drawing record list in PDF Format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 7: Review of shop drawings

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Sr. Project Manager $132.61 3 $ 397.83 CPH, LLC Project Manager $ 98.73 10 $ 987.30 CPH, LLC Architect $ 76.78 5 $ 383.90

Total $ 1,769.03

Subtask 8: RFIs Analysis and response

Description:

Analysis and response of RFI

Deliverables:

RFI Response in PDF format RFI Record List in PDF Format

Subtask 8: RFIs Analysis and response

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Sr. Project Manager $132.61 20 $ 2,652.20 CPH, LLC Project Manager $ 98.73 20 $ 1,974.60 CPH, LLC Architect $ 76.78 20 $ 1,535.60 CPH, LLC Senior Structural Engineer $112.39 10 $ 1,123.90 CPH, LLC Senior CAAD Technician $ 59.54 20 $ 1,190.80

Total $ 8,477.10

Subtask 9 : Site visits including visit observation report.

Description:

Site visits including observation reports.

a. 1 Site Visits Civil

b. 1 Site Visit - Architecture

c. 1 Site Visit Structure for Piling Certification

d. 1 Site Visit Structure

Deliverables:

Observation reports including pictures from visits.

a. 1 Visit Report Civil, in PDF Format

b. 1 Visit Report Architecture, in PDF format

c. 1 Visit Report Structure, including a signed Piling Certification in PDF Format.

d. 1 Visit report Structure in PDF Format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 9a : Site visit # 1 - Civil

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Field Technician $ 73.74 10 $ 737.40 Total $ 737.40

Reimbursable costs Travel / Transportation $ 208.00

Subtask 9b : Site visit # 2 - Architectural

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Field Technician $ 73.74 10 $ 737.40 Total $ 737.40

Reimbursable costs Travel / Transportation $ 208.00

Subtask 9c : Site visit # 3 Structural (Piling Certification)

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Field Technician $ 73.74 10 $ 737.40 Total $ 737.40

Reimbursable costs Travel / Transportation $ 208.00

Subtask 9d : Site visit # 4 Structural

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Field Technician $ 73.74 10 $ 737.40

Total $ 737.40

Reimbursable costs Travel / Transportation $ 208.00

Substantial Completion

Subtask 10: Initial Punch list

Description:

Site visit at the end of the project, draft a punch list and follow up with contractor for completion.

Deliverables:

Site Visit Report Initial Punch List, in PDF Format Initial Punch-List, in PDF Format

Subtask 10: Initial Punch List

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Sr. Project Manager $132.61 2 $ 265.22 CPH, LLC Project Manager $119.16 4 $ 476.64 CPH, LLC Field Technician $ 73.74 10 $ 737.40

Total $ 1,479.26

Reimbursable costs Travel / Transportation $ 208

Final Completion

Subtask 11: Final Punch list and Certification of completion

Description:

Site visit to review all items from the initial Punch List, prepare and sign the Certification of Completion

Deliverables:

Site visit report Final Punch List, in PDF format Final Punch List reviewed, in PDF Format Signed Certification of Completion, in PDF Format and Hard Copy (if requested)

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Subtask 11: Final Punch list and Certification of Completion

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

CPH, LLC Sr. Project Manager $132.61 4 $ 530.44 CPH, LLC Project Manager $119.16 6 $ 714.96 CPH, LLC Field Technician $ 73.74 10 $ 737.40

Total $ 1,982.80

Reimbursable costs Travel / Transportation $ 208 Postage (Hard Copy of Certification of Completion) $ 100

Fixed Price Cost:

Summary of Fees:

Administration / Constructions Observation Services

Task Fixed Price Cost Reimbursable

Subtask 6: Pre-Construction Meeting $ 660.14 Subtask 7: Review of shop drawings $ 1,769.03 Subtask 8: RFIs Analysis and response $ 8,477.10 Subtask 9a : Site visit - Civil $ 737.40 $ 208.00 Subtask 9b : Site visit - Architectural $ 737.40 $ 208.00 Subtask 9c : Site visit - Structural (Piling Certification) $ 737.40 $ 208.00 Subtask 9d : Site visit- Structural $ 737.40 $ 208.00 Subtask 10: Initial Punch List $ 1,479.26 $ 208.00 Subtask 11: Final Punch list and Certification of Completion $ 1,982.80 $ 308.00

Total Fixed Cost: $ 17,317.93 Total Reimbursable Cost: $ 1,348.00

Overall Total Cost: $ 18,665.93

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.