This Task Assignment Change Order Form (CO2) is issued by the Florida Department of Environmental Protection (FDEP) for Contract CN210 involving CPH, Inc. as the consultant. The change order modifies Task Assignment TA47 for the Big Shoals State Park Trail Bridge Replacement project, located at Big Shoals State Park. Key personnel include Kayla Sheffield, P.E. as the Consultant Representative and Ralph Perkins as the FDEP Contract Manager. The change order was necessitated by potential wetland impacts requiring additional permitting tasks as documented in an attachment dated May 13, 2024.
The change order increases the task amount by $23,319.45, bringing the total task cost from $76,675.86 to $99,995.31. The cost structure includes $1,190.00 in reimbursable expenses and $98,805.31 in fixed fees. The additional work consists of two main tasks: Task 10 (Additional Survey) totaling $4,046.14 and Task 11 (Ecological Services) totaling $19,273.31. Task 10 includes additional surveying work with deliverables of survey documentation. Task 11 encompasses ecological field work, application preparation and submittal to the Southwest Florida Water Management District (SRWMD), response to permitting inquiries, and Work of the District permit coordination, with a new task end date of March 3, 2025. The project schedule spans 194 calendar days with specific durations allocated for each subtask. Payment will be made upon FDEP approval of deliverables for each subtask as specified.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN210 TA47 CO2 61497C
Big Shoals State Park Trail Bridge Replacement
CPH, Inc.
Kayla Sheffield, P.E. 904-332-0999 ksheffield@cphcorp.com
Ralph Perkins or successor 850-245-2460 ralph.perkins@floridadep.gov
Due to potential wetland impacts, additional permitting tasks are required per the attached dated 5/13/24.
$ 1,190.00 $ 69,408.26 $ 70,598.26 $ 1,190.00 $ 75,485.86 $ 76,675.86
$ 0.00 $ 23,319.45 $ 23,319.45 $ 1,190.00 $ 98,805.31 $ 99,995.31
07/31/2023
06/21/2026
03/03/2025
03/03/2025
Tamika Bass
Richard Marcil
Ralph Perkins
Kayla Sheffield, P.E.
Michael W. Foster Jr., P.E.
61497C 37502000213 080039/23 423001 U3200 131500 QK $ 23,319.45
$ 23,319.45