This is a Task Assignment Change Order Form (Change Order No. 3) issued by the Florida Department of Environmental Protection (FDEP) for the Fort Zachary Taylor Historic State Park Administration Building Replacement project. The contract involves FDEP, the consultant CPH, LLC., and subcontractor Universal Engineering. The project is located at Fort Zachary Taylor Historic State Park, and the FDEP Contract Manager is Ralph Perkins. The change order was executed in April 2023 and represents a restructuring of deliverables without any modification to the contract's time or financial terms.

The change order restructures the scope of work across five subtasks: Pre-Design ($6,817.79 fixed fee plus $1,000.00 reimbursable), Preliminary Design at 30% ($8,719.10 fixed fee), Design Documents at 90% ($20,905.86 fixed fee), Construction Documents at 100% ($7,180.67 fixed fee plus $500.00 reimbursable), and Permitting ($3,475.67 fixed fee plus $500.00 reimbursable). The overall contract value remains unchanged at $49,099.09, consisting of $47,099.09 in fixed fees and $2,000.00 in reimbursable expenses. The original task execution date was March 21, 2022, with an original end date of July 29, 2022, extended to December 29, 2023 with zero net change in days under this change order. Payment is made upon FDEP approval of deliverables for each subtask, with all deliverables provided in PDF and CAD formats as applicable.

View the file

Other files

File Type Posted
CN-370000-CN210-T12.pdf PDF
CN-370000-CN210-T17.pdf PDF
CN-370000-CN210-T18CO1.pdf PDF
CN-370000-CN210-T18CO2.pdf PDF
CN-370000-CN210-T21.pdf PDF
CN-370000-CN210-T21CO2.pdf PDF
CN-370000-CN210-T21CO3.pdf PDF
CN-370000-CN210-T23CO2.pdf PDF
CN-370000-CN210-T29CO1.pdf PDF
CN-370000-CN210-T30.pdf PDF
CN-370000-CN210-T31CO1.pdf PDF
CN-370000-CN210-T34.pdf PDF
CN-370000-CN210-T37.pdf PDF
CN-370000-CN210-T37CO1.pdf PDF
CN-370000-CN210-T38CO1.pdf PDF
CN-370000-CN210-T39CO1.pdf PDF
CN-370000-CN210-T3CO2.pdf PDF
CN-370000-CN210-T42CO1.pdf PDF
CN-370000-CN210-T44CO3.pdf PDF
CN-370000-CN210-T46.pdf PDF
CN-370000-CN210-T46CO1.pdf PDF
CN-370000-CN210-T48.pdf PDF
CN-370000-CN210-T49CO1.pdf PDF
CN-370000-CN210-T5.pdf PDF
CN-370000-CN210-T5CO1.pdf PDF
CN-370000-CN210-T8.pdf PDF
CN-370000-CN210-T8CO1.pdf PDF
CN-370000-CN210-TA25 CO2.pdf PDF
CN-370000-CN210-TA3CO3.pdf PDF
CN-370000-CN210-TA42CO2.pdf PDF
CN-370000-CN210-TA4CO2.pdf PDF
CN-370000-CN210.pdf PDF
CN-370000-CN210-A1.pdf PDF
CN-370000-CN210-CMC2.pdf PDF
CN-370000-CN210-CMC3.pdf PDF
CN-370000-CN210-CMC4.pdf PDF
CN-370000-CN210-CMC5.pdf PDF
CN-370000-CN210-T14CO3.pdf.crdownload CRDOWNLOAD file
CN-370000-CN210-T18CO3.pdf PDF
CN-370000-CN210-T1CO2.pdf PDF
CN-370000-CN210-T23.pdf PDF
CN-370000-CN210-T23CO3.pdf PDF
CN-370000-CN210-T25.pdf PDF
CN-370000-CN210-T3.pdf PDF
CN-370000-CN210-T30CO1.pdf PDF
CN-370000-CN210-T30CO2.pdf PDF
CN-370000-CN210-T31.pdf PDF
CN-370000-CN210-T32.pdf PDF
CN-370000-CN210-T35CO1.pdf PDF
CN-370000-CN210-T36CO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN210 35 3 61390C

Fort Zachary Taylor Historic State Park Administration Building Replacement

CPH, LLC.

Kyle Bechtelheimer, P.E. (305) 274-4805 kbechtelheimer@cphcorp.com

Ralph Perkins or successor (850) 245-2460 Ralph.Perkins@FloridaDEP.gov

Consultant has provided a Change Order to the structure of deliverables on the contract to better fit the project. The Change Order does not include any additional time or fees associated with the work. See attached dated 3/31/23.

$ 2,000.00 $ 47,099.09 $ 49,099.09 $ 2,000.00 $ 47,099.09 $ 49,099.09

$ 0.00 $ 0.00 $ 0.00 $ 2,000.00 $ 47,099.09 $ 49,099.09

03/21/2022

07/29/2022

12/29/2023

12/29/2023

Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2023.04.06 11:01:40 -04'00'

Terry McCullum Jr. Terry McCullum, Jr.

Digitally signed by Terry McCullum, Jr.

Date: 2023.04.10 08:15:49 -04'00'

Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2023.04.11 09:50:56 -04'00'

Kyle Bechtelheimer, P.E.

Digitally signed by Kyle M Bechtelheimer DN: C=US, O=CPH INC., dnQualifier=A01410D0000017E96D48F500004E671, CN=Kyle M Bechtelheimer Reason: I am the author of this document Location: your signing location here Date: 2023.04.12 08:01:12-04'00' Foxit PhantomPDF Version: 10.1.3

Kyle M Bechtelheimer 4/12/2023

Michael W. Foster Jr, P.E. Michael W. Foster Jr., P.E.

Digitally signed by Michael W.

Foster Jr., P.E.

Date: 2023.04.20 16:16:44 -04'00'

$ 0.00

March 31, 2023

Terry McCullum, Jr.

Project Manager Florida Department of Environmental Protection Bureau of Design and Construction Division of Recreation and Parks

RE: Fort Zachary Taylor – Admin Building Replacement – Change Order 3

Dear Terry;

For your review, CPH, LLC., has provided a Change Order to the structure of deliverables on the contract to better fit the project. The Change Order does not include any additional time or fees associated with the work.

Please review the attached revised Proposal Summary and deliverables.

Sincerely, CPH, LLC.

Kyle Bechtelheimer Vice President / Associate

5601 Mariner Street Suite 105

Tampa, FL 33609 Phone: 813.288.0233

Fax: 813.288.0433

Matson_D Text Box

CN210 TA35 CO3

Fort Zachary Taylor Admin Building March 31, 2023

SubTask 1: Pre-Design

Description:

1A - Survey

• Topographic Survey at 25’ cross sections to include the location of visible above ground improvements and visible above ground utilities within the project area. Project area defined as a 9,500± square foot area (see “Survey Site Exhibit” for limits).

• Location of trees measured at diameter at breast height (dbh) within scope (size and common name only).

• Survey will be based on North American Datum 1983 (NAD83).

SURVEY SITE EXHIBIT

1B - Geotechnical Report

• Two (2) Standard Penetration Test (SPT) borings to depths of 30 feet below existing grade to provide data for foundation evaluation for the proposed admin building.

Deliverables:

• 1A – PDF/CAD file of survey area for use in design

• 1B – Geotechnical Report for use in design, PDF Format

Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely. (Please do not alter this language)

Reimbursable Cost:

Travel/Transportation $1,000

SubTask 2: Preliminary Design (30%)

• 30% Design shall include site due diligence, review of FEMA flood plain and Monroe County building permit criteria

• 30% Design shall include preparation of floor plan to submit to FDEP for review, meeting with

FDEP to discuss layout, and revising floor plan based on FDEP comments.

Deliverables:

• 30% Design – Floor Plan, PDF Format

Firm Name Position Classification Hourly

Rate Hours

Total Fixed Price

Cost

CPH, LLC Sr. Project Manager $132.61 1 $ 132.61

CPH, LLC Survey Crew (2 Man) $119.16 15 $ 1,787.40

CPH, LLC

Survey Project

Manager/CADD $ 80.47 10 $ 804.70

CPH, LLC GPS (2 Man) $146.66 3 $ 439.98

CPH, LLC Field Crew Coordinator $ 62.43 3 $ 187.29

CPH, LLC Principal Surveyor $121.41 3 $ 364.23

CPH, LLC Clerical II $ 47.36 3 $ 142.08

Total $ 3,858.29

Firm Name Position Classification Hourly

Rate Hours

Allowance Not to Exceed (NTE)

(SUB)Universal

Engineering Geotechnical N/A N/A $ 2,959.50

$ 6,817.79

SubTask 1 – Pre-Design

SubTask 1 Total

Subtask 1A – Survey

Subtask 1B – Geotechnical Report

Travel/Transportation N/A

Printing & Postage N/A

SubTask 3: Design Documents (90%)

• Design Documents will include plan sheets and specifications for the demolition of the existing administrative office, temporary trailer placement for administrative use during construction, and construction of the new office building.

• The new administrative office will be sized based on standard modular building sizes, and the approved floor plan.

• Design will incorporate ADA accessibility codes

• Design will include all Civil, Architectural, Structural, and Mechanical/Electrical/Plumbing needed to facilitate the bid of a modular building o Design does not include modifications to the modular structure nor components of the modular building. Design does not include HVAC o MEP design shall be limited to making connections to the stub-outs provided by the modular manufacturer, and tying into the service providers.

• Plans will be sized to 24” x 36” plan sheets

• Landscape Plans shall include minor tree disposition and planting around immediate area of new building

• Plan shall be prepared per Monroe County code for permit submittal

• Permit applications shall be prepared for owner signatures

Deliverables:

• 90% Plans and Permit Applications, PDF Format

Firm Name Position Classification Hourly

Rate Hours

Total Fixed Price

Cost

CPH, LLC Sr. Project Manager $132.61 12 $ 1,591.32

CPH, LLC Project Engineer $ 73.37 12 $ 880.44

CPH, LLC Senior CADD Tech $ 59.54 12 $ 714.48

CPH, LLC Principal Architect $130.60 7 $ 914.20

CPH, LLC Sr. Architectual Mngr. $ 87.45 9 $ 787.05

CPH, LLC Architect $ 76.78 14 $ 1,074.92

CPH, LLC Senior Struct. Engineer $112.39 14 $ 1,573.46

CPH, LLC MEP Proj. Designer $ 69.44 2 $ 138.88

CPH, LLC Principal Landscape Arch $126.83 5 $ 634.15

CPH, LLC Landscape Designer $ 58.60 7 $ 410.20

$ 8,719.10

SubTask 2 – Preliminary Design (30%)

SubTask 2 Total

• 90% Opinion of Construction Costs (OPCC), PDF Format

Travel/Transportation N/A

Printing & Postage N/A

SubTask 4: Construction Documents (100%)

• CPH will prepare hard copy and electronic versions of final construction documents, including details and specifications for bidding purposes.

Deliverables:

• 100% Construction Documents, PDF and CAD format

• 100% Opinion of Construction Costs (OPCC), PDF Format

Firm Name Position Classification Hourly

Rate Hours

Total Fixed Price

Cost

CPH, LLC Sr. Project Manager $132.61 28 $ 3,713.08

CPH, LLC Project Engineer $ 73.37 28 $ 2,054.36

CPH, LLC Senior CADD Tech $ 59.54 28 $ 1,667.12

CPH, LLC Principal Architect $130.60 17 $ 2,220.20

CPH, LLC Sr. Architectual Mngr. $ 87.45 23 $ 2,011.35

CPH, LLC Architect $ 76.78 34 $ 2,610.52

CPH, LLC Senior Struct. Engineer $112.39 34 $ 3,821.26

CPH, LLC MEP Proj. Designer $ 69.44 6 $ 416.64

CPH, LLC Principal Landscape Arch $126.83 11 $ 1,395.13

CPH, LLC Landscape Designer $ 58.60 17 $ 996.20

$ 20,905.86

SubTask 3 – Design Documents (90%)

SubTask 3 Total

Travel/Transportation $250

Printing & Postage $250

SubTask 5: Permitting

• CPH shall coordinate with selected contractor and contractors’ modular manufacturer to produce building permit set of plans. Scope includes minor modifications to the bid to adjust connections to manufacturer specific drawings

• CPH shall coordinate with the selected contractor and FDEP to submit and obtain Building

Permit for the construction of the new administrative building

• All permit applications fees shall be paid by FDEP, the contractor, or by CPH to be reimbursed by

FDEP

o Scope does not include Stormwater ERP Modification or Flood Management Permitting

Deliverables:

• Building Permits, PDF Format

Travel/Transportation $250

Printing & Postage $250

Fixed Price Cost:

Summary of Fees:

Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.

Firm Name Position Classification Hourly

Rate Hours

Total Fixed Price

Cost

CPH, LLC Sr. Project Manager $132.61 3 $ 397.83

CPH, LLC Project Engineer $ 73.37 1 $ 73.37

CPH, LLC Administrative $ 59.24 24 $ 1,421.76

CPH, LLC Senior CADD Tech $ 59.54 3 $ 178.62

CPH, LLC Principal Architect $130.60 1 $ 130.60

CPH, LLC Sr. Architectual Mngr. $ 87.45 1 $ 87.45

CPH, LLC Architect $ 76.78 3 $ 230.34

CPH, LLC Senior Struct. Engineer $112.39 5 $ 561.95

CPH, LLC MEP Proj. Designer $ 69.44 3 $ 208.32

CPH, LLC Principal Landscape Arch $126.83 1 $ 126.83

CPH, LLC Landscape Designer $ 58.60 1 $ 58.60

$ 3,475.67 SubTask 5 Total

SubTask 5 – Permitting

SubTask Task Fixed

Price Cost Reimbursable

1 - Pre-Design $6,817.79 $1,000.00

2 - Preliminary Design (30%) $8,719.10

3 - Design Documents (75%) $20,905.86

4 - Construction Documents (100%) $7,180.67 $500.00

5 - Permitting $3,475.67 $500.00

Total Fixed Cost: $47,099.09

Total Reimbursable Cost: $2,000.00

Overall Total Cost: $49,099.09