Attachment 7 - Drawings Part-6.pdf

PDF 14 MB Posted

Attached to
Y1DA--EHRM Infrastructure Upgrades Construction Jefferson Barracks Federal contract opportunity
Solicitation number
36C77623R0009
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document provides details for a federal contract solicitation to provide infrastructure upgrades at the St. Louis Jefferson Barracks VA Medical Center. The solicitation seeks a general contractor to upgrade electrical systems including panels, power, bonding and UPS; assess and potentially upgrade HVAC systems; renovate and expand existing space through demolition, new construction and finish work; renovate the existing data center; upgrade communication, security and fiber optic infrastructure; and conduct hazardous material abatement. The work will occur across 25 buildings on the campus including buildings 1 through 3, 3T, 18, 23 through 26, 51 through 61, 75 and other site locations. The soliciting agency is the Department of Veterans Affairs Technology Acquisition Center located in Austin, Texas.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--EHRM Infrastructure Upgrades Construction Jefferson Barracks, newest first.
File Type Posted
36C77623R0009 0005.pdf PDF
36C77623R0009 0004.pdf PDF
657-21-701JB - 100 PC - Basis of Design.pdf PDF
329000-05-R1 Sod Certificate.pdf PDF
32 32 23 01R1 - Mechanically Stabilized Earth Wall System RESPONSE.pdf PDF
Attachment 43 - Construction Wage Rates - St. Louis 3-3-23.pdf PDF
36C77623R0009 0003.pdf PDF
36C77623R0009 0002.pdf PDF
Site Visit Sign-in Sheet - St. Louis 2-28-23.pdf PDF
36C77623R0009 0001.pdf PDF
36C77623R0009 - 2-16-23.pdf PDF
Attachment 11 - Drawings Part-10.pdf PDF
Attachment 12 - Drawings Part-11.pdf PDF
Attachment 13 - Drawings Part-12.pdf PDF
Attachment 18 - Drawings Part-17.pdf PDF
Attachment 31 - Drawings Part-30.pdf PDF
Attachment 35 - Envr. Report - Appendix A.pdf PDF
Attachment 38 - Envr. Report - Drawings.pdf PDF
Attachment 42 - Limitations on Subcontracting - Construction.docx DOCX document
Attachment 45 - Site Visit Instructions.pdf PDF
Attachment 4 - Drawings Part-3.pdf PDF
Attachment 10 - Drawings Part-9.pdf PDF
Attachment 14 - Drawings Part-13.pdf PDF
Attachment 20 - Drawings Part-19.pdf PDF
Attachment 21 - Drawings Part-20.pdf PDF
Attachment 25 - Drawings Part-24.pdf PDF
Attachment 26 - Drawings Part-25.pdf PDF
Attachment 28 - Drawings Part-27.pdf PDF
Attachment 29 - Drawings Part-28.pdf PDF
Attachment 32 - Drawings Part-31.pdf PDF
Attachment 39 - ICRA ILSM Tool - MCM 001S-03 Att B.zip ZIP file
Attachment 1 - Specifications.pdf PDF
Attachment 5 - Drawings Part-4.pdf PDF
Attachment 6 - Drawings Part-5.pdf PDF
Attachment 9 - Drawings Part-8.pdf PDF
Attachment 16 - Drawings Part-15.pdf PDF
Attachment 22 - Drawings Part-21.pdf PDF
Attachment 24 - Drawings Part-23.pdf PDF
Attachment 36 - Envr. Report - Appendix B.pdf PDF
Attachment 41 - COVID-19 Safety Protocols 12-14-21.pdf PDF
Attachment 44 - Contractor Safety - Environmental Form.docx DOCX document
Attachment 2 - Drawings Part-1.pdf PDF
Attachment 3 - Drawings Part-2.pdf PDF
Attachment 8 - Drawings Part-7.pdf PDF
Attachment 15 - Drawings Part-14.pdf PDF
Attachment 17 - Drawings Part-16.pdf PDF
Attachment 19 - Drawings Part-18.pdf PDF
Attachment 23 - Drawings Part-22.pdf PDF
Attachment 27 - Drawings Part-26.pdf PDF
Attachment 30 - Drawings Part-29.pdf PDF
Show all 50

Y1DA--EHRM Infrastructure Upgrades Construction Jefferson Barracks has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

4160 VO

LTS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

CONNECTING CORRIDORS

TO BUILDING 23

CONNECTING CORRIDORS

TO BUILDING 24

UP

UP

UP

UP

EXTERIOR

SURFACE

BASEMENT

LEVEL

TRENCH

STAIRS TO

BASEMENT

LEVEL

ROOF

BELOW

A

A

A.1

A.1 A.3A.2 B C.1

D.2

D.2C

D.1

D.1D

E.1

E

F

F

G

G

H

H

J.1

J

H.2 J.2

K

L M

M

N

N

O

O

P

P Q

R.3

R.1

R.1 R.2

S U

V.3

V.3T V.2V V.1

A.4 B.1 B.2 C.2 R.4 T.1 T.2 U.1

4.7

8.1

10.1

G.1

G.1 K.2

N.1

N.1

R

01EP401a

01EP401b

01EP401a

01EP401b

TR

C102D

01EP401a

01EP401a

01EP401b

01EP401b

MEDICAL PROVIDERS

MEDICAL PROVIDERS

PREP

TRAINING

MENS RESTROOM/LOCKER

ROOM

CORRIDOR

110 KITCHENETTE

CORRIDOR

1-L11(S) 1-L11(L)

1-L12

H1

EC1

N1

N1A

MCC-EMSP

EM1

EM1A

1-L13A

1-L13R

1-L13L

EC13

1-L15

1-L14

RF

RF

SERVER RM

1E07

OPEN OFFICES

1E09

TR

1E15

OFFICE

C105

EXISTING DISPATCH

1E11A

GROUP ROOM

1W08B

GROUP ROOM

1W08A

OFFICE

1W09

VEST.

1W08

TOILET

1W07A

WAITING ROOM

1W07OFFICE

1W10

OFFICE

1W11A

CORRIDOR

H119

OFFICE

1W06

TOILET

1W05

VEST.

1W06A

OFFICE

1W11B

CONSULT

1W12 OFFICE

1W04

CORRIDOR

1W13

CONSULT

1W03

MECH. RM.

1W02CONSULT

1W14

OFFICE

1W15

ELEV 1

E1

MECH

1W01

CORRIDOR

H116

OFFICE

1W16

STAIR 3

S103

TOILET

1W31

CONSULT

1W17

STORAGE

1W18

WAITING

1W30A

OFFICE

1W18A

OFFICE

1W20

OFFICE

1W21

OFFICE

1W22A

OFFICE

1W30

OFFICE

1W29

TOILET

1W28

WAITING RM.

1W27

OFFICE

1W22

HALLWAY

1W24

TOILET

1W25

STORAGE

1W23

SHARED OFFICE

C106A

OFFICE

C106

OFFICE

C108

LACTATION

C108A

CORRIDOR

H111

OT GROUP ROOM

C104

CONTROL

C102E

FES UTILITY

C101

STAIR 2

S102

VEST.

H109

CLEAN UTILITY

C102J

CORRIDOR

H113

OFFICE

C110COPY RM.

C109

OFFICE

C111

OFFICE

C112

OFFICE

C113

OFFICE

C114

OFFICE

C115

OFFICE

C116

OFFICE

C117

OFFICE

C115A

OFFICE

C115B

AGENT CASHIER

C119

OFFICE

C122A

OFFICE

C122

VACANT

C120

HAC

C121

VACANT

C123C

OFFICE

C123B

OFFICE

C123A

LOBBY

C124

HALLWAY

C123

CORRIDOR

H106

TOILET, MALE

C127

TOILET, FEMALE

C126

OFFICE

C125

CLOSET

C126A

STAIRWELL NO. 1

S101

CLEAN LINEN RM.

1E136

COPY/STORAGE

1W13A

STORAGE

C129

WAITING RM.

C131

ALCOVE

H113A

CORRIDOR

H118

CORRIDOR

H117

CORRIDOR

1W28A

ALCOVE

H117A

CORRIDOR

H114 RECEPTION

C118

CORRIDOR

H110 CORRIDOR

H108

CORRIDOR

H107

WAITING RM.

C128

CORRIDOR

H115

TOILET

C103

CLOSET

1W06B

CHASE

CH-C-1

ELEVATOR NO. 2

E2

CHASE

CH-1W-4

CHASE

CH-1W-3

CHASE

CH-1W-2

CHASE

CH-C-2

CHASE

CH-C-3

CHASE

CH-1W-1

D.W.

E3

UTILITY

E4

WAITING RM.

H115A

MAIL RM.

C115C

AGENT CASHIER

C119B

TOILET

C127

STAIR 4

S104

CHASE

CH-E-2

CHASE

CH-E-1

CHASE

CH-C-5

CHASE

CH-1W-6

CHASE

CH-C-4

COMMUNITY BREAK ROOM

1W32

MVP

C102A

STORAGE

106A

HOLDING

ARMS

WOMENS RESTROOM/LOCKER

ROOM

STORAGE

1E13

INTERVIEW

STORAGE

1E02

STORAGE

1E01

STORAGE

1E14

MEDICATION/LOGISTICS

EXAM

EXAM

EXAM

SOILED UTILITY

EXAM

EXAM

DOCTOR OFFICE

IMAGING

RESTROOM

EXAM

EXAM

EXAM

LPN/VITALS

WAITING

RECEPTION

EXISTING STORAGE

1E11

CORRIDOR

CORRIDOR

BLDG 01

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL

FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED.

ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE

DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE

NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO

ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN

ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH

VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

01EP101

BLDG 01 - FLOOR 1 - ELECTRICAL PLAN

SPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM INFRASTRUCTURE

UPGRADES

ST. LOUIS VA MEDICAL CENTER - JEFFERSON

BARRACKS MO

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

- 1/16" = 1'-0"

1 BLDG 01 - FLOOR 1 - ELECTRICAL PLAN

0' 8' 16' 32'

GENERAL NOTES

KEY PLAN

PROJECT

NORTH

KEY NOTES

PROJECT

NORTH

Revisions: Date:

LRL/WNM LLT/JPS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

A

A

A.1

A.1 A.3A.2 B C.1

D.2

D.2C

D.1

D.1D

E.1

E F G H

J.1

J

H.2 J.2

K

L

M N O P Q

R.2

R

R

R.1

R.1

S U

V.3

V.3T

V.2

V.2V V.1

A.4 B.1 B.2 C.2 R.3 T.1 T.2 U.1

10.1

8.1

01EP402

01EP402

LAB.

2C07

LAB.

2C08

UNDER CONSTRUCTION

2C09

CORRIDOR

H204

OFFICE

2C04

VETERAN HEALTH EDUCATION

2C03

LOW VISION THERAPY

2C02OFFICE

2C01A

LOW VISION CLINIC

2C01

RECEPTION

2C01B

WAITING RM.

2E27

TOILET

2E28

OXYGEN STORAGE

2E30

EXAM

2E29

TOILET, STAFF

2E31

OFFICE

2C05

HAC

2C06

CORRIDOR

H210 STORAGE

2E16A

EXAM

2E21

EXAM

2E20

TOILET

2E22A

CORRIDOR

H203

OFFICE

2E22

STAIR 1

S201

EXAM

2E26

TOILET

2E25B

EXAM

2E25A

OFFICE

2E23

TOILET

2E24

EXAM

2E25

HIMS WORK ROOM

2C19

CORRIDOR

H206

EXAM

2W22C

TOILET

2W23

OFFICE

2W26

OFFICE

2W24

MECH

2W25

CORRIDOR

H207

OFFICE

2W27

OFFICE

2W28

OFFICE

2W28A

OFFICE

2W29

OFFICE

2W28C

TELEHEALTH

2W28B

CLEAN SUPPLY

2W29A

STORAGE

SW29C

OFFICE

2W29B

TOILET, STAFF

2W29F

VEST.

2W29E

TELEHEALTH

2W29D

OFFICE

2W33

EXAM

2W32

OFFICE

2W30

HAC

2W36

TOILET

2W34

SHARED OFFICE

2W35

STAIR 3

S203

STORAGE

2C22

TOILET

2C24

STORAGE

2C21

LAB.

2C20

OFFICE

2C29

STAIR 2

S202

LAB.

2C23

TOILET, FEMALE

2C27

HAC

2C28

EXAM

2C25

EXAM

2C11

OPTICAL SHOP

2C12

NURSE STATION

2C13

EXAM

2C14

ELEC RM.

2C18

KITCHENETTE

2C17

SHARED OFFICE

2C15

TOILET, MALE

2C16

CORRIDOR

H205

CLOSET

2C20A

TOILET

2W03

MED. PREP.

2W04

STORAGE

2W05

BREAK RM.

2W06

TOILET

2W08

EXAM

2W07

TOILET

2W11

EXAM

2W10

EXAM

2W09

EXAM

2W12

RECEPTION

2W01

CORRIDOR

H208

CORRIDOR

H209

OFFICE

2W21

PATIENT NOUR.

2W22

OFFICE

2W22ACLEAN LINEN / STORAGE

2W22B

CORRIDOR

2W19

TOILET, STAFF

2W20

SHARED OFFICE

2W18

TOILET

2W17

TOILET

2W14

EXAM

2W15

EXAM

2W16

EXAM

2W13

FAX RM.

2W02

ELEV 1

E1

CHASE

CH-C-6

CHASE

CH-C-3

CHASE

CH-C-1

ELEC. CLOSET

2C03A

CHASE

CH-E-3

CHASE

CH-W-1

CHASE

CH-C-5

CHASE

CH-W-2

CHASE

CH-W-4

CHASE

CH-W-3

CHASE

CH-W-5

ELEVATOR NO. 2

E2

CHASE

CH-C-4

D.W.

E3

CHASE

CH-W-8

CHASE

CH-W-6

CHASE

CH-W-7

CHASE

CH-E-8

STAIR 4

S204

01EP402

01EP402

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

OI&T

2C10A

EC2A

1-L21L

1-L21R

1-L22L1-L22R

2CEC

EC2B

1-L23

TR

2C10A

LAB.

2C10

SERVER RM.

2C10B

2WMC

BLDG 01

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL

FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED.

ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE

DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE

NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO

ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN

ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH

VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

01EP102

BLDG 01 - FLOOR 2 - ELECTRICAL PLAN

SPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM INFRASTRUCTURE

UPGRADES

ST. LOUIS VA MEDICAL CENTER - JEFFERSON

BARRACKS MO

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

- 1/16" = 1'-0"

1 BLDG 01 - FLOOR 2 - ELECTRICAL PLAN

PROJECT

NORTH

0' 8' 16' 32'

GENERAL NOTES

KEY PLAN

PROJECT

NORTH

KEY NOTES

Revisions: Date:

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

CORRIDOR

H302

STAIRWELL NO.

S301

STORAGE

3E02

HAC

3E01

KITCHEN

3E03

CORRIDOR

H301

187 SF

OFFICE

3E04

131 SF

OFFICE

3E04A

OFFICE

3E05

TRAINING RM.

3E07

VOL. SERVICE

KIOSK

3E06

CLOTHING RM.

3E08

LAB.

3E12

STORAGE

3E12A

MECH. RM.

3E11

OFFICE

3E10

LAB.

3E09

OFFICE

W307

CONFERENCE

RM.

W308

OFFICE

W309

COPY ROOM

W306

OFFICE

W304

OFFICE

W305

TOILET, MALE

W301

STAFF LOUNGE

W302

MAIL RM.

W303

OFFICE

W319

OFFICE

H308

OFFICE

H307

STORAGE

W310

OFFICE

W311

LOBBY

W318

OFFICE

H306

COLD RM.

3E21A

TOILET, FEMALE

E311

BREAK RM.

E313

HAC

E312 TOILET, MALE

E310

OFFICE

E309

OFFICE

E308

OFFICE

E301

OFFICE, OPEN

E302

OFFICE

E305

OFFICE

E307

OFFICE

E306

STORAGE

E303A

TR

E303

OFFICE

E304

COLD RM.

3E21

HAC

3C20

LAB.

3C21

474 SF

SHARED OFFICE

3C26

MECH. RM.

3C23

LAB.

3C17

CORRIDOR

H304

LAB.

3C18

CORRIDOR

H305

LAB.

3C27

STAIRWELL NO.

S302

OFFICE

C305

OFFICE

C307

PREP. RM.

3C29

TOILET

C307A

PREP. RM.

3C28

OFFICE

C304

OFFICE

C306

MECH. RM.

W314

DATA CLOSET

W315

STAIRWELL NO.

S303

OFFICE

W312

TOILET, FEMALE

W313

TR

3C13

LAB.

3C15 LAB.

3C12

STERILIZATION

RM.

3C16

LAB.

3C09

LAB.

3C07

LAB.

3C08

CORRIDOR

H303

OFFICE

C303 OFFICE

C302

STORAGE

C301

MVP OFFICE

3C04

MECH. RM.

3C06

DARK RM.

3C06A

RECEPTION

W316

CHASE

CH-W-1

CHASE

CH-W-2

ELEV 1

E1

CHASE

CH-C-8

CHASE

CH-W-5

CHASE

CH-W-3

CHASE

CH-C-7

CHASE

CH-C-6

CHASE

CH-C-5

CHASE

CH-C-3

CHASE

CH-C-4

CHASE

CH-C-2

CHASE

CH-C-1

CHASE

CH-E-2

CHASE

CH-E-4

CHASE

CH-E-5

CHASE

CH-E-6

CHASE

CH-E-1

CHASE

CH-E-3

CHASE

CH-W-4

D.W.

E3

CHASE

CH-E-7

CHASE

CH-C-9

CHASE

CH-C-10

UP

SP

CHASE

CH-E-10

CHASE

CH-E-9

DNDN

DN

UP

DN

STAIRWELL NO.

S304

OFFICE

3C11

CORRIDOR

H302

A

A

A.1

A.1 A.3A.2 B C.1

D.2

D.2C

D.1

D.1D

E

F

F

G

G

H

H

J.1

J

H.2 J.2

K

L M

M

N

N

O

O

P

P Q

R.2

R

R R.1

S U

V.3

V.3T V.2V V.1

A.4 B.1 B.2 C.2 R.3 T.1 T.2 U.1

10.1

8.1

OFFICE

H309

OFFICE

W321

OFFICE

W320

01EP403b

1 - L31A

EC3A

1 - L31B

1 - L32R

1 - L32L

1 - L32A

3CEC

EP3 - L

EP3 - R

225A

ENCLOSED

CKT BKR

1 - L34

1 - L33

EC3B

ABANDONED PANEL

USED AS PULLBOX

H302

3LL1

3EML1 - 2

3EML1 - 1

01EP403a

01EP403a

01EP403a

01EP403a

01EP403b

01EP403b

01EP403b

BLDG 01

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL

FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED.

ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE

DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS OTHERWISE

NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO

ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN

ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH

VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

01EP103

BLDG 01 - FLOOR 3 - ELECTRICAL PLAN

SPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM INFRASTRUCTURE

UPGRADES

ST. LOUIS VA MEDICAL CENTER - JEFFERSON

BARRACKS MO

657-21-701JB

03/31/2022 LRL/WNM JBB

CONSTRUCTION

DOCUMENTS

- 1/16" = 1'-0"

1 BLDG 01 - FLOOR 3 - ELECTRICAL PLAN

PROJECT

NORTH

0' 8' 16' 32'

GENERAL NOTES

KEY PLAN

PROJECT

NORTH

KEY NOTES

Revisions: Date:

UP

LTS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

1 2 3 5 7 8 9 104 6

4.5 6.5

A

B

D

C

D.1

B

PRL - 1

MDP - L

MDP - R

ELEVATOR

MACHINE

AND MAIN

DISCONNECT

LB - 1

AC - EAST

02EP400

02EP400

2-DP-TRAB 1

MDP-2 1

02EP400

02EP400

E FG

H

I

MDP - R

STORAGE

G07

STORAGE

G06

STORAGE

G07A

TOILET

G05A

HAC

G05B

STORAGE

G05

TR

G04

STORAGE

G03

ELEVATOR

EQUIP.

G01

TRANSFORMER

RM.

G09

MECH. RM.

G08

STORAGE

G02

CORRIDOR

H003

STAIRWELL NO. 1

S001

ELEVATOR NO. 1

E-00 STORAGE/ COPY

RM.

G02A

STORAGE

G02B

CHASE

CH-0-1

CORRIDOR

H001

PANEL 2-G03A

PANEL 2-G03B

2-DP-TRAB

2-DP-TRAB

BLDG 02

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR

SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO

BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER

TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL

REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL

CONFORM WITH VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

9. REFERENCE ONE-LINE DIAGRAM ON SHEET 02EP601 FOR CONDUIT AND WIRE

SIZING.

AREA OF WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO

02EP100

BLDG 02 - FLOOR 0 - ELECTRICAL

PLANSPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM INFRASTRUCTURE

UPGRADES

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

- 3/16" = 1'-0"

1 BLDG 02 - FLOOR 0 - ELECTRICAL PLAN

KEY PLAN

GENERAL NOTES

0' 2' 4' 8'

KEY NOTES

Revisions: Date:

1 EQUIPMENT TO BE ADDED. REFERENCE ONE-LINE DIAGRAM ON SHEET 02EP601

FOR ADDITIONAL INFORMATION.

EXISTING PANEL TO BE MODIFIED. REFERENCE ONE-LINE DIAGRAM ON SHEET

02EP601 FOR ADDITIONAL INFORMATION.

PROJECT

NORTH

PROJECT

NORTH

UP

UP

UP

UP

UP

4160 VO

LTS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

OFFICE

CLOSET

116A

TOILET

CORRIDOR

H105

OFFICE

OFFICE

OFFICE

MECH. RM.

TR

OFFICE

STORAGE

110A

OFFICE

OFFICE

CORRIDOR

H101

OFFICE

OFFICE

105A

OFFICE

OFFICE

CORRIDOR

H103

CLOSET

118A

OFFICE

OFFICE

OFFICE

119A

OFFICE

TOILET

STAIRWELL NO.

S101

LOBBY

ELEVATOR

LOBBY

123A

VEST.

CORRIDOR

H102

ELEVATOR NO.

E-01

CLOSET

113ACORRIDOR

H104

DN

CHASE

CH-1-1

CHASE

CH-1-3

1 2 3 5 7 8 9 104 6

4.5 6.5

A

B

D

C

L1 - 4

L1 - 1

L1 - 2

L1 - 3

LE - 1

02EP401

02EP401

02EP401

02EP401

E FG

H

I

2-G03A-6,8

02-CU-3-G04

02-CU-3-111

02-CU-2-209 02-CU-3-308

2-111A-6,8 2-209A-6,8 2-308A-6,8

TYP.

BLDG 02

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR

SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO

BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER

TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL

REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL

CONFORM WITH VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO

02EP101

BLDG 02 - FLOOR 1 - ELECTRICAL

PLANSPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM INFRASTRUCTURE

UPGRADES

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

- 3/16" = 1'-0"

1 BLDG 02 - FLOOR 1 - ELECTRICAL PLAN

KEY PLAN

GENERAL NOTES

0' 2' 4' 8'

KEY NOTES

Revisions: Date:

PROVIDE CONDUIT AND WIRE FROM CONDENSING UNIT TO ASSOCIATED AC UNIT

AS REQUIRED PER MANUFACTURER'S INSTRUCTIONS. COORDINATE WITH

MECHANICAL CONTRACTOR AS REQUIRED.

PROJECT

NORTH

PROJECT

NORTH

4160 VO

LTS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

CONFERENCE

RM.

OFFICE

212E

OFFICE

212C

OFFICE

212F

OFFICE

212A

TR

TOILET, MALE

TOILET, FEMALE

OFFICE

OFFICE

OFFICE

OFFICE

STAIRWELL NO.

S201

STORAGE

201A

HAC

FEC

FEC

OFFICE

CORRIDOR

H202

ELEVATOR NO.

E-02

8 SF

CHASE

CH-2-1

4 SF

CHASE

CH-2-2

DN

RAD

RAD

OFFICE

212D

UP

CHASE

CH-2-3

CHASE

CH-2-4

ROOF BELOW

FE

FAP

FAP

1 2 3 5 7 8 9 104 6

4.5 6.5

A

B

D

C

L2 - 1

L21 - A

02EP402

02EP402

02EP402

02EP402

E FG

H

I

BLDG 02

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR

SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO

BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER

TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL

REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL

CONFORM WITH VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO

02EP102

BLDG 02 - FLOOR 2 - ELECTRICAL

PLANSPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM INFRASTRUCTURE

UPGRADES

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

- 3/16" = 1'-0"

1 BLDG 02 - FLOOR 2 - ELECTRICAL PLAN

KEY PLAN

GENERAL NOTES

0' 2' 4' 8'

KEY NOTES

Revisions: Date:

PROJECT

NORTH

PROJECT

NORTH

LTS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

DN

DN

RAD

DN

1 2 3 5 7 8 9 104 6

4.5 6.5

A

B

D

C

L3 - 1

L3 - 2

L1 - 4

L3 - 5

02EP403

02EP403

02EP403

02EP403

E FG

H

I

STAIRWELL NO. 2

S302

OFFICE

TOILET

OFFICE

OFFICE

316A

OFFICE

316B

KITCHENETTE

STAIRWELL NO. 1

S301

STORAGE

301A

OFFICE

302A

OFFICE

OFFICE

OFFICE

306OFFICE

OFFICE

307A

MECH. RM.

OFFICE

OFFICE

310A

OFFICE

STAIRWELL NO. 3

S303

OI&T

317A

MECH. RM.

317C

OI&T

317B

OFFICE

OFFICE

CLOSET

304A

OI&T

311A

CORRIDOR

H301

CORRIDOR

H302

CORRIDOR

H303

ELEVATOR NO. 1

E-03

CHASE

CH-3-1

TR

BLDG 02

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR

SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO

BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND

RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS

WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF

MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER

AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER

TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL

REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL

CONFORM WITH VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO

02EP103

BLDG 02 - FLOOR 3 - ELECTRICAL

PLANSPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM INFRASTRUCTURE

UPGRADES

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

- 3/16" = 1'-0"

1 BLDG 02 - FLOOR 3 - ELECTRICAL PLAN

KEY PLAN

GENERAL NOTES

0' 2' 4' 8'

KEY NOTES

Revisions: Date:

PROJECT

NORTH

PROJECT

NORTH

UP

DN

UP

4160 VO

LTS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

RAD

UNEXCAVATED

UNEX. UNEX.

UNEX. UNEX.

ELEVATOR

MACHINE AND MAIN

DISCONNECT

P - 3

P - 1

MLP - L

MLP - R

P2

03EP400

03EP400

K L M

G H I J

3-DP-TRAB 1

MDP-31

STAIRWELL NO. 1

B001

GROUP RM.

B002

STORAGE

B003

GROUP

B004

ACTIVITY

B006

STORAGE

B008

MECH. RM.

B013

CLEAN STORAGE

B010

CORRIDOR

B011

STORAGE

B005

MECH. RM.

B009

ELEVATOR MACHINE RM.

B017

CORRIDOR

B015

SERVICE

B014

STORAGE

B024

MECH. RM.

B026

TR

B025A

STORAGE

B027

MECH. RM.

B029

STAIRWELL NO. 3

B028

TOILET

B023

CLOSET

B022

CORRIDOR

B030

LAUNDRY

B021

STAIRWELL NO. 2

B019

VENDING

B020

CORRIDOR

B012

CLOSET

B018

ENTRY

B016

OI&T

B002A

OI&T

B007

ELEVATOR

B031

VACANT

B025

03EP400

03EP400

A B C D E F N O P

BLDG 03

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR

SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT

TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,

AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL

LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER

INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY

POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.

POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND

SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN

SHALL CONFORM WITH VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

9. REFERENCE ONE-LINE DIAGRAM ON SHEET 03EP601 FOR CONDUIT AND WIRE

SIZING.

AREA OF WORK

- 1/8" = 1'-0"

1 BLDG 03 - FLOOR 0 - ELECTRICAL PLAN

0' 4' 8' 16'

KEY PLAN

GENERAL NOTES

KEY NOTES

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

03EP100

BLDG 03 - FLOOR 0 - ELECTRICAL

PLANSPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM - INFRASTRUCTURE

UPGRADES

ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

Revisions: Date:

1 EQUIPMENT TO BE ADDED. REFERENCE ONE-LINE DIAGRAM ON SHEET 03EP601

FOR ADDITIONAL INFORMATION.

EXISTING PANEL TO BE MODIFIED. REFERENCE ONE-LINE DIAGRAM ON SHEET

03EP601 FOR ADDITIONAL INFORMATION.

PROJECT

NORTH

PROJECT

NORTH

4160 VO

LTS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

DN

UP

DN

-3'-8" FLOOR

ELEVATION

DN

UPMP1

D

03EP401

03EP401

K L M

G H I J

03-CU-3-B025

03-CU-3-224A

03EP401

03EP401

3-117A-6,8

03-CU-3-117A

TYP.

3-B025AA-6,8

3-224AA-6,8

STAIRWELL NO. 2

B019

PATIENT RM.

TOILET

103A

HAC

PATIENT RM.

TOILET, MALE

TOILET

PATIENT RM.

TELECOM

STAIRWELL NO. 2

OFFICE

OFFICE

SHOWER

TOILET

PATIENT RM.

PATIENT RM.

STAIRWELL NO. 3

PATIENT RM.

PATIENT RM.

PATIENT RM.

KITCHEN

RECEPTION

PATIENT ADA

PATIENT RM.

PATIENT RM.

PATIENT RM.

PATIENT RM.

CLOSET

PATIENT RM.

TOILET

102A

STAIRWELL NO. 1

S101

CORRIDOR

101A

CORRIDOR

ELEVATOR LOBBY

PATIENT LOUNGE

TELECOM

117A

ELEVATOR LOBBY

VESTIBULE

CORRIDOR

CHASE

CH-1-2

CHASE

CH-1-1

CHASE

CH-1-3

CHASE

CH-1-4

ELEVATOR

E1

A B C D E F N O P

BLDG 03

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR

SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT

TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,

AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL

LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER

INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY

POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.

POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND

SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN

SHALL CONFORM WITH VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

- 1/8" = 1'-0"

1 BLDG 03 - FLOOR 1 - ELECTRICAL PLAN

0' 4' 8' 16'

KEY PLAN

GENERAL NOTES

KEY NOTES

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

03EP101

BLDG 03 - FLOOR 1 - ELECTRICAL

PLANSPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM - INFRASTRUCTURE

UPGRADES

ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

Revisions: Date:

1 PROVIDE CONDUIT AND WIRE FROM CONDENSING UNIT TO ASSOCIATED AC UNIT AS

REQUIRED PER MANUFACTURER'S INSTRUCTIONS. COORDINATE WITH MECHANICAL

CONTRACTOR AS REQUIRED.

PROJECT

NORTH

PROJECT

NORTH

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

DN

DN

DN

LP2

03EP402

K L M

G H I J

DN

DN

DN

03EP402

03EP402

03EP402

PATIENT RM.

PATIENT RM.

PATIENT RM.

TOILET

PATIENT RM.

CLOSET

203A

CLOSET

205A

CLOSET

207A

CLOSET

209A

CLOSET

215A

CLOSET

FIRE SPRINKLER CLOSET

220A

STAIRWELL NO. 2

PATIENT RM.

PATIENT RM.

CLOSET

PATIENT RM.

CLOSET

229A

PATIENT RM.

CLOSET

233B

CLOSET

233A

MECH. RM.

235 STAIRWELL NO. 3

CORRIDOR

CORRIDOR

CORRIDOR

CORRIDOR

PATIENT RM.

PATIENT RM.

PATIENT RM.

PATIENT RM.

QUIET RM.

CLEAN LINEN

KITCHEN

TOILET

OFFICE

PATIENT RM.

PATIENT RM.

CLOSET

232A

CLOSET

230A

CLOSET

228A

HAC

CLOSET

210A

CLOSET

208ACLOSET

206A

CLOSET

204A

CLOSET

202A

ELEVATOR LOBBY

PATIENT RM.

CHASE

CH-2-1

CHASE

CH-2-2

ELEVATOR

E2

TR

224A

LOUNGE

PATIENT RM.

TOILET

STAIRWELL NO. 1

PATIENT RM.

OFFICE

A B C D E F N O P

BLDG 03

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR

SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT

TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,

AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL

LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER

INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY

POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.

POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND

SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN

SHALL CONFORM WITH VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

- 1/8" = 1'-0"

1 BLDG 03 - FLOOR 2 - ELECTRICAL PLAN

0' 4' 8' 16'

KEY PLAN

GENERAL NOTES

KEY NOTES

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

03EP102

BLDG 03 - FLOOR 2 - ELECTRICAL

PLANSPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM - INFRASTRUCTURE

UPGRADES

ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO

657-21-701JB

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

Revisions: Date:

PROJECT

NORTH

PROJECT

NORTH

DN

UP

UP

UP

4160 VO

LTS

DUST CO

LLECTO

R

LIQ UEFIED PETRO LEUM G AS

FLAM M ABLE G AS 2

TRASH COM

PACTO

R

P

SILVERBUILDING 1 23

VA PO

LICE

E

LECTRIC ACCESS

TRANSFO

RM

ER

TRANSFO

RM

ER

TRANSFO

RM

ER

HVAC UNIT

E

LECTRIC PANEL

HVAC UNIT

S&C PAD M

O

UNTED G

EAR

CATALO

G

# 55152-C3DGIG

2P1V M

O

DEL# PM

H-9

EE13299 SG

-52

13278

BUILDING

03TEP401

03TEP401

B C

VESTIBULE

H101

HAC

TOILET, MALE

TOILET, FEMALE

OFFICE

OFFICE

COPIER / FAX

OFFICE

OFFICE

OFFICE

COMPUTER LAB

OFFICE

OFFICE

OFFICE

CONFERENCE

RM.

OFFICE

BREAK RM.

OFFICE

OFFICE

CORRIDOR

H102

CORRIDOR

H105

CORRIDOR

H104

CORRIDOR

H103

TR

A D E F G H I

BLDG 03T

1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR

SHALL FIELD VERIFY ALL POWER ,LIGHTING AND ASSOCIATED CIRCUITRY AS

REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT

TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS

OTHERWISE NOTED.

2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,

AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL

LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER

INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.

3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY

DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE

REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE

ACCEPTANCE OF THE OWNER.

4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM

SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED

EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY

POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.

POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND

SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN

SHALL CONFORM WITH VA STANDARDS.

5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE

RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL

DRAWINGS AS REQUIRED.

6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL

INFORMATION.

7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL

PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.

8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING

TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.

COORDINATE WITH VA AS REQUIRED.

AREA OF WORK

- 1/4" = 1'-0"

1 BLDG 03T - FLOOR 1 - ELECTRICAL PLAN

KEY PLAN

KEY NOTES

GENERAL NOTES

0' 2' 4' 8'

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

03TEP101

BLDG 03T - FLOOR 1 - ELECTRICAL

PLANSPEES DESIGN BUILD

625 1ST AVE, STE 301

SEATTLE, WA 98104

(206) 590-2118

RAY SPEES

EHRM - INFRASTRUCTURE

UPGRADES

JEFFERSON BARRACKS - 1 JEFFERSON BARRACKS

DRIVE - ST. LOUIS, MO 63125

657-21-701JB

03T

03/31/2022 LRL/WNM JPS/LLT

CONSTRUCTION

DOCUMENTS

Revisions: Date:

PROJECT

NORTH

PROJECT

NORTH

File details come from the government source that posted it. Updated .