Attachment 13 - Drawings Part-12.pdf
PDF 14 MB Posted
- Attached to
- Y1DA--EHRM Infrastructure Upgrades Construction Jefferson Barracks Federal contract opportunity
- Solicitation number
- 36C77623R0009
About this file
This document provides details for a federal contract solicitation seeking infrastructure upgrades at the St. Louis Jefferson Barracks VA Medical Center. The solicitation seeks a general contractor to provide electrical panel upgrades and power systems work, building management system integration, HVAC assessments and upgrades, facility renovations including demolition and new construction, data center renovations, physical security improvements, fiber optic infrastructure assessment and upgrades, installation of a diversified wide area network path to the datacenter, and hazardous materials abatement. The work locations include Buildings 1 through 3, 3T, 18, 23 through 25, 51 through 53, 53T, 55 through 61, 75, and other site work. The solicitation was issued by the Department of Veterans Affairs Technology Acquisition Center located in Austin, Texas.
View the file
Other files for this federal contract opportunity
Show all 50
Y1DA--EHRM Infrastructure Upgrades Construction Jefferson Barracks has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S S
S
Mo
TR
138.12 SF
TR
117A
7.59 SF
FIBER OPTIC
PATCH PANEL
TELECOMMUNICATION
ENCLOSURE
ACCESS POWER
CONTROLLER PANEL
ACCESS DOOR
CONTROLLER
EXISTING POWER
SUPPLIES AND
DATA CABINET
FIBER OPTIC
TERMINAL BOX
TELEPHONE
TERMINAL BOARD
EXISTING FIRE
ALARM PANELS
FIBER OPTIC SYSTEM
4 TYP
3-117A-2
3-117A-2
3-117B-2
3-117B-1,3,5 3-117A-1,3,5
TR
138.12 SF
03-AC-3-117
TR
138.12 SF
3-117A-2
DATA
RACK,
TYP.
EP502
3-117B-7,9,11 3-117A-7,9,11
3-117A-2
3-117B-2
EXISTING FIRE
ALARM PANELS
FIBER OPTIC SYSTEM
ACCESS POWER
CONTROLLER
PANEL
ACCESS DOOR
CONTROLLER
3-DP-TRAB
3-DP-TRAB
FIBER OPTIC PATCH
PANEL (BELOW)
TR
138.12 SF
TR
117A
7.59 SF
TYP
TR
117A
7.59 SF
TR
138.12 SF
3-117A-4
L2 L2
L2 L2
L2
DATA
RACK,
TYP. 3-117A
3-117B
SOURCE A POWER PANELBOARD "3-117A".
SOURCE B POWER PANELBOARD "3-117B".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE
SHALL BE DEMOLISHED BACK TO SOURCE.
EXISTING SPECIAL SYSTEM EQUIPMENT. COORDINATE RELOCATION/DEMOLITION
WITH TELECOMMUNICATIONS CONTRACTOR AS REQUIRED.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL CONTRACTOR
AS REQUIRED.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL
FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED.
ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE
DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS
OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND
RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS
WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF
MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL
REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL
CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
10. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
03EP401
BLDG 03 - FLOOR 1 - ENLARGED
ELECTRICAL PLANSSPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
EHRM - INFRASTRUCTURE
UPGRADES
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
657-21-701JB
03/31/2022 LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
KEY PLAN
GENERAL NOTES
3/8" = 1'-0"03EP101
1 RM 117 - DEMOLITION ELECTRICAL PLAN
3/8" = 1'-0"03EP101
2 RM 117 - ELECTRICAL PLAN
3/8" = 1'-0"03EP101
3 RM 117 - DEMOLITION LIGHTING PLAN
3/8" = 1'-0"03EP101
4 RM 117 - LIGHTING PLAN
KEY NOTES
0' 1' 2' 4'
0' 1' 2' 4'
0' 1' 2' 4'
0' 1' 2' 4'
Revisions: Date:
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
LRL/WNM LLT/JPS
J
S S
Mo
224A
K
LOUNGE
140.33 SF
I J
TYP.
K
LOUNGE
140.33 SF
TR
224A
123.32 SF
I J
DATA
RACK,
TYP.
3-224AA-2
3-224AA-2
3-224AA-2
3-224AB-2
3-224AB-2
3-224AB-2
3-224AB-2
3-224AA-2
3-224AA-1,3,5
3-224AB-1,3,5
03-AC-3-224A
EP502
3-DP-TRAB
3-DP-TRAB
K
LOUNGE
140.33 SF
I J
K
LOUNGE
140.33 SF
I J
TR
224A
123.32 SF
DATA
RACK,
TYP
3-224AA-4
L2 L2
L2 L2
3-224AA
3-224AB
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL
FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS REQUIRED.
ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO BE
DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS
OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND
RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS
WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF
MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL
REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL
CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
10. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
SOURCE A POWER PANELBOARD "3-224AA".
SOURCE B POWER PANELBOARD "3-224AB".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE
SHALL BE DEMOLISHED BACK TO SOURCE.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL CONTRACTOR
AS REQUIRED.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
FURNISH AND INSTALL BOXED POWER SUPPLIES AS INDICATED ABOVE
ACCESSIBLE CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER
SUPPLY FOR EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY
SERVE DOORS WITH ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS
REQUIRED. SEE REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH
ARCHITECT AND DOOR INSTALLER.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
03EP402
BLDG 03 - FLOOR 2 - ENLARGED
ELECTRICAL PLANSSPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
EHRM - INFRASTRUCTURE
UPGRADES
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
657-21-701JB
03/31/2022 LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
KEY PLAN
GENERAL NOTES
3/8" = 1'-0"03EP102
1 RM 224 - DEMOLITION ELECTRICAL PLAN
3/8" = 1'-0"03EP102
2 RM 224A - ELECTRICAL PLAN
3/8" = 1'-0"03EP102
3 RM 224 - DEMOLITION LIGHTING PLAN
3/8" = 1'-0"03EP102
4 RM 224A - LIGHTING PLAN
KEY NOTES
0' 1' 2' 4'
Revisions: Date:
0' 1' 2' 4'
0' 1' 2' 4' 0' 1' 2' 4'
PROJECT
NORTH
PROJECT
NORTHPROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
B C
EXISTING
PANEL 3T-1
ACCESS POWER
CONTROLLER
PANEL
34 SF
TR
TELEPHONE
TERMINAL
BOARD
DATA RACK
BLDG
ENTRANCE
TERMINAL
PAD
B C
1/2
34 SF
TR
EXISTING
PANEL 3T-1
ACCESS POWER
CONTROLLER
PANEL
TELEPHONE TERMINAL BOARD
PAD
DATA RACK
BLDG
ENTRANCE
TERMINAL
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS
REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT
TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS
OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
10. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
03TEP401
BLDG 03T - FLOOR 1 - ENLARGED
ELECTRICAL PLANSSPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
EHRM - INFRASTRUCTURE
UPGRADES
JEFFERSON BARRACKS - 1 JEFFERSON BARRACKS
DRIVE - ST. LOUIS, MO 63125
657-21-701JB
03T
03/31/2022 LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
KEY PLAN
KEY NOTES
GENERAL NOTES
1/2" = 1'-0"03TEP101
1 RM 118 - DEMOLITION ELECTRICAL PLAN
1/2" = 1'-0"03TEP101
2 RM 118 - ELECTRICAL PLAN
IN-LINE TRANSFER FAN WITH SPEED CONTROLLER. COORDINATE SPEED
CONTROLLER INSTALLATION LOCATION WITH MECHANICAL CONTRACTOR.
UPS RECEPTACLE.
CONTRACTOR SHALL REPLACE EXISTING RACK-MOUNTED UPS WITH NEW UPS. UPS
SHALL BE 3kW, 120V, 1-PHASE, APC #SMX3000RMLV2U, OR EQUAL.
0' 1' 2' 4' 0' 1' 2' 4'
Revisions: Date:
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
Mo
S S
D
E
C
B
2423 25
TYP
OFFICE
157 SF
D
E
C
B
2423 25
TR
011A
123 SF
6 18-011A-2 18-011A-2
318-011A-218-011A-2
18-011B-2 18-011B-2
18-011B-2
DATA RACK,
TYP.
18-011A-1,3,5 18-011B-1,3,5
18-AC-3-011A
EP502
18-DP-TRAB
18-DP-TRAB
18-011B-2
011 011A
D
E
C
B
2423 25
OFFICE
157 SF
TR
011A
123 SF
TYP
D
E
C
B
2423 25
TR
011A
123 SF
OFFICE
157 SF
OFFICE
18-011A-4
DATA
RACK,
TYP.
L2 L2
L2 L2
18-011A18-011B
SOURCE A POWER PANELBOARD "18-011A".
SOURCE B POWER PANELBOARD "18-011B".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE SHALL
BE DEMOLISHED BACK TO SOURCE.
CIRCUIT RECEPTACLES TO SAME PANEL AND CIRCUIT AS THE EXISTING
RECEPTACLES THAT WERE DEMOLISHED FROM ROOM. REFERENCE DETAIL 1 ON
THIS SHEET FOR ADDITIONAL INFORMATION.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL CONTRACTOR
AS REQUIRED.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
FURNISH AND INSTALL BOXED POWER SUPPLIES AS INDICATED ABOVE ACCESSIBLE
CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER SUPPLY FOR
EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY SERVE DOORS
WITH ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS REQUIRED. SEE
REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH ARCHITECT AND
DOOR INSTALLER.
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSOCIATED
CIRCUITRY AS REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH
EQUIPMENT TO BE DEMOLISHED SHALL BE DEMOLISED BACK TO THEIR SOURCE,
UNLESS OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR
ALL PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
657-21-701JB
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES 18EP400
BLDG 18 - FLOOR 0 - ENLARGED
ELECTRICAL PLANS 18
LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
03/31/2022
1/4" = 1'-0"18EP100
1 RM 011 - DEMOLITION ELECTRICAL PLAN
1/4" = 1'-0"18EP100
2 RM 011A - ELECTRICAL PLAN
KEY PLAN
GENERAL NOTES
1/4" = 1'-0"18EP100
3 RM 011 - DEMOLITION LIGHTING PLAN
1/4" = 1'-0"18EP100
4 RM 011A - LIGHTING PLAN
KEY NOTES
0' 2' 4' 8'
0' 2' 4' 8' 0' 2' 4' 8'
0' 2' 4' 8'
NON SPRINKLERED
Revisions: Date:
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
S
S
M o
S
S S
D
E
C
B
10 11 1312
TYPOI&T
84 SF
EXISTING TELEPHONE
TERMINAL BOARD
EXISTING PANEL 18-4
EXISTING
JUNCTION BOX
EXISTING
PANEL 18-2
EXISTING
PANEL DP18-1
D
E
C
B
10 11 1312
TR
141 SF
DATA RACK, TYP.
18-119A-2
18-119A-2
18-119A-2
18-119B-2
18-119B-2
18-119B-1,3,5
18-119A-1,3,5
18-AC-3-119
18-DP-TRAB
18-ECB-TR1
RELOCATED PANEL 18-2
RELOCATED JUNCTION BOX
RELOCATED PANEL 18-4
EP502
RELOCATED PANEL
DP18-110
D
E
C
B
10 11 1312
TR
141 SF
TYP D
E
C
B
10 11 1312
TR
141 SF18-119A-4
DATA RACK, TYP.
L1 L1
L1
L1 L1
10-119A
RELOCATED PANEL 18-2
RELOCATED PANEL DP18-1
RELOCATE JUNCTION BOX
10-119B
18-DP-TRAB 10
RELOCATED PANEL 18-4
18-ECB-TR1
SOURCE A POWER PANELBOARD "18-119A".
SOURCE B POWER PANELBOARD "18-119B".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE SHALL
BE DEMOLISHED BACK TO SOURCE.
EXISTING EQUIPMENT SHALL BE RELOCATED AS SHOWN. EXTEND ALL RACEWAYS
AND CONDUCTORS AS REQUIRED.
EXISTING SPECIAL SYSTEM EQUIPMENT. COORDINATE RELOCATION/DEMOLITION
WITH TELECOMMUNICATIONS CONTRACTOR AS REQUIRED.
EXISTING PANEL TO BE MODIFIED. REFERENCE ONE-LINE DIAGRAM ON SHEET
18EP601 AND LOAD SCHEDULES ON SHEET 18EP701.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL
CONTRACTOR AS REQUIRED.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
EQUIPMENT TO BE ADDED. REFERENCE ONE-LINE DIAGRAM ON SHEET 18EP601 FOR
ADDITIONAL INFORMATION.
FURNISH AND INSTALL BOXED POWER SUPPLIES AS INDICATED ABOVE ACCESSIBLE
CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER SUPPLY FOR
EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY SERVE DOORS
WITH ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS REQUIRED. SEE
REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH ARCHITECT AND
DOOR INSTALLER.
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSOCIATED
CIRCUITRY AS REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH
EQUIPMENT TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE,
UNLESS OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR
ALL PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
12. REFERENCE ONE-LINE DIAGRAM ON SHEET 18EP601 FOR CONDUIT AND WIRE
SIZING.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
657-21-701JB
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES 18EP401
BLDG 18 - FLOOR 1 - ENLARGED
ELECTRICAL PLANS 18
LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
03/31/2022
KEY PLAN
GENERAL NOTES
1/4" = 1'-0"18EP101
1 RM 119 - DEMOLITION ELECTRICAL PLAN
1/4" = 1'-0"18EP101
2 RM 119 - ELECTRICAL PLAN
1/4" = 1'-0"18EP101
3 RM 119 - DEMOLITION LIGHTING PLAN
1/4" = 1'-0"18EP101
4 RM 119 - LIGHTING PLAN
KEY NOTES
0' 2' 4' 8' 0' 2' 4' 8'
0' 2' 4' 8' 0' 2' 4' 8'
NON SPRINKLERED
Revisions: Date:
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
S
S
M o S
212A
8' - 1"
F
G
D
E
C
10 11 1312
LP2A
LP2B
TR
115 SF
115 SF
KITCHENETTE
212A
TYP
F
G
D
E
C
10 11 1312
LP2A
LP2B
TR
115 SF
DATA RACK,TYP.
18-213A-2
18-213A-2
18-213B-2
18-213B-2
18-213B-2
18-213A-1,3,5 18-213B-1,3,5
18-AC-3-213
EP502
18-213A-1,3,5 18-213B-1,3,5
TYP
18-DP-TRAB 18-DP-TRAB
F
G
D
E
C
10 11 1312
TR
115 SF
CHASE
CH-2-1
49 SF
115 SF
KITCHENETTE
212A
F
G
D
E
C
10 11 1312
TR
115 SF
CHASE
CH-2-1
49 SF
ELEC. CLOSET
32 SF
18-213A-4
L2
L2
L2
DATA RACK,TYP.
L2
18-213A
LP2A
LP2B
18-213B
SOURCE A POWER PANELBOARD "18-213A".
SOURCE B POWER PANELBOARD "18-213B".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE SHALL
BE DEMOLISHED BACK TO SOURCE.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL CONTRACTOR
AS REQUIRED.
FURNISH AND INSTALL BOXED POWER SUPPLIES AS INDICATED ABOVE ACCESSIBLE
CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER SUPPLY FOR
EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY SERVE DOORS
WITH ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS REQUIRED. SEE
REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH ARCHITECT AND
DOOR INSTALLER.
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSOCIATED
CIRCUITRY AS REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH
EQUIPMENT TO BE DEMOLISHED SHALL BE DEMOLISED BACK TO THEIR SOURCE,
UNLESS OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR
ALL PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
657-21-701JB
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES 18EP402
BLDG 18 - FLOOR 2 - ENLARGED
ELECTRICAL PLANS 18
LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
03/31/2022
KEY PLAN
GENERAL NOTES
1/4" = 1'-0"18EP102
1 RM 212A & 213 - DEMOLITION ELECTRICAL PLAN
1/4" = 1'-0"18EP102
2 RM 213 - ELECTRICAL PLAN
1/4" = 1'-0"18EP102
3 RM 212A & 213 - DEMOLITION LIGHTING PLAN
0' 1' 2' 4' 0' 1' 2' 4'
0' 1' 2' 4' 1/4" = 1'-0"18EP102
4 RM 213 - LIGHTING PLAN
0' 1' 2' 4'
KEY NOTES
NON SPRINKLERED
Revisions: Date:
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
SS
M o
S
D
E
C
10 11 1312
EXISTING LP3A
EXISTING LP3B
ELEC. CLOSET
32 SF
62 SF
TELECOM
TYP
D
E
C
10 11 1312
EXISTING LP3B
TR
63 SF ELEC. CLOSET
32 SF
EXISTING LP3ADATA
RACK
18-312A-2
18-312A-2 18-312A-2 6
18-312A-1,3,5
18-312B-1,3,5
18-AC-2-312
EP502
18-DP-TRAB
18-DP-TRAB
D
E
C
10 11 1312
TR
63 SF
ELEC. CLOSET
32 SF
TYP
D
E
C
10 11 1312
TR
63 SF
ELEC. CLOSET
32 SF
18-312A-4
L2 L2
DATA
RACK
L2
EXISTING LP3B
EXISTING LP3A
18-312B
18-312A
SOURCE A POWER PANELBOARD "18-312A".
SOURCE B POWER PANELBOARD "18-312B".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE SHALL
BE DEMOLISHED BACK TO SOURCE.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL CONTRACTOR
AS REQUIRED.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
FURNISH AND INSTALL BOXED POWER SUPPLIES AS INDICATED ABOVE ACCESSIBLE
CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER SUPPLY FOR
EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY SERVE DOORS
WITH ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS REQUIRED. SEE
REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH ARCHITECT AND
DOOR INSTALLER.
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSOCIATED
CIRCUITRY AS REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH
EQUIPMENT TO BE DEMOLISHED SHALL BE DEMOLISED BACK TO THEIR SOURCE,
UNLESS OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR
ALL PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
657-21-701JB
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES 18EP403
BLDG 18 - FLOOR 3 - ENLARGED
ELECTRICAL PLANS 18
LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
03/31/2022
KEY PLAN
GENERAL NOTES
1/4" = 1'-0"18EP103
1 RM 312 - DEMOLITION ELECTRICAL PLAN
1/4" = 1'-0"18EP103
2 RM 312 - ELECTRICAL PLAN
1/4" = 1'-0"18EP103
3 RM 312 - DEMOLITION LIGHTING PLAN
1/4" = 1'-0"18EP103
4 RM 312 - LIGHTING PLAN
KEY NOTES
0' 2' 4' 8'
0' 2' 4' 8'0' 2' 4' 8'
0' 2' 4' 8'
NON SPRINKLERED
Revisions: Date:
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
DN
S S
S S
Mo
G09B G09
B.8
LOCK SHOP
G09
107 SF
TYP
TR
G09B
105 SF
B.8
LOCK SHOP
G09
107 SF
DATA
RACK,
TYP.
23-G09A-2
23-G09A-223-G09A-2
23-G09A-2
23-G09B-2
23-G09B-2
23-G09B-2
23-G09B-2
23-G09BA-1,3,5
23-G09BB-1,3,5
23-AC-3-G09B EP502
MSB-23
MSB-23
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL
FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSOCIATED CIRCUITRY AS
REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO
BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS
OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND
RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS
WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF
MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF DEVICES
SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN
ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH
VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
SOURCE A POWER PANELBOARD "23-G09BA".
SOURCE B POWER PANELBOARD "23-G09BB".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE SHALL
BE DEMOLISHED BACK TO SOURCE.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL
CONTRACTOR AS REQUIRED.
FURNISH AND INSTALL BOXED POWER SUPPLIES AS INDICATED ABOVE ACCESSIBLE
CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER SUPPLY FOR
EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY SERVE DOORS WITH
ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS REQUIRED. SEE
REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH ARCHITECT AND
DOOR INSTALLER.
PROVIDE REQUIRED ELECTRICAL CONNECTIONS FOR RELOCATED MECHANICAL
EQUIPMENT.
B.8
DATA
RACK,
TYP.
TR
G09B
105 SF
23-G09BA-4
L2 L2
L2 L2
23-G09BA
23-G09BB
B.8
LOCK SHOP
G09
107 SF
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
657-21-701JB
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES 23EP400
BLDG 23 - FLOOR 0 - ENLARGED
ELECTRICAL PLANS 23
LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
03/31/2022
PROJECT
NORTH
0' 2' 4' 8'
3/8" = 1'-0"23EP100
1 RM G09 - DEMOLITION ELECTRICAL PLAN
3/8" = 1'-0"23EP100
2 RM G09B - ELECTRICAL PLAN
KEY PLAN
KEY NOTES
GENERAL NOTES
3/8" = 1'-0"23EP100
4 RM G09B - LIGHTING PLAN
3/8" = 1'-0"23EP100
3 RM G09 - DEMOLITION LIGHTING PLAN
PROJECT
NORTH
0' 2' 4' 8'
PROJECT
NORTH
0' 2' 4' 8'
PROJECT
NORTH
0' 2' 4' 8'
Revisions: Date:
NON SPRINKLERED
PROJECT
NORTH
Mo
DN
J
B.8
TYP
PROSTHETICS
RESTORATION
107 SF
TR
121A
102 SF
B.8
DATA
RACK,
TYP.
23-121AA-4
L2
L2
L2
L2
23-121AA
23-121AB
121 121A
B.8
PROSTHETICS
RESTORATION
107 SF
TYP
B.8
23-121AA-2 23-121AA-2
23-121AB-2
DATA
RACK,
TYP.
23-121AB-2
23-121AB-2
23-121AA-2
23-121AA-1,3,5
23-121AB-1,3,5
23-AC-3-121-A
23-121AB-223-121AB-2
TR
121A
102 SF
EP502
MSB-23
MSB-23
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR SHALL
FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSOCIATED CIRCUITRY AS
REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT TO
BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS
OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS, AND
RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL LOCATIONS
WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER INSTALLATION OF
MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF DEVICES
SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY POWER
AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT. POWER TO
ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND SHALL REMAIN
ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN SHALL CONFORM WITH
VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
SOURCE A POWER PANELBOARD "23-121AA".
SOURCE B POWER PANELBOARD "23-121AB".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE SHALL
BE DEMOLISHED BACK TO SOURCE.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL
CONTRACTOR AS REQUIRED.
FURNISH AND INSTALL BOXED POWER SUPPLIES AS INDICATED ABOVE ACCESSIBLE
CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER SUPPLY FOR
EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY SERVE DOORS WITH
ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS REQUIRED. SEE
REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH ARCHITECT AND
DOOR INSTALLER.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
23EP401
BLDG 23 - FLOOR 1 - ENLARGED
ELECTRICAL PLANSSPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
EHRM INFRASTRUCTURE
UPGRADES
657-21-701JB
03/31/2022 LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
3/8" = 1'-0"23EP101
3 RM 121 - DEMOLITION LIGHTING PLAN
3/8" = 1'-0"23EP101
4 RM 121A - LIGHTING PLAN
PROJECT
NORTH
0' 2' 4' 8'
3/8" = 1'-0"23EP101
1 RM 121 - DEMOLITION ELECTRICAL PLAN
3/8" = 1'-0"23EP101
2 RM 121A - ELECTRICAL PLAN
KEY PLAN
KEY NOTES
GENERAL NOTES
Revisions: Date:
PROJECT
NORTH
0' 2' 4' 8'
PROJECT
NORTH
0' 2' 4' 8'
PROJECT
NORTH
0' 2' 4' 8'
PROJECT
NORTH
1. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER, LIGHTING AND ASSOCIATED CIRCUITRY AS
REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH EQUIPMENT
TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE, UNLESS
OTHERWISE NOTED.
2. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
3. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
4. CONTRACTOR SHALL COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
5. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
6. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
7. CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR ALL
PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
8. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
B.8
B.2
23-CU-3-121A 23-CU-3-G09
23-G09A-6,823-121AA-6,8
EP503
TYP.
TYP.
23-CU-3-121A
23-CU-3-G09B
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
EHRM INFRASTRUCTURE
UPGRADES
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
657-21-701JB
SPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES 23EP402
BLDG 23 - ENLARGED ROOF PLAN
LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
03/31/2022
Revisions: Date:
KEY PLAN
KEY NOTES
GENERAL NOTES
- 1/2" = 1'-0"
1 BLDG 23 - ENLARGED ROOF PLAN
0' 2' 4' 8'
PROJECT
NORTH
PROVIDE CONDUIT AND WIRE FROM CONDENSING UNIT TO ASSOCIATED AC UNIT AS
REQUIRED PER MANUFACTURER'S INSTRUCTIONS. COORDINATE WITH MECHANICAL
CONTRACTOR AS REQUIRED.
PROJECT
NORTH
S
S
DN
J
Q R S
B B B
TYP
BB
TR
114B
156 SF
EXPOSED
Q R S
24-G02AA-4
DATA
RACK,
TYP.
TR
G02A
156 SF
L3 L3
L3 L3
24-G02AA 24-G02AB
G02A
Q R S
TYP
TR
G02A
156 SF
Q R S
3 1
24-G02AA-2
24-G02AA-2
24-G02AA-2
24-G02AB-2
24-G02AB-2
DATA
RACKS,
TYP.
24-G02AB-7,9,11
24-G02AA-7,9,11
24-G02AA-2
24-G02AB-2
24-G02AB-2
24-AC-3-G02A
EP502
24-G02AB-1,3,5
24-G02AA-1,3,5
TYP
TR
G02A
156 SF
24-DP-TRAB 24-DP-TRAB
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSSOCIATED
CIRCUITRY AS REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH
EQUIPMENT TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE,
UNLESS OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR
ALL PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
SOURCE A POWER PANELBOARD "24-G02AA".
SOURCE B POWER PANELBOARD "24-G02AB".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE
SHALL BE DEMOLISHED BACK TO SOURCE.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL
CONTRACTOR AS REQUIRED.
FURNISH AND INSTALL BOXED POWER SUPPLIES AS INDICATED ABOVE
ACCESSIBLE CEILINGS. VERIFY LOCATIONS WITH ARCHITECT. PROVIDE (1) POWER
SUPPLY FOR EACH DOOR OPENING. PROVIDE 120V POWER TO ADEQUATELY
SERVE DOORS WITH ELECTRIFIED DOOR HARDWARE AND MAKE CONNECTIONS AS
REQUIRED. SEE REQUIREMENTS IN 087100 - DOOR HARDWARE. COORDINATE WITH
ARCHITECT AND DOOR INSTALLER.
AREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ST. LOUIS VA MEDICAL CENTER - JEFFERSON BARRACKS, MO
24EP400a
BLDG 24 - FLOOR 0 - ENLARGED
ELECTRICAL PLANSSPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
EHRM INFRASTRUCTURE
UPGRADES
657-21-701JB
03/31/2022 LRL/WNM JPS/LLT
CONSTRUCTION
DOCUMENTS
3/8" = 1'-0"24EP100
3 RM G02A - DEMOLITION LIGHTING PLAN
3/8" = 1'-0"24EP100
4 RM G02A - LIGHTING PLAN0' 2' 4' 8' 0' 2' 4' 8'
0' 2' 4' 8'
3/8" = 1'-0"24EP100
1 RM G02A - DEMOLITION ELECTRICAL PLAN
3/8" = 1'-0"24EP100
2 RM G02A - ELECTRICAL PLAN
KEY PLAN
KEY NOTES
GENERAL NOTES
PROJECT
NORTH
Revisions: Date:
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH
PROJECT
NORTH0' 2' 4' 8'
FUTURE DATA
RACK
DN
A B C
A/C AHU
24ML
PANEL B
24MR3
A
A
B
B
C
C
MSB-241
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSSOCIATED
CIRCUITRY AS REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH
EQUIPMENT TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE,
UNLESS OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR
ALL PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
EQUIPMENT TO BE ADDED. REFERENCE ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
PROVIDE CONCRETE PAD. EXTEND AROUND EQUIPMENT FOOTPRINT BY 6".
CONCRETE SHALL BE 6" THICK, 3000psi MINIMUM. COORDINATE WITH CIVIL
SPECIFICATIONS AS REQUIRED.
EXISTING EQUIPMENT TO BE DEMOLISHED; EXTEND EXISTING CONDUCTORS AND
RACEWAYS TO NEW SWITCHBOARD AS REQUIRED. REFERENCE ONE-LINE
DIAGRAM FOR ADDITIONAL INFORMATION.
G02A
PROJECT
NORTHAREA OF WORK
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
24EP400b
BLDG 24 - FLOOR 0 - ENLARGED
ELECTRICAL PLANSSPEES DESIGN BUILD
625 1ST AVE, STE 301
SEATTLE, WA 98104
(206) 590-2118
RAY SPEES
EHRM INFRASTRUCTURE
UPGRADES
JEFFERSON BARRACKS - 1 JEFFERSON BARRACKS
DRIVE - ST. LOUIS, MO 63125
657-21-701JB
03/31/2022 Checker Author
CONSTRUCTION
DOCUMENTS
KEY PLAN
KEY NOTES
GENERAL NOTES
1/2" = 1'-0"24EP100
1 EXTERIOR WIREWAY - DEMOLITION PLAN
1/2" = 1'-0"24EP100
2 EXTERIOR WIREWAY - ELECTRICAL PLAN
Revisions: Date:
Mo
S
S
S
DN
J
Q R S T
A A ATR
114B
156 SF
MEDICAL
LIBRARY
TYP
OI&T
114C
27 SF
Q R S T
TR
114B
156 SF
MEDICAL
LIBRARY
DATA
RACK,
TYP.
24-114BA-4
L3 L3
L3 L3
OI&T
114C
27 SF
24-114BA 24-114BB
114C
114B
Q R S T
OI&T
114C
27 SF
TR
114B
156 SF
TYP
Q R S T
DATA
RACKS,
TYP.
24-114BB-2
24-114BA-2
TR
114B
156 SF
24-114BB-2
24-114BB-2 24-114BA-2
24-114BB-7,9,11
24-114BA-7,9,11
24-AC-3-114B
24-114BB-2
24-114BA-2
24-114BA-2
EP502
24-114BB-1,3,5
24-114BA-1,3,5
OI&T
114C
27 SF
TYP
24-DP-TRAB
24-DP-TRAB
1. DEMOLITION PLANS/NOTES ARE BASED ON SITE INVESTIGATIONS AND RECORD
DRAWINGS. IF DISCREPANCIES ARE FOUND THAT MAY IMPACT WORK, PROMPTLY
NOTIFY VA AND ENGINEER OF SAID DISCREPANCY.
2. ALL EXISTING EQUIPMENT MAY NOT BE SHOWN FOR CLARITY. CONTRACTOR
SHALL FIELD VERIFY ALL POWER AND SIGNAL DEVICES AND ASSSOCIATED
CIRCUITRY AS REQUIRED. ALL RACEWAYS AND CONDUCTORS ASSOCIATED WITH
EQUIPMENT TO BE DEMOLISHED SHALL BE DEMOLISHED BACK TO THEIR SOURCE,
UNLESS OTHERWISE NOTED.
3. CONTRACTOR SHALL DEMOLISH ALL ELECTRICAL EQUIPMENT, CONDUCTORS,
AND RACEWAYS ASSOCIATED WITH WALLS BEING REMOVED AND IN ALL
LOCATIONS WHERE JUNCTION BOXES WILL NOT REMAIN ACCESSIBLE AFTER
INSTALLATION OF MILLWORK, UNLESS OTHERWISE NOTED.
4. CONTRACTOR SHALL DISPOSE OF THE REMOVED DEVICES. DISPOSAL OF
DEVICES SHALL COMPLY WITH ALL APPROPRIATE CODES.
5. PROTECT ALL EXISTING WORK FROM DAMAGE DURING CONSTRUCTION. ANY
DAMAGED MATERIALS, SYSTEMS, COMPONENTS, FINISHES BE LIKE, SHALL BE
REPAIRED OR REPLACED AT THE EXPENSE OF THE CONTRACTOR TO THE
ACCEPTANCE OF THE OWNER.
6. FIELD VERIFY ALL RACEWAY DEMOLITION AND INSTALLATIONS PRIOR TO
PERFORMING WORK.
7. CONTRACTOR TO COORDINATE NORMAL/ESSENTIAL ELECTRICAL SYSTEM
SHUTDOWNS AND PHASING WITH THE VA PRIOR TO PERFORMING REQUIRED
EQUIPMENT UPGRADES. CONTRACTOR TO PROVIDE BACKUP EMERGENCY
POWER AND DETERMINE TIE-IN/CONNECTION PLAN WITH EXISTING EQUIPMENT.
POWER TO ALL EXISTING ESSENTIAL EQUIPMENT CANNOT BE INTERRUPTED AND
SHALL REMAIN ACTIVE DURING CONSTRUCTION. BACKUP POWER AND TIE-IN
SHALL CONFORM WITH VA STANDARDS.
8. SEAL ALL INTERIOR WALL AND CEILING PENETRATIONS TO MATCH EXISTING FIRE
RATING OR NEW FIRE RATING, IF REQUIRED. COORDINATE WITH ARCHITECTURAL
DRAWINGS AS REQUIRED.
9. REFERENCE CORRESPONDING ONE-LINE DIAGRAM FOR ADDITIONAL
INFORMATION.
10. THE CONTRACTOR SHALL PROVIDE UPDATED CIRCUIT PANEL DIRECTORIES FOR
ALL PANELS THAT CONTAIN CIRCUITS IMPACTED BY THIS PROJECT.
11. CONTRACTOR SHALL BE RESPONSIBLE FOR RELOCATING FURNITURE, INCLUDING
TRANSPORTATION, FOR ALL WORK TO DESIRED VA STORAGE LOCATION.
COORDINATE WITH VA AS REQUIRED.
SOURCE A POWER PANELBOARD "24-114BA".
SOURCE B POWER PANELBOARD "24-114BB".
SECONDARY BONDING BUS BAR.
EXISTING EQUIPMENT TO BE DEMOLISHED. ASSOCIATED CONDUIT AND WIRE
SHALL BE DEMOLISHED BACK TO SOURCE.
OVERHEAD TR RACK SOURCE A AND SOURCE B POWER RECEPTACLE.
AC UNIT IS CIRCUITED TO CORRESPONDING CONDENSING UNIT VIA
MANUFACTURER'S CONNECTIONS. COORDINATE WITH MECHANICAL
CONTRACTOR AS REQUIRED.
FURNISH AND INSTALL BOXED POWER SUPPLIES…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .