56-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf

PDF 132 KB Posted

Attached to
Morrisville Borough 2026 Design/Build Curb Ramp Project
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a technical specification document for bituminous concrete paving work prepared for the Municipal Authority of the Borough of Morrisville in Bucks County, Pennsylvania, in conjunction with a 2026 Design/Build Curb Ramp Project. The specification details the complete paving requirements including asphalt base course, binder course, wearing course, and tack coat materials, all conforming to Pennsylvania Department of Transportation (PennDOT) Superpave standards as outlined in Publication 408. The work encompasses asphalt paving of roadways with subbase course preparation using PennDOT No. 2A coarse aggregate, surface preparation including proof-rolling with a 10-ton roller, tack coat application, and multiple asphalt layers placed to specified compacted thicknesses. Environmental requirements specify that asphalt placement cannot occur when base surface temperature is below 40 degrees Fahrenheit or when the base surface is wet or frozen. All work must conform to the latest edition of PennDOT Publication 408 and applicable Borough standards for paving work on public property.

The specification establishes strict quality assurance standards requiring material certifications from bituminous and aggregate suppliers and compliance with PennDOT specifications. Tolerances are tightly controlled, with maximum flatness variation of 1/4 inch measured with a 10-foot straight edge, compacted thickness within 1/4 inch of design specifications, and elevation variation not exceeding 1/2 inch. The contractor is responsible for restoring any existing paving outside the work limits that is damaged by contractor operations. Joint preparation requires minimum one-foot cutbacks with straight joint lines and right-angle offsets, and completed joints must be sealed with hot bituminous material. Hand compaction is required in areas inaccessible to rolling equipment, and painted markings must be provided as shown on project drawings.

View the file

Other files

File Type Posted
53-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
9-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
45-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
39-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
18-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
29-Doc 00 73 00 6 - RESPONSIBLE - CONTRACTOR ORDINANCE.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 73 00 07 - APPENDIX D - COVER.pdf PDF
13-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
54-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
32-Doc 00 73 00 08 Part 1 Contract Language Requirements.pdf PDF
42-Sec 01 33 00 - SUBMITTALS.pdf PDF
49-Sec 02 41 16 - DEMOLITION.pdf PDF
6-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
58-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
22-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
55-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
46-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
2-Doc 00 01 10-TOC.pdf PDF
24-Doc 00 73 00 1 - APPENDIX A - COVER.pdf PDF
19-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
43-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
31-Doc 00 73 00 07 APPENDIX D - CDBG AND STATE REQUIREMENTS.pdf PDF
36-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
1-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
34-Doc 00 73 00 10 - Part 3 Section 3 Requirements.pdf PDF
40-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
20-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
50-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
59-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
37-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
25-Doc 00 73 00 1 - APPENDIX A - DAVIS BACON FEDERAL WAGE DETERMINATION.pdf PDF
62-CDBG Curb Ramp Concept Plans.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
15-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
47-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
16-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
4-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
57-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
52-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
61-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
41-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
23-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
7-Doc 00 41 00 - BID FORM - EBID.pdf PDF
17-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
10-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
21-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BITUMINOUS CONCRETE PAVING

32 12 00-1

SECTION 32 12 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of this Section Includes:

1. Asphalt paving of roadways.

1.02 SYSTEM DESCRIPTION

A. Paving: Designed for traffic anticipated on the roadways.

1.03 RELATED SECTIONS

A. Section not used

1.04 QUALITY ASSURANCE

A. Reference Standards:

1. Pennsylvania Department of Transportation:

a. Publication 408 Specifications

b. Publication 27 – Specification for Bituminous Mixtures (Bulletin 27)

B. Perform Work in accordance with the latest edition of PennDOT Publication 408.

C. Mixing Plant: Conform to PennDOT Bulletin 27, chapter 1 Standards.

D. Conform to applicable Borough standards for paving work on public property.

1.05 SUBMITTALS

A. Certificates:

Submit certification from bituminous and aggregate suppliers attesting that materials conform to the State Specifications in accordance with Section 01 33 00.

1.06 ENVIRONMENTAL REQUIREMENTS

A. Do not place asphalt when base surface temperature is less than 40 degrees F or base surface is wet or frozen.

1.07 JOB CONDITIONS

A. Restore existing paving outside the limits of the Work that is damaged by Contractor’s operations, to its original condition at the expense of Contractor.

PART 2 PRODUCTS

2.01 PAVING MATERIALS

A. Bituminous Concrete Base Course: PennDOT Superpave (Section 313 of Publication 408).

B. Binder Course: PennDOT Superpave (Section 410 & 413 of Publication 408).

C. Wearing Course: PennDOT Superpave (Section 410 & 413 of Publication 408).

D. Tack Coat: Per Section 460 of PennDOT Publication 408, except revise the first sentence to read:

Emulsified Asphalt, Class E-8 (AASHTO CSS-1h or SS-1h)

E. Joint Seal: Asphalt PG 64S-22 Sealant (Publication 408).

2.02 SUBBASE COURSE MATERIALS

A. Coarse Aggregate: PennDOT No. 2A (Section 703.2 of Publication 408).

32 12 00-2

2.03 PAINTING MATERIALS

A. Sections 962, PennDOT Publication 408.

PART 3 EXECUTION

3.01 EXAMINATION AND PREPARATION

A. Verify gradients and elevations of area to be paved.

B. Trim existing paving with minimum one (1) foot cutbacks to remove damaged areas. Cut straight joint lines and right angle offsets.

C. Remove any temporary paving material.

D. Proof-roll subgrade (10 ton roller) and replace any soft or unsuitable material with coarse aggregate.

Verify compacted subgrade is dry and ready to support paving and imposed loads.

E. Apply tack coat in accordance with PennDOT Publication 408 requirements prior to placing an overlay over existing paving or prior to placing a wearing coarse over a previous placed binder course.

F. Coat surfaces of any manhole or catch basin frames with oil to prevent bond with asphalt paving.

3.02 SUBBASE COURSE

A. Place PennDOT No. 2A coarse aggregate in continuous layers not exceeding 6 inches loose depth, and compact (10 ton roller) to required contours and elevations.

3.03 PLACING ASPHALT PAVEMENT

A. Place bituminous concrete base course on surface of compacted subbase course to compacted thickness (10 ton roller where possible; minimum 5 ton roller in trenches) as shown on Drawings.

B. Place binder and wearing courses to compacted thicknesses (10 ton roller except minimum 5 ton roller for binder course in trenches) as shown on the Drawings. Apply tack coat on completed binder course before placing wearing course should there be a delay between completion of binder course and placement of wearing course.

C. Place wearing course overlay to compacted thickness (10 ton roller) as and where shown on the Drawings.

D. Compact pavement by rolling to achieve even and smooth finish, without roller marks. Hand compact in areas inaccessible to rolling equipment.

E. Where proposed asphalt paving adjoins existing asphalt paving, seal the joint with hot bituminous material in accordance with PennDOT Publication 408 requirements.

F. Provide painted markings where shown on Drawings.

3.04 TOLERANCES

A. Flatness: Maximum variation of 1/4 inch measured with 10 foot straight edge.

B. Compacted Scheduled Thickness: Within 1/4 inch of design thickness.

C. Variation from True Elevation: Within 1/2 inch.

END OF SECTION