This is a Contract Closeout specification document (Section 01 70 00) applicable to the Municipal Authority of the Borough of Morrisville's 2026 Design/Build Curb Ramp Project in Pennsylvania. The specification establishes comprehensive closeout procedures that contractors must follow upon project completion, including final cleaning of interior and exterior surfaces, equipment adjustment, and site debris removal. Contractors are required to maintain on-site project record documents throughout construction, including marked-up drawings, specifications, addenda, change orders, shop drawings, and manufacturer's instructions, with entries recorded concurrent with construction progress. The specification mandates submission of final completion photos, outstanding inspection reports, material testing reports, and final CS-4401 forms prior to final payment. A final inspection will be conducted by the Owner's Engineer, who will prepare a punchlist of items requiring completion or correction, which must be addressed within the existing contract time. The contract term is 45 consecutive calendar days from the Notice to Proceed, with final payment contingent upon completion and acceptance of all work and punchlist items.
Documentation required prior to final Application for Payment includes payroll certification forms from the contractor and all subcontractors for contracts exceeding $25,000, waivers of liens from all subcontractors and suppliers, a maintenance bond, any outstanding change orders with supporting documentation, applicable liquid fuels and PennDOT compliance certifications, and test or sample results. Contractors must also submit a final Application for Payment identifying the total adjusted contract price, previous payments, and remaining amount due. The specification requires a 10% bid bond or certified check, performance bonds, labor and material payment bonds, and comprehensive insurance documentation. All work must comply with PennDOT Publication 408 and Borough Standards, with the Owner purchasing all water system materials under a separate contract. The project involves installation of ADA/PennDOT-compliant curb ramps, sidewalks, curbing, and sign relocation/installation, with one base bid and seven alternate bids available for sealed bid submission through PennBid by November 13, 2025, at 10:00 AM.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT CLOSEOUT
01 70 00-1
SECTION 01 70 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Closeout procedures.
2. Final cleaning.
3. Adjusting.
4. Project record documents.
5. Operation and maintenance manual.
6. Spare parts and maintenance Products.
7. Other documentation.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 50 00: Construction Facilities and Temporary Controls: Progress cleaning.
1.03 CLOSEOUT PROCEDURES
A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Owner’s Engineer's review.
B. Owner’s Engineer shall make a final inspection and prepare a punchlist of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph 14.06 of the General Conditions.
C. Complete all items on the punchlist, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.
D. Provide submittals to Owner’s Engineer that are required by governing or other authorities.
E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.
F. Final Payment will not be made until final completion and acceptance of the Work.
G. Contractor shall provide final completion photos and any outstanding inspection reports, material testing reports, and final CS-4401 forms.
1.04 FINAL CLEANING
A. Execute final cleaning prior to final Project inspection.
B. Clean interior and exterior glass and surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.
C. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.
01 70 00-2
D. Clean or replace filters of operating equipment.
E. Clean debris from roofs, gutters, downspouts, and drainage systems.
F. Clean site; sweep paved areas, rake clean landscaped surfaces.
G. Remove waste and surplus materials, rubbish, and construction facilities from the site.
1.05 ADJUSTING
A. Adjust operating Products and equipment to ensure smooth and unhindered operation.
1.06 PROJECT RECORD DOCUMENTS
A. Maintain on-site one set of the following record documents; record actual revisions to the Work:
1. Drawings.
2. Specifications.
3. Addenda.
4. Change Orders and other modifications to the Contract.
5. Reviewed Shop Drawings, Product data, and samples.
6. Manufacturer’s instructions for assembly, installation and adjusting.
B. Ensure entries are complete and accurate, enabling future reference by Owner.
C. Store record documents separate from documents used for construction.
D. Record information concurrent with construction progress.
E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:
1. Manufacturer's name and product model and number.
2. Product substitutions or alternates utilized.
3. Changes made by Addenda and modifications.
F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:
1. Measured depth of foundations in relation to finish main floor datum.
2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.
3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.
4. Field changes of dimension and detail.
5. Details not on original Contract Drawings.
G. Delete Engineer's title block and seal from all documents.
H. Submit documents to Owner’s Engineer with claim for final Application for Payment.
1.07 OTHER DOCUMENTATION
A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:
1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds
01 70 00-3
$25,000).
2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's Release of Liens and Consent of Surety to Final Payment.
3. Maintenance Bond.
4. Any Change Orders with supporting documentation which remain to be submitted.
5. Applicable liquid fuels, PennDOT Compliance Certifications and related documents.
6. Test and/or sample results.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION