40-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf
PDF 104 KB Posted
- Solicitation number
- Not on record
- Issued by
- Bucks County, Pennsylvania
About this file
This is a Narrative Construction Schedule specification document prepared for the Municipal Authority of the Borough of Morrisville's 2026 Design/Build Curb Ramp Project located in Bucks County, Pennsylvania. The specification outlines the contractor's requirements for preparing, maintaining, and revising a detailed construction project schedule that monitors progress and duration of project operations. The contractor must submit an initial schedule based on the anticipated Notice to Proceed date, identifying the start dates for both the design and construction phases and specifying the order of completing each intersection. The schedule submission must include activity descriptions and locations, activity durations measured in working days, and calendar start and finish dates for all activities. Additionally, the contractor shall provide a workday calendar indicating work and non-work days, number of shifts per day, and hours per shift, with sufficient activity detail to demonstrate necessary interdependencies. The Owner's Engineer will review and respond to the detailed schedule and supporting documentation within ten calendar days of receipt. The contract duration is set at forty-five consecutive calendar days from the Notice to Proceed.
The Owner reserves the right to withhold progress payments until an acceptable construction schedule is submitted and approved. If the schedule is not received prior to the start of construction, the contractor will be required to attend a scheduling meeting to prepare an acceptable schedule, with the Owner potentially withholding progress payments until scheduling is completed. All submissions must be made electronically through PennBid by November 13, 2025, at 10:00 AM. The project involves ADA and PennDOT-compliant curb ramp installation with associated sidewalk, curbing, and sign work at specified locations within Morrisville Borough, with all materials, labor, and equipment required to comply with PennDOT Publication 408 and Borough Standards. The project includes a base bid and seven alternate bids, with assistance from CDBG funding. Bidders must submit a certified check or bid bond equal to ten percent of the bid amount and are required to provide performance bonds, labor and material payment bonds, and a maintenance bond.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NARRATIVE CONSTRUCTION SCHEDULE
01 32 16-1
SECTION 01 32 16
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. The Work Of This Section Includes:
1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 31 00 - Coordination and Meetings
PART 2 – PRODUCTS
2.01 Not Used
PART 3 - EXECUTION
3.01 CONSTRUCTION SCHEDULE
A. Base the initial schedule on the anticipated Notice to Proceed Date in the proposal. Submit an initial schedule outlining the anticipated start date for the design phase and construction phase. The schedule for the construction phase shall identify the order of completing each intersection. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.
B. Owner’s Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:
Activity description & location;
Duration of activity, in working days; and Start and finish calendar dates of activities.
D. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.
E. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.
F. If the schedule is not received prior to the start of construction, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.
END OF SECTION