45-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf

PDF 133 KB Posted

Attached to
Morrisville Borough 2026 Design/Build Curb Ramp Project
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Construction Facilities and Temporary Controls specification document (Section 01 50 00) related to the Municipal Authority of the Borough of Morrisville's 2025 Galvanized Service Replacement project and 2026 Design/Build Curb Ramp Project in Bucks County, Pennsylvania. The specification outlines the contractor's responsibility for providing temporary utilities including electricity, lighting, heat, ventilation, communications, water, and sanitary facilities during construction. The contractor must also establish temporary controls consisting of barriers, enclosures, and fencing; provide protection of work; implement water control and dust control measures; and develop construction facilities including access roads, parking areas, progress cleaning, project signage, and temporary buildings. The contract duration is 45 consecutive calendar days from the Notice to Proceed, with electronic bid submissions required through PennBid by November 13, 2025, at 10:00 AM. Sealed bids must be accompanied by a certified check or bid bond equal to at least 10 percent of the bid amount.

The specification establishes that all costs associated with temporary utilities, sanitary facilities, fencing, water control, and dust control are the contractor's responsibility at no additional cost to the Owner. The contractor must provide a 6-foot-high fence with vehicular and pedestrian gates around the construction site and implement dust control measures as directed by the Owner's Engineer. The contractor is required to maintain the site in a clean and orderly condition through daily waste removal and debris collection, provide security to prevent unauthorized entry and vandalism, and restore all temporary facilities and existing facilities used during construction to original condition upon project completion. Bidders must demonstrate prior experience by having completed at least three similar projects valued at 75 percent or more of the proposed contract amount and provide performance bonds, labor and material payment bonds, and maintenance bonds along with comprehensive insurance documentation. The project focuses on ADA/PennDOT compliant curb ramp installation with sidewalks, curbing, and sign relocation in accordance with PennDOT Publication 408 and Borough Standards, with CDBG funding assistance.

View the file

Other files

File Type Posted
53-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
9-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
39-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
18-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
29-Doc 00 73 00 6 - RESPONSIBLE - CONTRACTOR ORDINANCE.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 73 00 07 - APPENDIX D - COVER.pdf PDF
13-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
54-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
32-Doc 00 73 00 08 Part 1 Contract Language Requirements.pdf PDF
42-Sec 01 33 00 - SUBMITTALS.pdf PDF
49-Sec 02 41 16 - DEMOLITION.pdf PDF
6-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
58-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
22-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
55-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
46-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
56-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
2-Doc 00 01 10-TOC.pdf PDF
24-Doc 00 73 00 1 - APPENDIX A - COVER.pdf PDF
19-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
43-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
31-Doc 00 73 00 07 APPENDIX D - CDBG AND STATE REQUIREMENTS.pdf PDF
36-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
1-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
34-Doc 00 73 00 10 - Part 3 Section 3 Requirements.pdf PDF
40-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
20-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
50-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
59-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
37-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
25-Doc 00 73 00 1 - APPENDIX A - DAVIS BACON FEDERAL WAGE DETERMINATION.pdf PDF
62-CDBG Curb Ramp Concept Plans.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
15-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
47-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
16-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
4-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
57-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
52-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
61-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
41-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
23-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
7-Doc 00 41 00 - BID FORM - EBID.pdf PDF
17-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
10-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
21-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

01 50 00-1

SECTION 01 50 00

PART 1 GENERAL

1.01 GENERAL

A. The Work of this Section shall be the responsibility of the contractor as noted in the Summary of Work (Section 01 11 13).

1.02 SECTION INCLUDES

A. Temporary Utilities: Electricity, lighting, heat, ventilation, communications service, water and sanitary facilities.

B. Temporary Controls: Barriers, enclosures and fencing, protection of the Work, water control and dust control.

C. Construction Facilities: Access roads, parking, progress cleaning, project signage, and temporary buildings.

1.03 RELATED SECTIONS

A. Section 01 57 13: Soil Erosion and Sediment Control.

B. Section 01 55 26: Traffic Regulation.

C. Section 01 70 00: Contract Closeout: Final cleaning.

1.04 TEMPORARY ELECTRICITY

A. Cost: By Contractor; provide and pay for power service required from utility source.

1.05 TEMPORARY SANITARY FACILITIES

A. Provide and maintain required facilities and enclosures.

Existing facility use is not permitted. Provide at time of project mobilization.

B. At end of construction, return facilities to same or better condition than originally found.

1.06 BARRIERS

A. Provide barriers to prevent unauthorized entry to construction areas and to protect existing facilities and adjacent properties from damage from construction operations.

B. Provide protection for plants designated to remain. Replace damaged plants.

C. Protect non-owned vehicular traffic, stored materials, site, and structures from damage.

1.07 FENCING

A. Construction: Contractor's option.

B. Provide 6-foot-high fence around construction site; equip with vehicular and pedestrian gates with locks.

1.08 WATER CONTROL

01 50 00-2

A. Grade site to drain. Maintain excavations free of water. Provide, operate, and maintain pumping equipment.

B. Protect site from puddling or running water.

1.09 PROTECTION OF INSTALLED WORK

A. Protect installed Work and provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed Products. Control activity in immediate work area to prevent damage.

C. Prohibit traffic from landscaped areas.

1.10 SECURITY

A. Provide security and facilities to protect Work, and Owner's operations from unauthorized entry, vandalism, or theft.

1.11 PROGRESS CLEANING AND WASTE REMOVAL

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition.

B. Collect and remove waste materials, debris, and rubbish from site daily and dispose off-site.

C. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids.

1.12 PROJECT IDENTIFICATION

A. No other signs are allowed without Owner permission except those required by law.

1.13 REMOVAL OF UTILITIES, FACILITIES, AND CONTROLS

A. Clean and repair damage caused by installation or use of temporary work.

B. Restore existing facilities used during construction to original condition. Restore permanent facilities used during construction to specified condition.

1.14 DUST CONTROL

A. Execute Work by methods to minimize raising dust from construction operations.

B. Provide positive means (i.e. use of sprinkling water or other methods approved by the Owner) to prevent air-borne dust from dispersing into atmosphere.

C. Dust control measures shall be employed when required in the opinion of the Owner’s

Engineer at no additional cost to Owner.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

01 50 00-3

Not Used

END OF SECTION