38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf

PDF 136 KB Posted

Attached to
Morrisville Borough 2026 Design/Build Curb Ramp Project
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Contract Considerations specification document (Section 01 29 00) applicable to the Municipal Authority of the Borough of Morrisville's 2025 Galvanized Service Replacement project (Contract No. W-56) in Pennsylvania. The document establishes procedures for schedule of values, applications for payment, change orders, and alternates. Contractors must submit a preliminary Schedule of Values in duplicate within 10 days after the effective date of the agreement, formatted according to supplementary conditions and including direct proportional amounts of overhead and profit for each line item. Applications for payment must be submitted monthly in triplicate on EJCDC Form C-620, utilizing the Schedule of Values for itemization, and must include payroll certification forms for contracts exceeding $25,000, updated construction progress schedules, and—for final payment applications only—waivers of liens or contractor's affidavits. The contract specifies a 45 consecutive calendar day performance period from the Notice to Proceed, with sealed bids due electronically through PennBidTM by November 13, 2025, at 10:00 AM. The project involves one base bid and seven alternate bids for ADA/PennDOT-compliant curb ramp installation, sidewalks, curbing, and sign relocation/installation within Morrisville Borough, with all work performed in accordance with PennDOT Publication 408 and Borough Standards.

The contract requires a 10% bid bond or certified check payable to the Owner, with bonds accepted only from companies licensed in Pennsylvania. Changes to the work are managed through multiple procedures: the Owner's Engineer may issue supplemental instructions for minor changes not affecting contract price or time; a Proposal Request process allows 15 days for contractor estimates on price and time impacts; contractors may propose changes with full documentation of effects; and change orders are executed as Stipulated Price Change Orders, Unit Price Change Orders, Work Change Directives (EJCDC Form C-940), or Time and Material Change Orders (EJCDC Form C-941) as appropriate. The Owner will separately purchase all water system materials under a distinct contract. Bidders must provide performance bonds, labor and material payment bonds, maintenance bonds, and comprehensive insurance documentation, with no bidder permitted to withdraw their bid within 60 days after the scheduled closing time. The Owner reserves the right to waive any informalities or reject any or all bids. CDBG funding is noted as assisting the project.

View the file

Other files

File Type Posted
53-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
9-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
45-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
39-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
18-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
29-Doc 00 73 00 6 - RESPONSIBLE - CONTRACTOR ORDINANCE.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 73 00 07 - APPENDIX D - COVER.pdf PDF
13-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
54-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
32-Doc 00 73 00 08 Part 1 Contract Language Requirements.pdf PDF
42-Sec 01 33 00 - SUBMITTALS.pdf PDF
49-Sec 02 41 16 - DEMOLITION.pdf PDF
6-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
58-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
22-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
55-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
46-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
56-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
2-Doc 00 01 10-TOC.pdf PDF
24-Doc 00 73 00 1 - APPENDIX A - COVER.pdf PDF
19-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
43-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
31-Doc 00 73 00 07 APPENDIX D - CDBG AND STATE REQUIREMENTS.pdf PDF
36-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
1-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
34-Doc 00 73 00 10 - Part 3 Section 3 Requirements.pdf PDF
40-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
20-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
50-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
59-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
37-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
25-Doc 00 73 00 1 - APPENDIX A - DAVIS BACON FEDERAL WAGE DETERMINATION.pdf PDF
62-CDBG Curb Ramp Concept Plans.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
15-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
47-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
16-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
4-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
57-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
52-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
61-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
41-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
23-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
7-Doc 00 41 00 - BID FORM - EBID.pdf PDF
17-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
10-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
21-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CONSIDERATIONS

01 29 00-1

SECTION 01 29 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Schedule of values.

2. Application for payment.

3. Change procedures.

4. Alternates.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Document 00 52 00: Agreement: Contract Price

2. Section 01 22 00: Measurement and Payment

3. Section 01 33 00: Submittals: Schedule of Values.

4. Section 01 60 00: Material and Equipment: Product substitutions and options.

1.03 SCHEDULE OF VALUES

A. Submit a printed schedule on Contractor's standard form or electronic media printout.

B. Submit preliminary Schedule of Values in duplicate within 10 days after Effective Date of the Agreement.

C. Format: See Supplementary Conditions

D. Include in each line item, the amount of allowance. For unit cost allowances, identify quantities taken from Contract Documents multiplied by the unit cost to achieve the total for the item.

E. Include within each line item, a direct proportional amount of Contractor's overhead and profit.

F. Revise schedule to list approved Change Orders, with each Application for Payment.

1.04 APPLICATIONS FOR PAYMENT

A. Submit three (3) copies of each application on EJCDC Form C-620.

B. Content and Format: Utilize Schedule of Values for listing items in Application for Payment.

C. Payment Period: Monthly

D. Include Payroll Certification forms with each Payment Application (if contract exceeds $25,000).

E. Include an updated construction progress schedule.

F. Waiver of Liens or Contractor's Affidavit, Contractor's Release and Statement of Surety Company (with Final Payment Application only).

1.05 CHANGE PROCEDURES

01 29 00-2

A. Owner’s Engineer will advise of minor changes in the Work not involving an adjustment to

Contract Price or Contract Time as authorized by Paragraph 9.5 of the General Conditions by issuing supplemental instructions.

B. Owner’s Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and specifications. Contractor will prepare and submit an estimate within 15 days relative to changes in Contract Price and/or Contract Time.

C. Contractor may propose changes by submitting a request for change to Owner’s Engineer, describing the proposed change and its full effect on the Work. Include a statement describing the reason for the change, and the effect on the Contract Price and Contract Time with full documentation and a statement describing effect on Work by any other contractors.

Document any requested substitutions in accordance with Section 01 60 00.

D. Stipulated Price Change Order: Based on Proposal Request and Contractor's fixed price quotation or Contractor's request for a Change Order as approved by Owner’s Engineer.

E. Unit Price Change Order: For contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of work which are not predetermined, the Change Order will be executed based on Contractor's proposed unit prices and quantities of units as approved by Owner’s Engineer.

F. Work Change Directive: Owner’s Engineer may issue a directive, on EJCDC Form C-940 Work Change Directive signed by Owner, instructing Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work, and designate method of determining any change in Contract Price or Contract Time. Promptly execute the change.

G. Time and Material Change Order: Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract. Engineer will determine the change allowable in Contract Price and Contract Time as provided in the Contract Documents.

H. Maintain detailed records of Work done on Time and Material basis. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

I. Change Order Form: EJCDC Form C-941.

J. Execution of Change Orders: Owner’s Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.06 ALTERNATES

A. Accepted alternates will be identified in the Agreement.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION