39-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf
PDF 112 KB Posted
- Solicitation number
- Not on record
- Issued by
- Bucks County, Pennsylvania
About this file
This is a technical specification document for Section 01 31 00 - Coordination and Meetings, applicable to the Municipal Authority of the Borough of Morrisville's 2026 Design/Build Curb Ramp Project in Pennsylvania. The specification outlines the contractor's responsibilities for project coordination, field engineering, and required meetings throughout the construction process. Key coordination requirements include scheduling submittals, sequencing interdependent construction elements, and managing site access during and after Owner occupancy. The contractor must provide field engineering services including survey control verification, stakeout, elevation and line establishment, and protection of survey control points established by the Design Engineer. A preconstruction meeting is mandatory, to be scheduled by the Owner's Engineer after the Effective Date of the Agreement and prior to work commencement, with required attendance from the Owner, Owner's Engineer, Owner's Resident Project Representative, Contractor, Contractor's Superintendent, major Subcontractors, Contractor's Design Engineer, and Third-Party Inspection representatives. The preconstruction meeting agenda must address contract document distribution, subcontractor and product submissions, personnel designations, procedures for field decisions and change orders, scheduling, and premises usage. Meeting minutes must be distributed within seven working days. Progress meetings are scheduled on an as-needed basis throughout construction, presided over by the Owner's Resident Project Representative, with required attendance from the Contractor's superintendent, major Subcontractors, suppliers, Owner, and Owner's Engineer as appropriate. Progress meeting agendas cover work progress review, field observations, submittal status, delivery schedules, progress schedule maintenance, quality standards, and coordination of projected progress, with minutes distributed within five working days.
The specification contains no explicit pricing terms, set-asides, incumbent information, or funding requirements, as it is a technical coordination procedure document rather than a bid solicitation or contract award notice. The document establishes administrative and coordination protocols to ensure efficient project execution and communication among all parties involved in the curb ramp construction project. Contract administration timelines are specified through meeting minute distribution requirements—seven working days for preconstruction meeting minutes and five working days for progress meeting minutes—establishing clear communication protocols for project documentation and coordination throughout the contract term.
View the file
Other files
Show 40 more
Latest 50 of 125 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COORDINATION AND MEETINGS
01 31 00-1
SECTION 01 31 00
COORDINATION AND MEETINGS
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. The Work of this Section Includes:
1. Coordination and Project conditions.
2. Field engineering.
3. Preconstruction meeting.
4. Progress meetings.
1.02 RELATED SECTIONS
A. This section not used.
1.03 COORDINATION AND PROJECT CONDITIONS
A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.
B. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial
Completion and for portions of Work designated for Owner’s occupancy.
C. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s activities.
1.04 FIELD ENGINEERING
A. Contractor is responsible to locate survey control and reference points and provide stakeout as required for construction activities. Contractor is responsible for the protection of survey control and reference points.
B. Control datum for survey is that established by Design Engineer providing survey.
C. Verify set-backs and easements; confirm drawing dimensions and elevations.
D. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.
E. Construct Work based on elevations, lines and locations as established, utilizing recognized survey control points and stakeout.
1.05 PRECONSTRUCTION MEETING
A. Owner’s Engineer will schedule a meeting at the Project site after the Effective Date of the
Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.
B. Attendance Required: Owner, Owner’s Engineer, Owner’s Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors, Contractor’s Design
01 31 00-2
Engineer, Contractor’s Third-Party Inspection representative.
C. Agenda:
1. Distribution of Contract Documents.
2. Submission of list of subcontractors, list of products, submittals, and progress schedule.
3. Designation of personnel representing the parties in Contract and the OWNER’S
ENGINEER.
4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.
5. Scheduling.
6. Use of premises by OWNER and CONTRACTOR.
D. Owner’s Engineer shall record minutes and distribute copies within seven (7) working days after meeting to Owner and all other participants.
1.06 PROGRESS MEETINGS
A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.
B. Owner’s Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings as necessary.
C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Owner, and Owner’s Engineer, as appropriate to agenda topics for each meeting.
D. Agenda:
1. Review minutes of previous meetings.
2. Review of Work progress.
3. Field observations, problems, and decisions.
4. Identification of problems which impede planned progress.
5. Review of submittals schedule and status of submittals.
6. Review of off-site fabrication and delivery schedules.
7. Maintenance of progress schedule.
8. Corrective measures to regain projected schedules.
9. Planned progress during succeeding work period.
10. Coordination of projected progress.
11. Maintenance of quality and work standards.
12. Effect of proposed changes on progress schedule and coordination.
13. Other business relating to Work.
E. Owner’s Resident Project Representative shall record minutes and distribute copies within five
(5) working days after meeting to Owner, Owner’s Engineer and all other participants.
PART 2 - PRODUCTS
2.01 Not Used
PART 3 - EXECUTION
3.01 Not Used
01 31 00-3
END OF SECTION