39-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf

PDF 112 KB Posted

Attached to
Morrisville Borough 2026 Design/Build Curb Ramp Project
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a technical specification document for Section 01 31 00 - Coordination and Meetings, applicable to the Municipal Authority of the Borough of Morrisville's 2026 Design/Build Curb Ramp Project in Pennsylvania. The specification outlines the contractor's responsibilities for project coordination, field engineering, and required meetings throughout the construction process. Key coordination requirements include scheduling submittals, sequencing interdependent construction elements, and managing site access during and after Owner occupancy. The contractor must provide field engineering services including survey control verification, stakeout, elevation and line establishment, and protection of survey control points established by the Design Engineer. A preconstruction meeting is mandatory, to be scheduled by the Owner's Engineer after the Effective Date of the Agreement and prior to work commencement, with required attendance from the Owner, Owner's Engineer, Owner's Resident Project Representative, Contractor, Contractor's Superintendent, major Subcontractors, Contractor's Design Engineer, and Third-Party Inspection representatives. The preconstruction meeting agenda must address contract document distribution, subcontractor and product submissions, personnel designations, procedures for field decisions and change orders, scheduling, and premises usage. Meeting minutes must be distributed within seven working days. Progress meetings are scheduled on an as-needed basis throughout construction, presided over by the Owner's Resident Project Representative, with required attendance from the Contractor's superintendent, major Subcontractors, suppliers, Owner, and Owner's Engineer as appropriate. Progress meeting agendas cover work progress review, field observations, submittal status, delivery schedules, progress schedule maintenance, quality standards, and coordination of projected progress, with minutes distributed within five working days.

The specification contains no explicit pricing terms, set-asides, incumbent information, or funding requirements, as it is a technical coordination procedure document rather than a bid solicitation or contract award notice. The document establishes administrative and coordination protocols to ensure efficient project execution and communication among all parties involved in the curb ramp construction project. Contract administration timelines are specified through meeting minute distribution requirements—seven working days for preconstruction meeting minutes and five working days for progress meeting minutes—establishing clear communication protocols for project documentation and coordination throughout the contract term.

View the file

Other files

File Type Posted
53-Sec 10 14 53 - POST MOUNTED SIGNS.pdf PDF
9-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
45-Sec 01 50 00 - CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
18-Doc 00 62 16 - CERTIFICATE OF INSURANCE.pdf PDF
35-Doc 00 91 13 - ADDENDA.pdf PDF
29-Doc 00 73 00 6 - RESPONSIBLE - CONTRACTOR ORDINANCE.pdf PDF
48-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
30-Doc 00 73 00 07 - APPENDIX D - COVER.pdf PDF
13-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
54-Sec 31 23 33 - EXCAVATION BACKFILL AND COMPACTION.pdf PDF
32-Doc 00 73 00 08 Part 1 Contract Language Requirements.pdf PDF
42-Sec 01 33 00 - SUBMITTALS.pdf PDF
49-Sec 02 41 16 - DEMOLITION.pdf PDF
6-Doc 00 21 13.1 - INSTRUCTIONS FOR ELECTRONIC BIDDING.pdf PDF
58-Sec 32 13 13 - PORTLAND CEMENT CONCRETE PAVING.pdf PDF
22-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
55-Sec 32 01 17.61 - POLYMER MODIFED ASPHALT JOINT AND CRACK SEALING.pdf PDF
46-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
38-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
56-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
2-Doc 00 01 10-TOC.pdf PDF
24-Doc 00 73 00 1 - APPENDIX A - COVER.pdf PDF
19-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
43-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
31-Doc 00 73 00 07 APPENDIX D - CDBG AND STATE REQUIREMENTS.pdf PDF
36-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
1-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
5-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
34-Doc 00 73 00 10 - Part 3 Section 3 Requirements.pdf PDF
40-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
20-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
50-Sec 03 11 00 - CONCRETE FORMWORK.pdf PDF
59-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
37-Sec 01 22 00 - MEASUREMENT AND PAYMENT.pdf PDF
25-Doc 00 73 00 1 - APPENDIX A - DAVIS BACON FEDERAL WAGE DETERMINATION.pdf PDF
62-CDBG Curb Ramp Concept Plans.pdf PDF
44-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
15-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
47-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
16-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
4-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
57-Sec 32 12 23 - RESTORATION OF PAVED SURFACES.pdf PDF
52-Sec 03 30 00 - CAST IN PLACE CONCRETE.pdf PDF
61-Sec 32 92 00 - FINISH GRADING, SEEDING, AND SODDING.pdf PDF
41-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
23-Doc 00 73 00 0 - SUPPLEMENTARY CONDITIONS.pdf PDF
7-Doc 00 41 00 - BID FORM - EBID.pdf PDF
17-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
10-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
21-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
Show 40 more

Latest 50 of 125 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COORDINATION AND MEETINGS

01 31 00-1

SECTION 01 31 00

COORDINATION AND MEETINGS

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of this Section Includes:

1. Coordination and Project conditions.

2. Field engineering.

3. Preconstruction meeting.

4. Progress meetings.

1.02 RELATED SECTIONS

A. This section not used.

1.03 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial

Completion and for portions of Work designated for Owner’s occupancy.

C. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s activities.

1.04 FIELD ENGINEERING

A. Contractor is responsible to locate survey control and reference points and provide stakeout as required for construction activities. Contractor is responsible for the protection of survey control and reference points.

B. Control datum for survey is that established by Design Engineer providing survey.

C. Verify set-backs and easements; confirm drawing dimensions and elevations.

D. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.

E. Construct Work based on elevations, lines and locations as established, utilizing recognized survey control points and stakeout.

1.05 PRECONSTRUCTION MEETING

A. Owner’s Engineer will schedule a meeting at the Project site after the Effective Date of the

Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.

B. Attendance Required: Owner, Owner’s Engineer, Owner’s Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors, Contractor’s Design

01 31 00-2

Engineer, Contractor’s Third-Party Inspection representative.

C. Agenda:

1. Distribution of Contract Documents.

2. Submission of list of subcontractors, list of products, submittals, and progress schedule.

3. Designation of personnel representing the parties in Contract and the OWNER’S

ENGINEER.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.

5. Scheduling.

6. Use of premises by OWNER and CONTRACTOR.

D. Owner’s Engineer shall record minutes and distribute copies within seven (7) working days after meeting to Owner and all other participants.

1.06 PROGRESS MEETINGS

A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.

B. Owner’s Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings as necessary.

C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Owner, and Owner’s Engineer, as appropriate to agenda topics for each meeting.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems which impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

E. Owner’s Resident Project Representative shall record minutes and distribute copies within five

(5) working days after meeting to Owner, Owner’s Engineer and all other participants.

PART 2 - PRODUCTS

2.01 Not Used

PART 3 - EXECUTION

3.01 Not Used

01 31 00-3

END OF SECTION