This is a Summary of Work document for the Borough of Doylestown, Pennsylvania, detailing Contract 2400754 for repairs to the Fanny Chapman Memorial Pool's main pool. The project scope encompasses the removal of surface concrete to competent substrate and resurfacing with polymer-modified concrete, along with grout injection to fill void spaces beneath the pool. The base bid covers approximately 2,900 square feet of pool surface, with alternate bid items available to expand work to an additional 1,960 square feet encompassing the entire main pool. Sealed bids will be accepted online via the PennBid Program until September 22, 2025, at 2:00 PM, with a non-mandatory pre-bid meeting scheduled for September 4, 2025, at 10:00 AM at the pool location (10 McKinstry Drive, Doylestown, PA 18901). The project must be completed by April 1, 2026. The Borough will occupy the site during construction and work must be scheduled to accommodate normal operations while maintaining coordination with property owners and underground utility owners through required advance notification periods of 72 hours for utilities and 24 hours for residents.

The contractor will be responsible for all labor, equipment, materials, and repair of any existing features damaged during execution of work, with no products supplied by the Borough except temporary post shores that must be returned upon project completion. Work must comply with OSHA Construction Workplace Safety Standards and Pennsylvania Act 287 regarding utility location. The Borough reserves the right to reject any or all bids and select the most advantageous combination of base and alternate bids. The project is subject to Pennsylvania's Prevailing Wage Act (Act 422) and Public Works Employment Verification requirements (Act 127). Contractors must demonstrate participation in formal apprenticeship training programs with at least 70 percent of craft employees being registered apprenticeship program graduates. Payment will be structured monthly with initial 10 percent retainage, potentially reducing to 5 percent at 50 percent completion, with liquidated damages set at $500 per day for delays beyond the completion date.

View the file

Other files

File Type Posted
11-Sec 01 50 00 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS.pdf PDF
44-Doc 00 72 00 GENERAL CONDITIONS.pdf PDF
36-Doc 00 65 19.13 ContractorsAffidavit.pdf PDF
39-Doc 00 61 19 MAINTENANCE BOND.pdf PDF
31-Doc 00 73 00.00 SUPPLEMENTARY CONDITIONS - revised.pdf PDF
18-Sec 01 40 00 QUALITY CONTROL.pdf PDF
16-X Sketch-Pool Repair Areas.pdf PDF
42-Doc 00 73 00.10 Attach A.pdf PDF
15-Sec 03 25 00 Waterstops and Waterproofing.pdf PDF
22-Doc 00 62 76 Appl Payment.pdf PDF
23-Doc 00 11 13 Advertisement PennBid FC Concrete 2026.pdf PDF
35-Doc 00 45 19 NON-COLLUSION AFFIDAVIT.pdf PDF
46-Doc 00 73 00.30 Attach C.pdf PDF
28-Doc 00 61 13.16 Payment Bond.pdf PDF
38-Doc 00 62 16 CERTIFICATE INSURANCE.pdf PDF
1-Doc 00 73 00.33 Attach C-RCO Subcontractor Certification Form.pdf PDF
13-Sec 13 11 13.1 Concrete Pool Repairs.pdf PDF
47-Doc 00 73 00.20 Attach B.pdf PDF
32-Doc 00 01 01 TITLE SHEET AND COVER.pdf PDF
20-Doc 00 45 53 AGREEMENT SURETY COMPANY.pdf PDF
37-Doc 00 65 19.19 Consent Surety Final.pdf PDF
27-Sec 01 70 00 CONTRACT CLOSEOUT.pdf PDF
2-Doc 00 73 00.31 Attach C-Responsible Contrator Ordinance.pdf PDF
7-Sec 02 41 19 Selective Demolition.pdf PDF
19-Doc 00 21 13 INSTRUCTIONS TO BIDDERS EBID 2026.pdf PDF
8-Sec 07 92 13 Thermal and Moisture Protection at Pool Expansion Joints.pdf PDF
45-X Product Data Sheets.pdf PDF
30-Doc 00 73 00.21 Attach B-Public Works Employment Verification Form.pdf PDF
41-Doc 00 45 13 BIDDER QUALIFICATION STATEMENT.pdf PDF
9-Sec 01 31 00 COORDINATION AND MEETINGS.pdf PDF
17-Doc 00 43 13 BID BOND.pdf PDF
29-Doc 00 73 00.32 Attach C-RCO Contractor Certification Form.pdf PDF
24-Sec 01 22 00 MEASUREMENT AND PAYMENT - 2025-09-16.pdf PDF
6-Sec 01 71 13 Mobilization.pdf PDF
12-Sec 03 62 13 Grouting.pdf PDF
43-Doc 00 41 00 BID FORM-EBID.pdf PDF
40-Doc 00 73 00.11 Attach A-prevailing wage rates 26-02618.pdf PDF
21-Doc 00 61 13.13 Peformance Bond.pdf PDF
14-Doc 00 01 10-Table Contents.pdf PDF
34-Doc 00 65 19.16 ContractorsRelease.pdf PDF
4-Doc 00 91 13 ADDENDA.pdf PDF
33-Doc 00 52 00 AGREEMENT.pdf PDF
26-Doc 00 45 10 BIDDERS ACKNOWLEDGEMENT.pdf PDF
25-Doc 00 63 63 ChangeOrder.pdf PDF
3-Sec 01 29 00 CONTRACT CONSIDERATIONS.pdf PDF
10-Sec 01 60 00 MATERIAL AND EQUIPMENT.pdf PDF
35-Doc 00 65 19.13 ContractorsAffidavit.pdf PDF
7-Doc 00 73 00.11 Attach A-prevailing wage rates 25-08056.pdf PDF
32-Doc 00 65 19.16 ContractorsRelease.pdf PDF
1-Doc 00 61 13.13 Peformance Bond.pdf PDF
Show 40 more

Latest 50 of 93 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Borough of Doylestown Section 01 11 13 Summary of Work 2400754 - Fanny Chapman - Main Pool Repairs Page 1 of 2

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Description of Work.

2. Work by Owner.

3. Work by other parties.

4. Owner supplied Products.

5. Contractor use of site [and premises].

6. Future work.

7. Work sequence of construction.

8. Owner occupancy.

1.02 DESCRIPTION OF WORK

A. The Work to be completed under this contract consists of all labor, equipment and materials to repair a section of the main pool by removing surface concrete to competent substrate and resurfacing the pool with polymer modified concrete. The work also includes filing of void space under the pool by grout injection. Alternate bid items may be included to increase the scope of work to encompass the entire main pool.

1.03 WORK BY OWNER

A. No other work is being planned by Owner at the site during construction of the Work under this contract.

1.04 WORK BY OTHER PARTIES

A. No other work by other parties is anticipated in the immediate vicinity during construction of the Work under this contract.

1.05 OWNER SUPPLIED PRODUCTS

A. No products are to be supplied and paid for by the Borough other than the Borough-Owned temporary post shores that are to be transported, installed and dismantled by the Contractor, and returned to the Borough at the conclusion of the project.

1.06 CONTRACTOR USE OF SITE AND PREMISES

A. Contractor shall take all necessary precautions to protect all existing water, gas, electric, communications, sanitary sewer, storm sewer, or other facilities encountered during the course of his operations, to guard against disruption of service. Before beginning Work, Contractor shall determine the location of each facility which is questionable. It is the responsibility of Contractor to establish the exact location in accordance with the requirements of Pennsylvania Act 287 (1974) as last amended by Act 121 (2008). A Utility User's List can be made available by request.

B. Repair and/or replacement of any existing features and facilities damaged in the execution of the Work under this Contract including but not limited to sidewalk, curb, water, gas, electric, communication, sanitary sewer and storm sewer shall be the responsibility of the Contractor.

C. Contractor shall conduct all Work in strict compliance with OSHA Construction Workplace

Safety Standards.

1.07 FUTURE WORK

A. No future work is proposed as part of this contract.

Borough of Doylestown Section 01 11 13 Summary of Work 2400754 - Fanny Chapman - Main Pool Repairs Page 2 of 2

1.08 WORK SEQUENCE OF CONSTRUCTION

A. During the performance of the Work, Contractor shall follow the sequence of construction noted on the Drawings. In addition to the sequence on the plan, the Contractor shall:

1. Contact all underground utility owners, Owner, and Engineer at least seventy-two (72) hours prior to beginning construction.

2. Contact property owners and residents at least twenty-four (24) hours prior to start of construction on or near their properties or residences.

B. Contractor may propose an alternate sequence of construction subject to approval by

Engineer.

1.09 OWNER OCCUPANCY

A. Owner will occupy the site and premises during the entire period of construction for the conduct of normal operations.

B. Cooperate with Owner to minimize conflict and to facilitate Owner’s operations.

C. Schedule the Work to accommodate Owner occupancy.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION