This is a prevailing wage rate document issued by the Commonwealth of Pennsylvania Department of Labor & Industry for the Fanny Chapman Memorial Pool – Main Pool Bottom Concrete Repair project (Serial Number 26-02618) in Doylestown Borough, Bucks County, Pennsylvania. The project involves removing surface concrete from approximately 2,900 square feet of the main pool bottom to competent substrate and resurfacing with polymer-modified concrete, with alternate bid items to expand the scope to an additional 1,960 square feet. Sealed bids are due April 14, 2026, at 2:00 PM via the PennBid Program, with a non-mandatory pre-bid meeting scheduled for March 31, 2026, at 10:00 AM at the pool location (10 McKinstry Drive, Doylestown, PA 18901). The contract award date is May 18, 2026, and project completion is scheduled for April 1, 2026. The project is classified as Highway work under the Pennsylvania Prevailing Wage Act (Act 422) and is subject to Public Works Employment Verification requirements (Act 127).
The prevailing wage rates document, effective March 17, 2026, establishes hourly rates and fringe benefits for all worker classifications required on the project, with rates varying by trade, effective date, and classification. Key trades identified include Cement Masons ($46.55–$79.21 total hourly compensation for Heavy/Highway work), Carpenters ($57.36–$97.96), Laborers (Class 01–14, ranging from $62.80–$72.13), and various Operators classifications ($79.50–$108.21). All contractors must comply with prevailing wage requirements and demonstrate participation in formal apprenticeship training programs, with at least 70% of craft employees being registered apprenticeship program graduates. The contract includes a PennBid administrative fee of 0.33% of the bid amount (minimum $150, maximum $6,000) for awarded bidders, monthly payment with initial 10% retainage reducing to 5% at 50% completion, and liquidated damages of $500 per day for delays beyond the completion deadline. Funding is provided through municipal sources.
View the file
Other files
Show 40 more
Latest 50 of 93 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: Fanny Chapman Memorial Pool - Main Pool Bottom Concrete Repair
General Description: Voids under the pool bottom are to be injection-filled with grout and the pool bottom concrete is to be repaired. The concrete repair involves removal of surface concrete on the bottom of the pool to competent substrate (approximately 2 to 3 inches) and resurfacing the pool bottom with polymer modified concrete.
Project Locality Doylestown Borough, PA
Awarding Agency: Doylestown Borough
Contract Award Date: 5/18/2026
Serial Number: 26-02618
Project Classification: Highway
Determination Date: 3/17/2026
Assigned Field Office: Philadelphia
Field Office Phone Number: (215)560-1858
Toll Free Phone Number:
Project County: Bucks County
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Commonwealth of Pennsylvania Department of Labor & Industry Report Date: 3/17/2026 Page 1 of 6
Project: 26-02618 - Building Effective Date
Expiration Date
Hourly Rate Fringe Benefits
Total
Asbestos & Insulation Workers 5/1/2025 $60.84 $48.71 $109.55
Boilermaker (Commercial, Institutional, and Minor Repair Work)
3/1/2024 $36.71 $19.13 $55.84
Boilermakers 1/1/2024 $52.10 $35.72 $87.82
Bricklayer 5/1/2023 $47.50 $31.42 $78.92
Bricklayer 5/1/2025 $50.00 $32.57 $82.57
Carpenter - Chief of Party (Surveying & Layout) 5/1/2025 $54.59 $29.02 $83.61
Carpenter - Instrument Person (Surveying & Layout) 5/1/2025 $47.47 $29.02 $76.49
Carpenter - Rodman (Surveying & Layout) 5/1/2025 $23.74 $20.62 $44.36
Carpenters 5/1/2025 $47.47 $29.02 $76.49
Cement Masons 5/1/2024 $46.70 $32.46 $79.16
Cement Masons 5/1/2025 $48.70 $32.46 $81.16
Dockbuilder, Pile Drivers 5/1/2025 $55.23 $37.99 $93.22
Dockbuilder, Pile Drivers 5/1/2026 $56.98 $37.99 $94.97
Dockbuilder/Pile Driver Diver 5/1/2025 $64.35 $41.74 $106.09
Dockbuilder/Pile Driver Diver 5/1/2026 $66.54 $41.74 $108.28
Dockbuilder/pile driver tender 5/1/2025 $55.23 $37.99 $93.22
Dockbuilder/pile driver tender 5/1/2026 $56.98 $37.99 $94.97
Drywall Finisher 5/1/2025 $40.14 $32.35 $72.49
Electricians 5/1/2024 $69.58 $45.66 $115.24
Electricians 5/1/2025 $70.97 $47.27 $118.24
Elevator Constructor 1/1/2025 $71.85 $45.77 $117.62
Elevator Constructor 1/1/2026 $74.86 $46.86 $121.72
Floor Coverer 5/1/2025 $51.67 $31.69 $83.36
Floor Coverer 5/1/2026 $52.84 $32.86 $85.70
Glazier 5/1/2024 $48.00 $37.50 $85.50
Glazier 5/1/2025 $49.96 $38.34 $88.30
Interior Finish 5/1/2023 $34.60 $25.80 $60.40
Iron Workers (Bridge, Structural, Ornamental, Precast) 7/1/2024 $53.20 $45.01 $98.21
Iron Workers (Riggers) 7/1/2024 $44.64 $34.39 $79.03
Iron Workers (Riggers) 7/1/2025 $44.77 $36.27 $81.04
Iron Workers (Rodman/Reinforcing) 7/1/2024 $47.70 $34.77 $82.47
Iron Workers (Rodman/Reinforcing) 7/1/2025 $47.80 $36.65 $84.45
Laborers (Class 01 - See notes) 5/1/2025 $37.25 $26.10 $63.35
Laborers (Class 02 - See notes) 5/1/2025 $41.00 $27.70 $68.70
Laborers (Class 03 - See notes) 5/1/2025 $37.67 $26.28 $63.95
Laborers (Class 04 - See notes) 5/1/2025 $37.67 $26.28 $63.95
Laborers (Class 05 - See notes) 5/1/2025 $37.25 $26.10 $63.35
Landscape Laborer 5/1/2024 $30.70 $24.23 $54.93
Landscape Laborer 5/1/2025 $32.15 $24.30 $56.45
Marble Finisher 5/1/2025 $41.17 $30.75 $71.92
Marble Mason 5/1/2023 $47.20 $31.95 $79.15
Mason Tender, Cement 5/1/2023 $35.02 $25.98 $61.00
Millwright 5/1/2025 $57.39 $35.81 $93.20
Millwright 5/1/2026 $60.20 $35.81 $96.01
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 3/17/2026 Page 2 of 6
Expiration Date
Hourly Rate Fringe Benefits
Total
Operators (Building, Class 01 - See Notes) 5/1/2025 $54.52 $34.49 $89.01
Operators (Building, Class 01 - See Notes) 5/1/2026 $55.67 $35.34 $91.01
Operators (Building, Class 01A - See Notes) 5/1/2025 $57.52 $35.38 $92.90
Operators (Building, Class 01A - See Notes) 5/1/2026 $58.68 $36.22 $94.90
Operators (Building, Class 02 - See Notes) 5/1/2025 $54.27 $34.42 $88.69
Operators (Building, Class 02 - See Notes) 5/1/2026 $55.43 $35.26 $90.69
Operators (Building, Class 02A - See Notes) 5/1/2025 $57.29 $35.29 $92.58
Operators (Building, Class 02A - See Notes) 5/1/2026 $58.44 $36.14 $94.58
Operators (Building, Class 03 - See Notes) 5/1/2025 $50.18 $33.22 $83.40
Operators (Building, Class 03 - See Notes) 5/1/2026 $51.34 $34.06 $85.40
Operators (Building, Class 04 - See Notes) 5/1/2025 $49.88 $33.13 $83.01
Operators (Building, Class 04 - See Notes) 5/1/2026 $51.04 $33.97 $85.01
Operators (Building, Class 05 - See Notes) 5/1/2025 $48.16 $32.62 $80.78
Operators (Building, Class 05 - See Notes) 5/1/2026 $49.32 $33.46 $82.78
Operators (Building, Class 06 - See Notes) 5/1/2025 $47.17 $32.33 $79.50
Operators (Building, Class 06 - See Notes) 5/1/2026 $48.34 $33.16 $81.50
Operators (Building, Class 07A- See Notes) 5/1/2025 $66.26 $39.55 $105.81
Operators (Building, Class 07A- See Notes) 5/1/2026 $67.73 $40.48 $108.21
Operators (Building, Class 07B- See Notes) 5/1/2025 $65.97 $39.46 $105.43
Operators (Building, Class 07B- See Notes) 5/1/2026 $67.44 $40.39 $107.83
Painters Class 1 (see notes) 5/1/2024 $42.97 $34.11 $77.08
Painters Class 1 (see notes) 5/1/2025 $44.38 $34.55 $78.93
Painters - Line Stripping 12/1/2024 $44.12 $27.91 $72.03
Painters - Line Stripping 12/1/2025 $45.12 $29.41 $74.53
Painters Class 4 (see notes) 5/1/2024 $45.06 $34.11 $79.17
Painters Class 4 (see notes) 5/1/2025 $46.47 $34.55 $81.02
Plasterers 5/1/2024 $39.88 $33.08 $72.96 plumber 5/1/2024 $67.53 $38.31 $105.84 plumber 5/1/2025 $70.53 $39.46 $109.99
Pointers, Caulkers, Cleaners 5/1/2025 $51.35 $31.80 $83.15
Roofers (Composition) 5/1/2024 $44.13 $34.77 $78.90
Roofers (Composition) 5/1/2025 $46.03 $34.77 $80.80
Roofers (Shingle) 5/1/2024 $34.35 $22.20 $56.55
Roofers (Slate & Tile) 5/1/2024 $37.35 $22.20 $59.55
Sheet Metal Workers 5/1/2024 $59.22 $50.56 $109.78
Sheet Metal Workers 5/1/2025 $62.62 $52.17 $114.79
Sign Makers and Hangars 7/15/2024 $32.32 $25.82 $58.14
Sign Makers and Hangars 7/15/2025 $33.48 $26.41 $59.89
Sprinklerfitters 1/1/2023 $62.23 $31.99 $94.22
Sprinklerfitters 5/1/2025 $70.37 $34.85 $105.22
Steamfitters 5/1/2024 $70.32 $43.09 $113.41
Steamfitters 5/1/2025 $72.52 $44.89 $117.41
Stone Masons 5/1/2023 $47.20 $31.95 $79.15
Stone Masons 5/1/2025 $50.00 $32.80 $82.80
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 3/17/2026 Page 3 of 6
Expiration Date
Hourly Rate Fringe Benefits
Total
Terrazzo Finisher 5/1/2023 $43.75 $27.86 $71.61
Terrazzo Finisher 5/1/2025 $45.61 $29.41 $75.02
Terrazzo Grinder 5/1/2023 $44.02 $27.86 $71.88
Terrazzo Grinder 5/1/2025 $45.88 $29.41 $75.29
Terrazzo Mechanics 5/1/2023 $50.26 $29.56 $79.82
Terrazzo Mechanics 5/1/2025 $52.21 $31.26 $83.47
Tile Finisher 5/1/2023 $39.52 $29.30 $68.82
Tile Finisher 5/1/2025 $41.17 $30.75 $71.92
Tile Setter 5/1/2023 $50.26 $29.56 $79.82
Tile Setter 5/1/2025 $52.21 $31.26 $83.47
Truckdriver class 1(see notes) 5/1/2024 $36.79 $22.54 $59.33
Truckdriver class 2 (see notes) 5/1/2024 $36.89 $22.54 $59.43
Window Film / Tint Installer 6/1/2024 $26.37 $14.83 $41.20
Window Film / Tint Installer 6/1/2025 $27.42 $15.13 $42.55
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 3/17/2026 Page 4 of 6
Project: 26-02618 - Heavy/Highway Effective
Expiration Date
Hourly Rate Fringe Benefits
Total
Bricklayer 5/1/2025 $50.00 $32.57 $82.57
Carpenter - Chief of Party (Surveying & Layout) 5/1/2025 $65.96 $30.09 $96.05
Carpenter - Chief of Party (Surveying & Layout) 5/1/2026 $67.52 $30.44 $97.96
Carpenter - Instrument Person (Surveying & Layout) 5/1/2025 $58.39 $29.06 $87.45
Carpenter - Instrument Person (Surveying & Layout) 5/1/2026 $60.09 $29.06 $89.15
Carpenter - Rodman (Surveying & Layout) 5/1/2025 $45.88 $23.19 $69.07
Carpenter - Rodman (Surveying & Layout) 5/1/2026 $46.97 $23.54 $70.51
Carpenter 5/1/2025 $57.36 $30.09 $87.45
Carpenter 5/1/2026 $58.71 $30.44 $89.15
Cement Masons 5/1/2023 $43.20 $32.91 $76.11
Cement Masons 5/1/2025 $46.55 $32.66 $79.21
Dockbuilder, Pile Drivers 5/1/2025 $55.23 $37.99 $93.22
Dockbuilder, Pile Drivers 5/1/2026 $56.98 $37.99 $94.97
Dockbuilder/Pile Driver Diver 5/1/2025 $60.31 $44.97 $105.28
Dockbuilder/Pile Driver Diver 5/1/2026 $61.88 $45.47 $107.35
Dockbuilder/pile driver tender 5/1/2025 $55.23 $37.99 $93.22
Dockbuilder/pile driver tender 5/1/2026 $56.98 $37.99 $94.97
Electric Lineman 6/3/2024 $62.07 $33.96 $96.03
Electric Lineman 6/2/2025 $65.10 $34.45 $99.55
Iron Workers (Bridge, Structural, Ornamental, Precast) 7/1/2024 $53.20 $45.01 $98.21
Iron Workers (Riggers) 7/1/2023 $42.53 $34.14 $76.67
Iron Workers (Rodman/Reinforcing) 7/1/2023 $45.70 $34.77 $80.47
Laborers (Class 01 - See notes) 5/1/2025 $40.20 $27.80 $68.00
Laborers (Class 02 - See notes) 5/1/2025 $40.40 $27.80 $68.20
Laborers (Class 03 - See notes) 5/1/2025 $40.40 $27.80 $68.20
Laborers (Class 04 - See notes) 5/1/2025 $35.00 $27.80 $62.80
Laborers (Class 05 - See notes) 5/1/2025 $41.05 $27.80 $68.85
Laborers (Class 06 - See notes) 5/1/2025 $41.10 $27.80 $68.90
Laborers (Class 07 - See notes) 5/1/2025 $40.95 $27.80 $68.75
Laborers (Class 08 - See notes) 5/1/2025 $40.70 $27.80 $68.50
Laborers (Class 09 - See notes) 5/1/2025 $40.55 $27.80 $68.35
Laborers (Class 10- See notes) 5/1/2025 $40.70 $27.80 $68.50
Laborers (Class 11 -See Notes) 5/1/2025 $40.60 $27.80 $68.40
Laborers (Class 12 -See Notes) 5/1/2025 $42.30 $27.80 $70.10
Laborers (Class 13 -See Notes) 5/1/2025 $44.33 $27.80 $72.13
Laborers (Class 14 -See Notes) 5/1/2025 $40.90 $27.80 $68.70
Laborers Utility (PGW ONLY) (Flagperson) 5/1/2025 $34.07 $19.73 $53.80
Laborers Utility (PGW ONLY) 5/1/2025 $41.10 $19.73 $60.83
Landscape Laborer 5/1/2024 $30.28 $24.05 $54.33
Landscape Laborer 5/1/2025 $31.73 $24.15 $55.88
Millwright 5/1/2025 $57.39 $35.81 $93.20
Millwright 5/1/2026 $60.20 $35.81 $96.01
Operators Class 01 - See Notes (Building, Heavy, Highway)
5/1/2025 $54.52 $34.49 $89.01
Operators Class 01 - See Notes (Building, Heavy, 5/1/2026 $55.67 $35.34 $91.01
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 3/17/2026 Page 5 of 6
Project: 26-02618 - Heavy/Highway Effective
Expiration Date
Hourly Rate Fringe Benefits
Total
Highway)
Operators Class 01a - See Notes (Building, Heavy, Highway)
5/1/2025 $57.52 $35.38 $92.90
Operators Class 01a - See Notes (Building, Heavy, Highway)
5/1/2026 $58.68 $36.22 $94.90
Operators Class 02 - See Notes (Building, Heavy, Highway)
5/1/2025 $54.27 $34.42 $88.69
Operators Class 02 - See Notes (Building, Heavy, Highway)
5/1/2026 $55.43 $35.26 $90.69
Operators Class 02a - See Notes (Building, Heavy, Highway)
5/1/2025 $57.29 $35.29 $92.58
Operators Class 02a - See Notes (Building, Heavy, Highway)
5/1/2026 $58.44 $36.14 $94.58
Operators Class 03 - See Notes (Building, Heavy, Highway)
5/1/2025 $50.18 $33.22 $83.40
Operators Class 03 - See Notes (Building, Heavy, Highway)
5/1/2026 $51.34 $34.06 $85.40
Operators Class 04 - See Notes (Building, Heavy, Highway)
5/1/2025 $49.88 $33.13 $83.01
Operators Class 04 - See Notes (Building, Heavy, Highway)
5/1/2026 $51.04 $33.97 $85.01
Operators Class 05 - See Notes (Building, Heavy, Highway)
5/1/2025 $48.16 $32.62 $80.78
Operators Class 05 - See Notes (Building, Heavy, Highway)
5/1/2026 $49.32 $33.46 $82.78
Operators Class 06 - See Notes (Building, Heavy, Highway)
5/1/2025 $47.17 $32.33 $79.50
Operators Class 06 - See Notes (Building, Heavy, Highway)
5/1/2026 $48.34 $33.16 $81.50
Operators Class 07 (A) - See Notes (Building, Heavy, Highway)
5/1/2025 $66.26 $39.55 $105.81
Operators Class 07 (A) - See Notes (Building, Heavy, Highway)
5/1/2026 $67.73 $40.48 $108.21
Operators Class 07 (B) - See Notes (Building, Heavy, Highway)
5/1/2025 $65.97 $39.46 $105.43
Operators Class 07 (B) - See Notes (Building, Heavy, Highway)
5/1/2026 $67.44 $40.39 $107.83
Painters - Line Stripping 12/1/2024 $44.12 $27.91 $72.03
Painters - Line Stripping 12/1/2025 $45.12 $29.41 $74.53
Painters Class 2 (see notes) 2/1/2025 $50.85 $33.91 $84.76
Painters Class 2 (see notes) 2/1/2026 $51.61 $35.00 $86.61
Painters Class 3 (see notes) 2/1/2025 $61.81 $33.95 $95.76
Painters Class 3 (see notes) 2/1/2026 $62.57 $35.04 $97.61
Pointers, Caulkers, Cleaners 5/1/2025 $51.35 $31.80 $83.15
Steamfitters (Heavy and Highway - Gas Distribution) 5/1/2024 $66.80 $42.93 $109.73
Steamfitters (Heavy and Highway - Gas Distribution) 5/1/2025 $68.89 $44.73 $113.62
Truckdriver class 1(see notes) 5/1/2024 $36.64 $22.54 $59.18
Truckdriver class 2 (see notes) 5/1/2024 $36.74 $22.54 $59.28