About this file

This is a technical specification document (Section 232123) for hydronic pumps to be installed at the Armed Forces Retirement Home Sheridan Building. The specification details requirements for close-coupled, end-suction centrifugal pumps and split-coupled, in-line mounted centrifugal pumps.

The document outlines detailed technical requirements including pump construction specifications, motor requirements, and acceptable manufacturers (Armstrong Pumps, Bell & Gossett, and ITT Corporation). Key requirements include cast iron casings with bronze wear rings, ASTM B584 cast bronze impellers, Type 304 stainless steel pump shafts, and mechanical seals. Motors must be NEMA Premium Efficient with totally enclosed fan-cooled enclosures and integral variable-speed controllers. The specification also covers installation requirements, startup procedures, field quality control testing, and mandates that a factory-authorized service representative must perform alignment service and train owner's maintenance personnel. The document is part of Bid Addendum 2/12/25 for the Sheridan Building renovation project.

View the file

Other files

File Type Posted
Amendment 0006 Solicitation 47PM0325R0002 2025 03 25.pdf PDF
Amendment 0005 RFI Responses 150 - 336 2025 03 18.pdf PDF
Amendment 0005 Solicitation 47PM0325R0002 2025 03 18 (2).pdf PDF
Amendment 0004 Solicitation 47PM0325R0002 2025 03 13.pdf PDF
H103 - CHILLER PLANT.pdf PDF
Amendment 0003 Technical Evaluation Factors-Best Value_ Trade Off 2025 03 04.pdf PDF
Amendment 0003 Solicitation 47PM0325R0002 2025 03 04.pdf PDF
A517 - EXTERIOR PLAN DETAILS.pdf PDF
A516 - EXTERIOR PLAN DETAILS.pdf PDF
087113 - Automatic Door Operator.pdf PDF
079500 - Exterior Expansion Control.pdf PDF
A427 - SPA ROOMS AND LAUNDRY ROOMS.pdf PDF
084113 - Aluminum-Framed Entrances and Storefronts.pdf PDF
A406 - CLINICAL AREAS- NURSE STATIONS - FIRST FLOOR.pdf PDF
AD100A - BASEMENT DEMOLITION PLAN A.pdf PDF
Amendment 0003 Solicitation_GC AFRH 2025 03 04.pdf PDF
236416 FL - Centrifugal Water Chillers- Addendum 3.pdf PDF
AI407 - TYPICAL ELEVATOR LOBBY FINISH PLANS AND ELEVATIONS (FLOORS 2-7).pdf PDF
107113 - Exterior Sun Control Devices.pdf PDF
088700 - Window Film.pdf PDF
AD100B - BASEMENT DEMOLITION PLAN B.pdf PDF
A405 - CLINICAL AREAS-NURSE STATIONS - FIRST FLOOR.pdf PDF
HD103 - CHILLER PLANT DEMO PLAN.pdf PDF
AI408 - TYPICAL NORTH- SOUTH ELEVATOR LOBBY FINISH PLANS (FLOORS 2-7).pdf PDF
A409 - ENLARGED TOILET ROOM PLANS AND ELEVATIONS.pdf PDF
087100 - Door Hardware.pdf PDF
101423.16 - Panel Signage.pdf PDF
A504 - EXTERIOR WALL SECTION DETAILS.pdf PDF
000110 Table of Contents.pdf PDF
H603 - HVAC DETAILS.pdf PDF
AFRH-Sheridan Pre-Bid Addendum 2-12-25.pdf PDF
081416 - Flush Wood Doors.pdf PDF
A601 - DOOR SCHEDULE TYPES DETAILS.pdf PDF
S542 - STRUCTURAL BALCONY ENCLOSURE DETAILS.pdf PDF
A560 - TYPICAL ROOF DETAILS.pdf PDF
A503 - EXTERIOR WALL SECTION DETAILS.pdf PDF
A602 - DOOR SCHEDULE TYPES DETAILS.pdf PDF
S521 - STRUCTURAL ANNEX FRAMING DETAILS.pdf PDF
095000 - Wood Panel Ceiling.pdf PDF
S552 - STRUCTURAL TRASH CHUTE GENERATOR ENCLSOURE BALCONY ENCLOSURE DETAILS.pdf PDF
Amendment 0003 RFI Responses 1-149 2025 03 04.pdf PDF
235700 FL - Heat Exchangers for HVAC.pdf PDF
S401 - STRUCTURAL ROOF FRAMING PARTIAL PLANS.pdf PDF
Amendment 0003 Solicitation 47PM0325R0002 2025 03 04.pdf PDF
H804 - CONTROL DIAGRAMS.pdf PDF
AEWLA22050. Geotechnical Report. 10142022.pdf PDF
A412 - ENLARGED RESIDENT ROOM SHOWERS.pdf PDF
089119 - Fixed Louvers.pdf PDF
A112B - SECOND FLOOR REFLECTED CEILING PLAN B.pdf PDF
AI406 - FIRST FLOOR TOILET ROOM FINISH PLANS AND ELEVATIONS.pdf PDF
Show 40 more

Latest 50 of 90 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Armed Forces Retirement Home Sheridan Building Design Documents | Specifications

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 1

SECTION 232123 - HYDRONIC PUMPS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Close-coupled, end-suction centrifugal pumps.

2. Split-coupled, In-line mounted centrifugal pump.

1.3 DEFINITIONS

A. ECM: Electronically commutated motor.

B. EPDM: Ethylene propylene diene monomer.

C. EPR: Ethylene propylene rubber.

D. FKM: Fluoroelastomer polymer.

E. HI: Hydraulic Institute.

F. NBR: Nitrile rubber or Buna-N.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of pump.

1. Include certified performance curves and rated capacities, operating characteristics, furnished specialties, final impeller dimensions, and accessories for each type of product indicated.

2. Indicate pump's operating point on curves.

B. Shop Drawings: For each pump.

1. Show pump layout and connections.

2. Include setting drawings with templates for installing foundation and anchor bolts and other anchorages.

3. Include diagrams for power, signal, and control wiring.

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 2

1.5 INFORMATIONAL SUBMITTALS

A. Coordination Drawings: Plans, or BIM model, drawn to scale, showing the items described in this Section, and coordinated with all building trades.

B. Seismic Qualification Data: Certificates for pumps, accessories, and components, from manufacturer.

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation.

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

C. Field quality-control reports.

1.6 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For pumps to include in emergency, operation, and maintenance manuals.

1.7 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Mechanical Seals: One mechanical seal(s) for each pump.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. Seismic Performance: Pumps shall withstand the effects of earthquake motions determined in accordance with ASCE/SEI 7.

1. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified and the unit will be fully operational after the seismic event."

2. Component Importance Factor: 1.5.

2.2 CLOSE-COUPLED, END-SUCTION CENTRIFUGAL PUMPS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

http://www.specagent.com/Lookup?ulid=3387

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 3

1. Armstrong Pumps, Inc.

2. Bell & Gossett.

3. ITT Corporation.

B. Source Limitations: Obtain pumps from single source from single manufacturer.

C. Description: Factory-assembled and-tested, centrifugal, overhung-impeller, close-coupled, end-suction pump as defined in HI 1.1-1.2 and HI 1.3; designed for installation with pump and motor shafts mounted horizontally.

D. Pump Construction:

1. Casing: Radially split, cast iron, with replaceable bronze wear rings, drain plug at bottom and air vent at top of volute, threaded gauge tappings at inlet and outlet, and threaded companion-flange connections.

2. Impeller: ASTM B584, cast bronze; statically and dynamically balanced, keyed to shaft, and secured with a locking cap screw. For constant-speed pumps, trim impeller to match specified performance.

3. Pump Shaft Sleeve: Bronze.

4. Pump Stub Shaft: Type 304 stainless steel.

5. Seal: Mechanical seal consisting of carbon rotating ring against a ceramic seat held by a stainless steel spring, and NBR bellows and gasket. Include water slinger on shaft between motor and seal.

E. Motor: Comply with NEMA designation, temperature rating, service factor, and efficiency requirements for motors specified in Section 230513 "Common Motor Requirements for HVAC Equipment."

1. Enclosure: Totally enclosed, fan cooled.

2. NEMA Premium Efficient motors as defined in NEMA MG 1.

3. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load will not require motor to operate in service factor range above 1.0.

4. Controllers, Electrical Devices, and Wiring: Comply with requirements for electrical devices and connections specified in electrical Sections.

5. Single and Variable-speed motors.

6. Provide integral pump motor variable-speed controller.

2.3 SPLIT-COUPLED, IN-LINE CENTRIFUGAL PUMPS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Armstrong Pumps, Inc.

2. Bell & Gossett.

3. ITT Corporation.

B. Source Limitations: Obtain pumps from single source from single manufacturer.

C. Description: Factory-assembled and-tested, centrifugal, overhung-impeller, close-coupled, end-suction pump as defined in HI 1.1-1.2 and HI 1.3; designed for installation with pump and motor shafts mounted horizontally.

D. Pump Construction:

http://www.specagent.com/Lookup?uid=123457150369 http://www.specagent.com/Lookup?uid=123457150369 http://www.specagent.com/Lookup?uid=123457150382 http://www.specagent.com/Lookup?ulid=3387 http://www.specagent.com/Lookup?uid=123457150369 http://www.specagent.com/Lookup?uid=123457150382

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 4

1. Casing: Radially split, cast iron, with replaceable bronze wear rings, drain plug at bottom and air vent at top of volute, threaded gauge tappings at inlet and outlet, and threaded companion-flange connections.

2. Impeller: ASTM A743 Grade CF8 (304 SS).

3. Pump Shaft Sleeve: 416 Stainless Steel.

4. Pump Stub Shaft: Type 416 stainless steel.

5. Seal: Inside flushed seal with EPR bellows, carbon-ceramic faces, stainless steel spring and metal parts.

E. Motor: Comply with NEMA designation, temperature rating, service factor, and efficiency requirements for motors specified in Section 230513 "Common Motor Requirements for HVAC Equipment."

1. Enclosure: Totally enclosed, fan cooled.

2. NEMA Premium Efficient motors as defined in NEMA MG 1.

3. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load will not require motor to operate in service factor range above 1.0.

4. Controllers, Electrical Devices, and Wiring: Comply with requirements for electrical devices and connections specified in electrical Sections.

5. Single and Variable-speed motors.

6. Provide integral pump motor variable-speed controller.

2.4 PUMP SPECIALTY FITTINGS

A. Suction Diffuser:

1. Angle pattern.

2. 175-psig pressure rating, cast-iron body and end cap, pump-inlet fitting.

3. Bronze 16-mesh wire startup and bronze permanent strainers with 3/16-inch.

4. Bronze straightening vanes.

5. Drain plug.

6. Factory-fabricated support.

B. Triple-Duty Valve:

1. Angle or straight pattern.

2. 175-psig pressure rating, cast-iron body, pump-discharge fitting.

3. Valve with multi-turn stem and memory stop to allow valve to be returned to its original position after shutoff.

4. Brass valve disc with EPDM rubber seat.

5. Type 304 stainless steel valve stem.

6. Drain plug and bronze-fitted shutoff, balancing, and check valve features.

7. Brass gauge ports with integral check valve and orifice for flow measurement.

2.5 INTEGRAL PUMP MOTOR VARIABLE-SPEED CONTROLLERS

A. Where specified or scheduled, provide pumps with an integral pump motor speed controller.

1. Motor: Operates as constant- or variable-speed pump with speed regulated by an integrated variable-speed drive.

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 5

2. Integrated Pump Controller: Supports direct communication with the building management system (BMS) with built-in support for the following protocols:

[Modbus RTU] [BACnet? MS/TP] [Metasys N2].

3. Commissioning and pump set up access to pump controls via the following:

a. A web interface (data exchange).

b. A user interface located on the face of speed controller to adjust modes and mode values.

c. An electronic display that reads real-time mode set values, flow, head, speed, and power and that locks out unauthorized adjustment of pump.

4. Provide electronics with "Auto" as factory default but slope of the proportional curve will automatically match the required system curve, constant pressure control (delta-p/c), variable differential pressure control (delta-p/v), constant curve duty (uncontrolled pump), and rpm regulation. RPM (speed) regulation can be accomplished by the following:

a. Manual (via user interface or HTML).

b. Remote via 0 to 10 V dc.

c. Data protocol communications with the BMS.

5. Pump Electronics: Standard with multiple digital inputs and one external digital output to be available for additional mechanical room control and pump status monitoring.

6. Controller: Mounted on or adjacent to the motor. Provide enclosure rated to UL Type 12.

7. Electronically Protected Pumps: Rated for continuous duty and with built-in startup circuit.

Provide overcurrent, line surge and current limit protection, thermal monitoring, heat sink status and over temperature protection.

8. Pump capable of being monitored continuously via integrated Internet link.

9. Integrated pump controller system to have the following features:

a. Controller software shall be capable of sensorless control in variable-volume systems without need for pump-mounted (internal/external) or remotely mounted differential pressure sensor.

b. Integrated Pump Controller Sensorless Control: Operates under Quadratic Pressure Control (QPC) to ensure that head reduction with reducing flow conforms to quadratic control curve.

c. Controller:

1) Minimum head of 40 percent of design duty head.

2) User-adjustable control mode settings and minimum/maximum head set points using built-in programming interface.

d. Controller Integrated Control Software:

1) Capable of controlling pump performance for non-overloading power at every point of operation.

2) Capable of maintaining flow rate data.

2.6 ELECTRONICALLY COMMUTATED MOTOR (ECM)

A. Provide pumps so they are specified or scheduled with ECM.

1. Synchronous, constant torque, ECM with permanent magnet rotor. Rotor magnets to be time-stable, nontoxic ceramic magnets (Sr-Fe).

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 6

2. Driven by a frequency converter with an integrated power factor correction filter.

Conventional induction motors will not be acceptable.

3. Each motor with an integrated variable-frequency drive, tested as one unit by manufacturer.

4. Motor speed adjustable over full range from 0 rpm to maximum scheduled speed.

5. Variable motor speed to be controlled by a 0- to 10 V-dc or 4- to 20-mA input.

6. Integrated motor protection verified by UL to protect the pump against over-

/undervoltage, overtemperature of motor and/or electronics, overcurrent, locked rotor, and dry run (no-load condition).

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine equipment foundations and anchor-bolt locations for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.

B. Examine roughing-in for piping systems to verify actual locations of piping connections before pump installation.

C. Examine foundations and inertia bases for suitable conditions where pumps will be installed.

D. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PUMP INSTALLATION

A. Comply with HI 1.4 and HI 2.4.

B. Install pumps to provide access for periodic maintenance including removing motors, impellers, couplings, and accessories.

C. Independently support pumps and piping so weight of piping is not supported by pumps and weight of pumps is not supported by piping.

D. Automatic Condensate Pump Units: Install units for collecting condensate and extend to open drain.

E. Equipment Mounting:

1. Install base-mounted pumps on cast-in-place concrete equipment bases. Comply with requirements for equipment bases and foundations specified in Section 033000 "Cast-in- Place Concrete."

2. Comply with requirements for vibration isolation and seismic-control devices specified in Section 230548 "Vibration and Seismic Controls for HVAC."

3. Comply with requirements for vibration isolation devices specified in Section 230548.13 "Vibration Controls for HVAC."

3.3 ALIGNMENT

A. Engage a factory-authorized service representative to perform alignment service.

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 7

B. Perform alignment service. When required by manufacturer to maintain warranty coverage, engage a factory-authorized service representative to perform it.

C. Comply with requirements in HI standards for alignment of pump and motor shaft. Add shims to the motor feet and bolt motor to base frame. Do not use grout between motor feet and base frame.

D. Comply with pump and coupling manufacturers' written instructions.

E. After alignment is correct, tighten foundation bolts evenly but not too firmly. Completely fill baseplate with nonshrink, nonmetallic grout while metal blocks and shims or wedges are in place. After grout has cured, fully tighten foundation bolts.

3.4 PIPING CONNECTIONS

A. Where installing piping adjacent to pump, allow space for service and maintenance.

B. Connect piping to pumps. Install valves that are same size as piping connected to pumps.

C. Install suction and discharge pipe sizes equal to or greater than diameter of pump nozzles.

D. Install triple-duty valve on discharge side of pumps.

E. Install suction diffuser and shutoff valve on suction side of pumps.

1. Use startup strainer for initial system startup. Install permanent strainer element before turnover of system to Owner.

F. Install flexible connectors on suction and discharge sides of base-mounted pumps between pump casing and valves.

G. Install pressure gauges on pump suction and discharge or at integral pressure-gauge tapping, or install single gauge with multiple-input selector valve.

H. Install check valve on each condensate pump unit discharge unless unit has a factory-installed check valve.

3.5 ELECTRICAL CONNECTIONS

A. Connect wiring in accordance with Section 260519 "Low-Voltage Electrical Power Conductors and Cables."

B. Ground equipment in accordance with Section 260526 "Grounding and Bonding for Electrical Systems."

C. Install electrical devices furnished by manufacturer, but not factory mounted, in accordance with NFPA 70 and NECA 1.

D. Install nameplate for each electrical connection, indicating electrical equipment designation and circuit number feeding connection.

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 8

1. Nameplate shall be laminated acrylic or melamine plastic signs, as specified in Section 260553 "Identification for Electrical Systems."

2. Nameplate shall be laminated acrylic or melamine plastic signs with a black background and engraved white letters at least 1/2 inch high.

3.6 CONTROL CONNECTIONS

A. Install control and electrical power wiring to field-mounted control devices.

B. Connect control wiring in accordance with Section 260523 "Control-Voltage Electrical Power Cables."

3.7 STARTUP SERVICE

A. Engage a factory-authorized service representative to perform startup service.

1. Complete installation and startup checks in accordance with manufacturer's written instructions.

2. Check piping connections for tightness.

3. Clean strainers on suction piping. Use startup strainer for initial startup.

4. Perform the following startup checks for each pump before starting:

a. Verify bearing lubrication.

b. Verify that pump is free to rotate by hand and that pump for handling hot liquid is free to rotate with pump hot and cold. If pump is bound or drags, do not operate until cause of trouble is determined and corrected.

c. Verify that pump is rotating in correct direction.

5. Prime pump by opening suction valves and closing drains, and prepare pump for operation.

6. Start motor.

7. Open discharge valve slowly.

3.8 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified testing agency to perform tests and inspections.

B. Manufacturer's Field Service: Engage a factory-authorized service representative to test and inspect components, assemblies, and equipment installations, including connections.

C. Perform tests and inspections with the assistance of a factory-authorized service representative.

D. Hydronic pumps will be considered defective if they do not pass tests and inspections.

E. Prepare test and inspection reports.

3.9 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain hydronic pumps.

Bid Addendum 2/12/25

HYDRONIC PUMPS 232123 - 9

END OF SECTION 232123