This is a technical specification section (079500) for exterior expansion control systems as part of renovation work at the Armed Forces Retirement Home's Sheridan Building. The specification details requirements for exterior wall and slab expansion control systems, including roof expansion joints, floor-to-floor joints, and related components.

The document outlines specific product requirements, including Emseal DFR2 roof expansion joints with 2-hour fire rating and ±50% movement capability, WABO ECF-300 flexible bellows with metal flanges, and Emseal RJ0400 floor-to-floor joints rated for seismic movement. Technical requirements include preformed cellular foam construction with silicone sealant faces, detailed submittal requirements for shop drawings and product data, and installation procedures. The specification requires products to be obtained from a single manufacturer, with approved manufacturers including Emseal (basis of design), Construction Specialties Inc., and MM Systems Corporation. Installation requirements specify proper surface preparation, use of manufacturer-recommended adhesives, and protection of completed work during construction.

View the file

Other files

File Type Posted
Amendment 0006 Solicitation 47PM0325R0002 2025 03 25.pdf PDF
Amendment 0005 RFI Responses 150 - 336 2025 03 18.pdf PDF
Amendment 0005 Solicitation 47PM0325R0002 2025 03 18 (2).pdf PDF
Amendment 0004 Solicitation 47PM0325R0002 2025 03 13.pdf PDF
H103 - CHILLER PLANT.pdf PDF
Amendment 0003 Technical Evaluation Factors-Best Value_ Trade Off 2025 03 04.pdf PDF
Amendment 0003 Solicitation 47PM0325R0002 2025 03 04.pdf PDF
A517 - EXTERIOR PLAN DETAILS.pdf PDF
A516 - EXTERIOR PLAN DETAILS.pdf PDF
087113 - Automatic Door Operator.pdf PDF
A427 - SPA ROOMS AND LAUNDRY ROOMS.pdf PDF
084113 - Aluminum-Framed Entrances and Storefronts.pdf PDF
A406 - CLINICAL AREAS- NURSE STATIONS - FIRST FLOOR.pdf PDF
AD100A - BASEMENT DEMOLITION PLAN A.pdf PDF
Amendment 0003 Solicitation_GC AFRH 2025 03 04.pdf PDF
236416 FL - Centrifugal Water Chillers- Addendum 3.pdf PDF
AI407 - TYPICAL ELEVATOR LOBBY FINISH PLANS AND ELEVATIONS (FLOORS 2-7).pdf PDF
107113 - Exterior Sun Control Devices.pdf PDF
088700 - Window Film.pdf PDF
AD100B - BASEMENT DEMOLITION PLAN B.pdf PDF
A405 - CLINICAL AREAS-NURSE STATIONS - FIRST FLOOR.pdf PDF
HD103 - CHILLER PLANT DEMO PLAN.pdf PDF
AI408 - TYPICAL NORTH- SOUTH ELEVATOR LOBBY FINISH PLANS (FLOORS 2-7).pdf PDF
A409 - ENLARGED TOILET ROOM PLANS AND ELEVATIONS.pdf PDF
087100 - Door Hardware.pdf PDF
101423.16 - Panel Signage.pdf PDF
A504 - EXTERIOR WALL SECTION DETAILS.pdf PDF
000110 Table of Contents.pdf PDF
H603 - HVAC DETAILS.pdf PDF
AFRH-Sheridan Pre-Bid Addendum 2-12-25.pdf PDF
081416 - Flush Wood Doors.pdf PDF
A601 - DOOR SCHEDULE TYPES DETAILS.pdf PDF
S542 - STRUCTURAL BALCONY ENCLOSURE DETAILS.pdf PDF
A560 - TYPICAL ROOF DETAILS.pdf PDF
A503 - EXTERIOR WALL SECTION DETAILS.pdf PDF
A602 - DOOR SCHEDULE TYPES DETAILS.pdf PDF
S521 - STRUCTURAL ANNEX FRAMING DETAILS.pdf PDF
095000 - Wood Panel Ceiling.pdf PDF
S552 - STRUCTURAL TRASH CHUTE GENERATOR ENCLSOURE BALCONY ENCLOSURE DETAILS.pdf PDF
Amendment 0003 RFI Responses 1-149 2025 03 04.pdf PDF
235700 FL - Heat Exchangers for HVAC.pdf PDF
S401 - STRUCTURAL ROOF FRAMING PARTIAL PLANS.pdf PDF
Amendment 0003 Solicitation 47PM0325R0002 2025 03 04.pdf PDF
H804 - CONTROL DIAGRAMS.pdf PDF
AEWLA22050. Geotechnical Report. 10142022.pdf PDF
A412 - ENLARGED RESIDENT ROOM SHOWERS.pdf PDF
089119 - Fixed Louvers.pdf PDF
A112B - SECOND FLOOR REFLECTED CEILING PLAN B.pdf PDF
AI406 - FIRST FLOOR TOILET ROOM FINISH PLANS AND ELEVATIONS.pdf PDF
A102B - SECOND FLOOR PLAN B.pdf PDF
Show 40 more

Latest 50 of 90 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Armed Forces Retirement Home Sheridan Building Design Documents | Specifications

Bid Addendum 2/12/25

EXPANSION CONTROL 079500 - 1

SECTION 079500 – EXTERIOR EXPANSION CONTROL

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Exterior wall and slab expansion control systems.

2.

3.

4.

B. Related Requirements:

1. Division 07 Section "Joint Sealants" for preformed joint sealants in non-fire-rated applications.

1.2 ACTION SUBMITTALS

A. Shop Drawings: For each expansion control system specified. Include plans, elevations, sections, details, splices, blockout requirement, attachments to other work, and line diagrams showing entire route of each expansion control system. Where expansion control systems change planes, provide isometric or clearly detailed drawing depicting how components interconnect.

B. Product Schedule: Prepared by or under the supervision of the supplier. Include the following information in tabular form:

1. Manufacturer and model number for each expansion control system.

2. Expansion control system location cross-referenced to Drawings.

3. Nominal joint width.

4. Movement capability.

5. Classification as thermal.

6. Materials, colors, and finishes.

7. Product options.

8. Fire-resistance ratings.

Bid Addendum 2/12/25

EXPANSION CONTROL 079500 - 2

1.3 INFORMATIONAL SUBMITTALS

A. Product Test Reports: For each fire barrier provided as part of an expansion control system, for tests performed by a qualified testing agency.

PART 2 - PRODUCTS

2.1 SYSTEM DESCRIPTION

A. General: Provide expansion control systems of design, basic profile, materials, and operation indicated. Provide units with capability to accommodate variations in adjacent surfaces.

1. Furnish units in longest practicable lengths to minimize field splicing. Install with hairline mitered corners where expansion control systems change direction or abut other materials.

2. Include factory-fabricated closure materials and transition pieces, T-joints, corners, curbs, cross-connections, and other accessories as required to provide continuous expansion control systems.

2.2 EXTERIOR EXPANSION CONTROL SYSTEMS

A. Basis-of-Design Product: Emseal. Subject to compliance with requirements, provide product comparable by one of the following:

1. Construction Specialties, Inc.

2. MM Systems Corporation.

B. Source Limitations: Obtain expansion control systems from single source from single manufacturer.

C. Roof Expansion Joint: Emseal DFR2

1. Design Criteria:

a. Nominal Joint Width: As indicated on Drawings.

b. Movement Capability: -50 percent/+50 percent.

c. Type of Movement: Thermal.

d. Fire-Resistance Rating: 2-Hour.

2. Type: Preformed cellular foam with sealant face.

a. Foam Material: Manufacturer's standard.

b. Sealant Face: Factory applied and cured silicone.

3. Location: As indicated on drawings.

D. Bellows with Metal Flanges: Flexible Bellows. WABO ECF-300 by Watson Bowman

E. Expansion Joint Cap: Fabricated to detail indicated. 032-inch aluminum sheet with continuous hold-down clips. Finish to match roof.

ErnieJoy Cloud

Bid Addendum 2/12/25

EXPANSION CONTROL 079500 - 3

F. Floor-to-Floor: Emseal RJ0400

1. Design Criteria:

a. Nominal Joint Width: 1 inch.

b. Movement Capability: -50 percent/+50 percent.

c. Type of Movement: Seismic.

2. Type: Preformed cellular foam with sealant face.

a. Foam Material: Manufacturer's standard.

b. Sealant Face: Vehicular / Traffic Grade Silicone Surface Seal.

1) Color: UV Stable Gray.

3. Location: Interior slab-on-grade to exterior concrete apron joint at door locations and as indicated on drawings.

2.3 MATERIALS

A. Cellular Foam Seals: Extruded, compressible foam designed to function under compression.

B. Fire Barriers: Any material or material combination, when fire tested after cycling, designated to resist the passage of flame and hot gases through a movement joint and to meet performance criteria for required fire-resistance rating.

C. Accessories: Manufacturer's standard anchors, clips, fasteners, set screws, spacers, and other accessories compatible with material in contact, as indicated or required for complete installations.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine surfaces where expansion control systems will be installed for installation tolerances and other conditions affecting performance of work.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Prepare substrates according to expansion control system manufacturer's written instructions. Coordinate and furnish anchorages, setting drawings, and instructions for installing expansion control systems. Provide fasteners of metal, type, and size to suit type of construction indicated and to provide for secure attachment of expansion control systems.

B. Cast-In Frames: Coordinate and furnish frames to be cast into concrete.

3.3 INSTALLATION

Bid Addendum 2/12/25

EXPANSION CONTROL 079500 - 4

A. Comply with manufacturer's written instructions for storing, handling, and installing expansion control systems and materials unless more stringent requirements are indicated.

B. Foam Seals: Install with adhesive recommended by manufacturer.

1. Apply bead of silicone sealant (matching the factory applied silicone) continuous along the edges of each expansion joint.

C. Terminate exposed ends of expansion control systems with field- or factory-fabricated termination devices.

3.4 PROTECTION

A. Do not remove protective covering until finish work in adjacent areas is complete. When protective covering is removed, clean exposed metal surfaces to comply with manufacturer's written instructions.

B. Protect the installation from damage by work of other Sections. Where necessary due to heavy construction traffic, remove and properly store cover plates or seals and install temporary protection over expansion control systems. Reinstall cover plates or seals prior to Substantial Completion of the Work.

END OF SECTION 079500