About this file

This specification document, Section 072713, details technical requirements for self-adhering, vapor-retarding, modified bituminous sheet air barriers for the Armed Forces Retirement Home Sheridan Building renovation project. The document outlines installation, testing, and quality assurance requirements for a continuous air barrier system that can accommodate building movement while preventing air leakage.

The specification requires a 40-mil thick self-adhering sheet consisting of 36 mils of rubberized asphalt laminated to a 4-mil cross-laminated polyethylene film, with approved products from Carlisle, Grace Construction Products, or Tremco. Key performance requirements include maximum air leakage of 0.04 cfm/sq. ft. at 1.57 lbf/sq. ft pressure difference, minimum tensile strength of 250 psi, and minimum 200% ultimate elongation. The installer must be licensed by the Air Barrier Association of America (ABAA) and follow their Quality Assurance Program. Testing requirements include air-leakage location testing per ASTM E 1186, volume testing per ASTM E 783, and adhesion testing per ASTM D 4541 for every 600 sq. ft. of installed barrier. The specification includes detailed requirements for surface preparation, installation procedures, field quality control, and protection of the completed air barrier system.

View the file

Other files

File Type Posted
Amendment 0006 Solicitation 47PM0325R0002 2025 03 25.pdf PDF
Amendment 0005 RFI Responses 150 - 336 2025 03 18.pdf PDF
Amendment 0005 Solicitation 47PM0325R0002 2025 03 18 (2).pdf PDF
Amendment 0004 Solicitation 47PM0325R0002 2025 03 13.pdf PDF
H103 - CHILLER PLANT.pdf PDF
Amendment 0003 Technical Evaluation Factors-Best Value_ Trade Off 2025 03 04.pdf PDF
Amendment 0003 Solicitation 47PM0325R0002 2025 03 04.pdf PDF
A517 - EXTERIOR PLAN DETAILS.pdf PDF
A516 - EXTERIOR PLAN DETAILS.pdf PDF
087113 - Automatic Door Operator.pdf PDF
079500 - Exterior Expansion Control.pdf PDF
A427 - SPA ROOMS AND LAUNDRY ROOMS.pdf PDF
084113 - Aluminum-Framed Entrances and Storefronts.pdf PDF
A406 - CLINICAL AREAS- NURSE STATIONS - FIRST FLOOR.pdf PDF
AD100A - BASEMENT DEMOLITION PLAN A.pdf PDF
Amendment 0003 Solicitation_GC AFRH 2025 03 04.pdf PDF
236416 FL - Centrifugal Water Chillers- Addendum 3.pdf PDF
AI407 - TYPICAL ELEVATOR LOBBY FINISH PLANS AND ELEVATIONS (FLOORS 2-7).pdf PDF
107113 - Exterior Sun Control Devices.pdf PDF
088700 - Window Film.pdf PDF
AD100B - BASEMENT DEMOLITION PLAN B.pdf PDF
A405 - CLINICAL AREAS-NURSE STATIONS - FIRST FLOOR.pdf PDF
HD103 - CHILLER PLANT DEMO PLAN.pdf PDF
AI408 - TYPICAL NORTH- SOUTH ELEVATOR LOBBY FINISH PLANS (FLOORS 2-7).pdf PDF
A409 - ENLARGED TOILET ROOM PLANS AND ELEVATIONS.pdf PDF
087100 - Door Hardware.pdf PDF
101423.16 - Panel Signage.pdf PDF
A504 - EXTERIOR WALL SECTION DETAILS.pdf PDF
000110 Table of Contents.pdf PDF
H603 - HVAC DETAILS.pdf PDF
AFRH-Sheridan Pre-Bid Addendum 2-12-25.pdf PDF
081416 - Flush Wood Doors.pdf PDF
A601 - DOOR SCHEDULE TYPES DETAILS.pdf PDF
S542 - STRUCTURAL BALCONY ENCLOSURE DETAILS.pdf PDF
A560 - TYPICAL ROOF DETAILS.pdf PDF
A503 - EXTERIOR WALL SECTION DETAILS.pdf PDF
A602 - DOOR SCHEDULE TYPES DETAILS.pdf PDF
S521 - STRUCTURAL ANNEX FRAMING DETAILS.pdf PDF
095000 - Wood Panel Ceiling.pdf PDF
S552 - STRUCTURAL TRASH CHUTE GENERATOR ENCLSOURE BALCONY ENCLOSURE DETAILS.pdf PDF
Amendment 0003 RFI Responses 1-149 2025 03 04.pdf PDF
235700 FL - Heat Exchangers for HVAC.pdf PDF
S401 - STRUCTURAL ROOF FRAMING PARTIAL PLANS.pdf PDF
Amendment 0003 Solicitation 47PM0325R0002 2025 03 04.pdf PDF
H804 - CONTROL DIAGRAMS.pdf PDF
AEWLA22050. Geotechnical Report. 10142022.pdf PDF
A412 - ENLARGED RESIDENT ROOM SHOWERS.pdf PDF
089119 - Fixed Louvers.pdf PDF
A112B - SECOND FLOOR REFLECTED CEILING PLAN B.pdf PDF
AI406 - FIRST FLOOR TOILET ROOM FINISH PLANS AND ELEVATIONS.pdf PDF
Show 40 more

Latest 50 of 90 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Armed Forces Retirement Home Sheridan Building Design Documents | Specifications

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 1

SECTION 072713 - MODIFIED BITUMINOUS SHEET AIR BARRIERS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes self-adhering, vapor-retarding, modified bituminous sheet air barriers.

1.2 DEFINITIONS

A. Air-Barrier Material: A primary element that provides a continuous barrier to the movement of air.

B. Air-Barrier Accessory: A transitional component of the air barrier that provides continuity.

C. Air-Barrier Assembly: The collection of air-barrier materials and accessories applied to an opaque wall, including joints and junctions to abutting construction, to control air movement through the wall.

D. ABAA: Air Barrier Association of America.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Participants: Architect, Contractor, air barrier installer, air barrier manufacturer’s representative, and installers whose work interfaces with or affects air barrier.

a. Include review of penetrations, building deflection joints, and other construction affecting air barrier installation.

b. Review methods, procedures, and construction sequence for air barrier and related construction, including review of manufacturer’s written product specifications and installation instructions.

1) Review requirements for coordination of air barrier with adjacent materials and construction.

c. Review substrate conditions and finishes required to comply with manufacturer’s requirements for installation of air barrier including fastening and flatness of substrate.

2. Air Barrier Manufacturer’s Acceptance: Obtain manufacturer’s acceptance of air barrier for intended use shown on Drawings and of compatibility of air barrier with all materials in contact with air barrier.

3. Agenda:

a. Review air-barrier requirements and installation, special details, mockups, air-leakage and bond testing, air-barrier protection, and work scheduling that covers air barriers.

1) Include review of penetrations, building deflection joints, and other construction affecting air barrier installation.

b. Review methods, procedures, and construction sequence for air barrier and related construction, including review of manufacturer’s written product specifications and installation instructions.

1) Review requirements for coordination of air barrier with adjacent materials and construction.

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 2

c. Review substrate conditions and finishes required to comply with manufacturer’s requirements for installation of air barrier including fastening and flatness of substrate.

4. Air Barrier Manufacturer’s Acceptance: Obtain manufacturer’s acceptance of air barrier for intended use shown on Drawings and of compatibility of air barrier with all materials in contact with air barrier.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include manufacturer's written instructions for evaluating, preparing, and treating each substrate;

technical data; and tested physical and performance properties of products.

B. Sustainable Design Submittals:

1. Product Data: For coatings, indicating VOC content.

2. Laboratory Test Reports: For coatings, indicating compliance with requirements for low-emitting materials.

C. Shop Drawings: For air-barrier assemblies.

1. Show locations and extent of air barrier materials, accessories, and assemblies specific to Project conditions.

2. Include details for substrate joints and cracks, counterflashing strips, penetrations, inside and outside corners, terminations, and tie-ins with adjoining construction.

3. Include details of interfaces with other materials that form part of air barrier including, but not limited to, the following as applicable to this Project:

a. Connection of air barrier in walls to roof membrane.

b. Connection of air barrier in walls to air barrier in foundation.

c. Application of air barrier to seismic and expansion joints.

d. Application of air barrier to openings and penetrations by windows, storefront framing, curtain wall framing, door frames, piping, conduit, ducts, masonry ties, screws, bolts, and similar components and penetrations.

e. Application of air barrier to precast concrete and other types of exterior wall construction.

D. Samples: Submit minimum 3-inch by 4-inch (75 mm by 100 mm) samples of each air barrier material, clearly labeled to indicate material and use in air barrier system.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer. Include list of ABAA-certified installers and supervisors employed by Installer, who work on Project.

B. Product Certificates: From air-barrier manufacturer, certifying compatibility of air barriers and accessory materials with Project materials that connect to or that come in contact with air barrier.

1. Submit evidence that Installer is currently accredited under ABAA Quality Assurance Program, including accreditation number for ABAA Certified Installers.

C. Certifications

1. Product Test Reports: For each air-barrier assembly, for tests performed by a qualified testing agency.

2. Acceptance of Materials: Submit document from air-barrier manufacturer certifying acceptance of materials proposed for use with air barrier that are not specified in this Section.

http://www.arcomnet.com/sustainable_design.aspx?topic=125

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 3

3. Substrate Compatibility: Submit document from air-barrier manufacturer certifying that air barrier system materials used to adhere air barrier to substrate are chemically compatible.

4. ABAA Certification: Submit evidence that air barrier system complies with requirements of ABAA Quality Assurance program specified in Quality Assurance article in this Section.

D. Field Quality-Control Reports: Submit test results from testing specified in Field Quality Control article in Part 3 of this Section.

E. ABAA QAP Report: Submit copy of ABAA Quality Assurance Program Report.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer.

1. Installer shall be licensed by ABAA according to ABAA's Quality Assurance Program and shall employ ABAA-certified installers and supervisors on Project. Refer to ABAA web site for current listing of ABAA accredited installers.

1.7 PRECONSTRUCTION TESTING

A. Preconstruction Testing Service: Owner will engage a qualified testing agency to perform preconstruction testing on field mockups.

B. Mockup Testing: Air-barrier assemblies shall comply with performance requirements indicated, as evidenced by reports based on mockup testing by a qualified testing agency.

1. Air-Leakage-Location Testing: Mockups will be tested for evidence of air leakage according to ASTM E 1186, chamber pressurization or depressurization with smoke tracers ASTM E 1186, chamber depressurization with detection liquids.

2. Air-Leakage-Volume Testing: Mockups will be tested for air-leakage rate according to ASTM E 783.

3. Quantitative Water-Leakage Testing: Test mockups for air leakage according to ASTM E 1105.

4. Adhesion Testing: Mockups will be tested for required air-barrier adhesion to substrate according to

ASTM D 4541.

5. Notify Architect ten days in advance of the dates and times when mockups will be tested.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Remove and replace liquid materials that cannot be applied within their stated shelf life.

B. Protect stored materials from direct sunlight.

1.9 FIELD CONDITIONS

A. Environmental Limitations: Apply air barrier within the range of ambient and substrate temperatures recommended in writing by air-barrier manufacturer.

1. Protect substrates from environmental conditions that affect air-barrier performance.

2. Do not apply air barrier to a damp or wet substrate or during snow, rain, fog, or mist.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Source Limitations: Obtain primary air-barrier materials and air-barrier accessories from single source from single manufacturer.

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 4

2.2 PERFORMANCE REQUIREMENTS

A. Air-Barrier Performance: Air-barrier assembly and seals with adjacent construction shall be capable of performing as a continuous air barrier and as a liquid-water drainage plane flashed to discharge to the exterior incidental condensation or water penetration. Air-barrier assemblies shall be capable of accommodating substrate movement and of sealing substrate expansion and control joints, construction material changes, penetrations, tie-ins to installed waterproofing, and transitions at perimeter conditions without deterioration and air leakage exceeding specified limits.

1. Movement/Control Joints: Provide air barrier assembly capable of accommodating movements of building and building materials, including providing expansion and control joints and applicable accessories required to accommodate these movements.

a. Provide air barrier assembly capable of withstanding combined design wind, fan, and stack pressures, positive and negative, on building envelope without damage or displacement and transferring loads to structure.

b. Provide air barrier assembly materials that do not displace adjacent materials and air barrier assembly materials under full load.

c. Provide air barrier assembly joined in airtight and flexible manner to air barrier materials incorporated into adjacent construction and that allows relative movement of assemblies due to thermal and moisture variations, creep, and anticipated seismic movement.

2. Connections to Adjacent Materials: Provide connections to adjacent materials that prevent air leakage at following locations:

a. Foundation and walls, including penetrations, ties and anchors.

b. Walls, windows, curtain walls, storefronts, louvers and doors.

c. Different assemblies and fixed openings within those assemblies.

d. Wall and roof connections.

e. Floors/soffits over unconditioned space.

f. Walls, floor and roof across construction, control and expansion joints.

g. Walls, floors and roof to utility, pipe and duct penetrations.

h. Seismic and expansion joints.

i. All other potential air leakage pathways in building envelope.

B. Air-Barrier Assembly Air Leakage: Maximum 0.04 cfm/sq. ft. of surface area at 1.57 lbf/sq. ft. (0.2 L/s x

sq. m of surface area at 75 Pa), when tested according to ASTM E 2357.

2.3 SELF-ADHERING SHEET AIR BARRIER

A. Modified Bituminous Sheet: 40-mil- (1.0-mm-) thick, self-adhering sheet consisting of 36 mils (0.9 mm) of rubberized asphalt laminated to a 4-mil- (0.1-mm-) thick, cross-laminated polyethylene film with release liner on adhesive side.

1. Products: Subject to compliance with requirements, provide one of the following:

a. Carlisle Coatings & Waterproofing Inc; CCW-705 HT

b. Grace Construction Products; W.R. Grace & Co. -- Conn.; Perm-A-Barrier HighTemperature

Wall Membrane.

c. Tremco Incorporated; ExoAir 110 HT.

2. Physical and Performance Properties:

a. Air Permeance: Maximum 0.004 cfm/sq. ft. of surface area at 1.57-lbf/sq. ft. (0.02 L/s x

sq. m of surface area at 75-Pa) pressure difference; ASTM E 2178.

b. Tensile Strength: Minimum 250 psi (1.7 MPa); ASTM D 412, Die C.

c. Ultimate Elongation: Minimum 200; ASTM D 412, Die C.

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 5

d. Puncture Resistance: Minimum 50 lbf (180 N); ASTM E 154/E 154M.

e. Water Absorption: Maximum 0.15 percent weight gain after 48-hour immersion at 70 deg F

(21 deg C); ASTM D 570.

f. Vapor Permeance: Maximum 0.1 perm (5.8 ng/Pa x s x sq. m); ASTM E 96/E 96M, Desiccant Method.

g. Adhesion to Substrate: Minimum 16 lbf/sq. in. (110 kPa) when tested according to

ASTM D 4541 as modified by ABAA.

h. Fire Propagation Characteristics: Passes NFPA 285 testing as part of an approved assembly.

i. UV Resistance: Can be exposed to sunlight for 60 days according to manufacturer's written instructions.

2.4 ACCESSORY MATERIALS

A. Requirement: Provide primers, transition strips, termination strips, joint sealants, counterflashing strips, flashing sheets and metal termination bars, termination mastic, substrate patching materials, adhesives, tapes, foam sealants, lap sealants, and other accessory materials that are recommended in writing by air-barrier manufacturer to produce a complete air-barrier assembly and that are compatible with primary air-barrier material and adjacent construction to which they may seal.

B. Primer: Liquid solvent-borne primer recommended for substrate by air-barrier material manufacturer.

1. VOC Content: 250 g/L or less.

2. Low-Emitting Materials: Interior coatings shall comply with the testing and product requirements of the California Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

C. Stainless-Steel Sheet: ASTM A 240/A 240M, Type 304, 0.0187 inch (0.5 mm) thick, and Series 300 stainless-steel fasteners.

D. Membrane Strips: Manufacturer standard peel/stick strips for sealing of fasteners at exterior wall.

E. Preformed Silicone Extrusion: Manufacturer's standard system consisting of cured low-modulus silicone extrusion, sized to fit opening widths, with a single-component, neutral-curing, Class 100/50 (low-modulus) silicone sealant for bonding extrusions to substrates.

1. Products: Subject to compliance with requirements, provide one of the following:

a. Pecora Corporation; Sil-Span.

b. Tremco Incorporated; Spectrem Simple Seal.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.

1. Verify that substrates are sound and free of oil, grease, dirt, excess mortar, or other contaminants.

2. Verify that substrates have cured and aged for minimum time recommended in writing by air-barrier manufacturer.

3. Verify that masonry joints are flush and completely filled with mortar.

http://www.arcomnet.com/sustainable_design.aspx?topic=280 ErnieJoy Cloud

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 6

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 SURFACE PREPARATION

A. Clean, prepare, treat, fill, and seal substrate and joints and cracks in substrate according to manufacturer's written instructions and details. Provide clean, dust-free, and dry substrate for air-barrier application.

B. Mask off adjoining surfaces not covered by air barrier to prevent spillage and overspray affecting other construction.

C. Remove grease, oil, bitumen, form-release agents, paints, curing compounds, and other penetrating contaminants or film-forming coatings from concrete.

D. Remove fins, ridges, mortar, and other projections and fill honeycomb, aggregate pockets, holes, and other voids in concrete with substrate-patching membrane.

E. Remove excess mortar from masonry ties, shelf angles, and other obstructions.

F. At changes in substrate plane, apply sealant or termination mastic beads at sharp corners and edges to form a smooth transition from one plane to another.

G. Cover gaps in substrate plane and form a smooth transition from one substrate plane to another with stainless-steel sheet mechanically fastened to structural framing to provide continuous support for air barrier.

H. Bridge expansion joints and discontinuous wall-to-wall, deck-to-wall, and deck-to-deck joints with air-barrier accessory material that accommodates joint movement according to manufacturer's written instructions and details.

3.3 INSTALLATION

A. Install materials according to air-barrier manufacturer's written instructions and details and according to recommendations in ASTM D 6135 to form a seal with adjacent construction and ensure continuity of air and water barrier.

1. When ambient and substrate temperatures range between 25 and 40 deg F (minus 4 and plus 5 deg C), install self-adhering, modified bituminous air-barrier sheet produced for low-temperature application. Do not install low-temperature sheet if ambient or substrate temperature is higher than 60 deg F (16 deg C).

2. Unless manufacturer recommends in writing against priming, apply primer to substrates at required rate and allow it to dry.

B. Prepare, treat, and seal inside and outside corners and vertical and horizontal surfaces at terminations and penetrations with termination mastic and according to ASTM D 6135.

C. Apply primer to substrates at required rate and allow it to dry. Limit priming to areas that will be covered by air-barrier sheet on same day. Reprime areas exposed for more than 24 hours.

D. Apply and firmly adhere air-barrier sheets over area to receive air barrier. Accurately align sheets and maintain uniform 2-1/2-inch- (64-mm-) minimum lap widths and end laps. Overlap and seal seams, and stagger end laps to ensure airtight installation.

1. Apply sheets in a shingled manner to shed water.

2. Roll sheets firmly to enhance adhesion to substrate.

E. Apply continuous air-barrier sheets over accessory strips bridging substrate cracks, construction, and contraction joints.

F. CMU: Install air-barrier sheet horizontally against the CMU beginning at base of wall. Align top edge of air-barrier sheet immediately below protruding masonry ties or joint reinforcement or ties, and firmly adhere in place.

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 7

1. Overlap horizontally adjacent sheets a minimum of 2 inches (50 mm) and roll seams.

2. Apply overlapping sheets with bottom edge slit to fit around masonry reinforcing or ties. Roll firmly into place.

3. Seal around masonry reinforcing or ties and penetrations with termination mastic.

4. Continue the sheet into all openings in the wall, such as doors and windows, and terminate at points to maintain an airtight barrier that is not visible from interior.

G. Seal top of through-wall flashings to air-barrier sheet with an additional 6-inch- (150-mm-) wide, transition strip.

H. Seal exposed edges of sheet at seams, cuts, penetrations, and terminations not concealed by metal counterflashings or ending in reglets with termination mastic.

I. Install air-barrier sheet and accessory materials to form a seal with adjacent construction and to maintain a continuous air barrier.

1. Coordinate air-barrier installation with installation of roofing membrane and base flashing to ensure continuity of air barrier with roofing membrane.

2. Install transition strip on roofing membrane or base flashing so that a minimum of 3 inches (75 mm) of coverage is achieved over each substrate.

J. Connect and seal exterior wall air-barrier sheet continuously to roofing-membrane air barrier, concrete below-grade structures, floor-to-floor construction, exterior glazing and window systems, glazed curtain-wall systems, storefront systems, exterior louvers, exterior door framing, and other construction used in exterior wall openings, using accessory materials.

K. At end of each working day, seal top edge of air-barrier material to substrate with termination mastic.

L. Apply joint sealants forming part of air-barrier assembly within manufacturer's recommended application temperature ranges. Consult manufacturer when sealant cannot be applied within these temperature ranges.

M. Wall Openings: Prime concealed, perimeter frame surfaces of windows and doors. Apply transition strip so that a minimum of 3 inches (75 mm) of coverage is achieved over each substrate. Maintain 3 inches (75

mm) of contact over firm bearing to perimeter frames, with not less than 1 inch (25 mm) of full contact.

1. Transition Strip: Roll firmly to enhance adhesion.

2. Preformed Silicone Extrusion: Set in full bed of silicone sealant applied to walls, frame, and air-barrier material.

3. Refer to Division 08 sections for entrances and storefronts and curtain walls for transition assemblies for concealed perimeter frame surfaces for entrances and storefronts and curtain walls.

N. Fill gaps in perimeter frame surfaces of windows doors, and miscellaneous penetrations of air-barrier material with foam sealant.

O. Repair punctures, voids, and deficient lapped seams in air barrier. Slit and flatten fishmouths and blisters.

Patch with air-barrier sheet extending 6 inches (150 mm) beyond repaired areas in all directions.

P. Do not cover air barrier until it has been tested and inspected by testing agency.

Q. Correct deficiencies in or remove air barrier that does not comply with requirements; repair substrates and reapply air-barrier components.

3.4 FIELD QUALITY CONTROL

A. ABAA Quality Assurance Program: Perform examinations, preparation, installation, testing, and inspections under ABAA's Quality Assurance Program.

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 8

B. Testing Agency: Owner will engage a qualified testing agency to perform tests and inspections.

1. Cooperate with Owner’s testing agency, allowing Owner’s testing agency access to work areas and staging and notifying Owner’s testing agency in writing of schedule for Work of this Section to allow sufficient time for testing and inspection by Owner’s testing agency. Do not cover Work of this section until testing and inspection by Owner’s testing agency has been completed and accepted.

C. ABAA Installer Testing and Audits: Cooperate with ABAA testing agency, allowing ABAA testing agency access to work areas and staging and notifying ABAA testing agency in writing of schedule for Work of this Section to allow sufficient time for testing and inspection by ABAA testing agency. Do not cover Work of this section until testing and inspection by ABAA testing agency has been completed and accepted.

1. Cost of ABAA Testing and Audit: Arrange and pay for site inspections and testing by ABAA to verify conformance of air barrier with specified requirements, air barrier system manufacturer’s installation instructions, and ABAA Site Quality Assurance Program.

2. Extent of Audit and Testing: Provide audit and testing as follows:

a. Up to 10,000 sq. ft. (929 sq. m.):....................................................1 audit/test.

b. 10,001 to 35,000 sq. ft. (929.1 to 3251.6 sq. m): ...........................2 audits/tests.

c. 35,001 to 75,000 sq. ft. (3251.7 to 6967.7 sq. m.): ........................3 audits/tests.

d. 75,001 to 125,000 sq. ft. (6967.78 to 11612.8 sq. m.): ..................4 audits/tests.

e. 125,001 to 200,000 sq. ft (11612.9 to 18580.6 sq. m.): .................5 audits/tests.

f. 200,001 sq. ft. (18580.7 sq. m.) and over: .....................................6 audits/tests.

3. Reporting: Submit written audit/testing reports to Architect within 10 working days of date inspection and testing performed.

4. Correction: If audit and testing reveals defects, promptly remove and replace defective air barriers at no additional cost to Owner.

D. Inspections: Air-barrier materials, accessories, and installation are subject to inspection for compliance with requirements. Inspections may include the following:

1. Continuity of air-barrier system has been achieved throughout the building envelope with no gaps or holes.

2. Continuous structural support of air-barrier system has been provided.

3. Masonry and concrete surfaces are smooth, clean, and free of cavities, protrusions, and mortar droppings.

4. Site conditions for application temperature and dryness of substrates have been maintained.

5. Maximum exposure time of materials to UV deterioration has not been exceeded.

6. Surfaces have been primed.

7. Laps in sheet materials have complied with the minimum requirements and have been shingled in the correct direction (or mastic applied on exposed edges), with no fishmouths.

8. Termination mastic has been applied on cut edges.

9. Air barrier has been firmly adhered to substrate.

10. Compatible materials have been used.

11. Transitions at changes in direction and structural support at gaps have been provided.

12. Connections between assemblies (air barrier and sealants) have complied with requirements for cleanliness, surface preparation and priming, structural support, integrity, and continuity of seal.

13. All penetrations have been sealed.

E. Tests: As determined by testing agency from among the following tests:

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 9

1. Air-Leakage-Location Testing: Air-barrier assemblies will be tested for evidence of air leakage according to ASTM E 1186, chamber pressurization or depressurization with smoke tracers.

2. Air-Leakage-Volume Testing: Air-barrier assemblies will be tested for air-leakage rate according to

ASTM E 783.

3. Adhesion Testing: Air-barrier assemblies will be tested for required adhesion to substrate according to ASTM D 4541 for each 600 sq. ft. (56 sq. m) of installed air barrier or part thereof.

F. Air barriers will be considered defective if they do not pass tests and inspections.

1. Apply additional air-barrier material, according to manufacturer's written instructions, where inspection results indicate insufficient thickness.

2. Remove and replace deficient air-barrier components for retesting as specified above.

G. Repair damage to air barriers caused by testing; follow manufacturer's written instructions.

H. Prepare test and inspection reports.

3.5 CLEANING AND PROTECTION

A. Protect air-barrier system from damage during application and remainder of construction period, according to manufacturer's written instructions.

1. Protect air barrier from exposure to UV light and harmful weather exposure as recommended in writing by manufacturer. If exposed to these conditions for longer than recommended, remove and replace air barrier or install additional, full-thickness, air-barrier application after repairing and preparing the overexposed materials according to air-barrier manufacturer's written instructions.

2. Protect air barrier from contact with incompatible materials and sealants not approved by air-barrier manufacturer.

B. Clean spills, stains, and soiling from construction that would be exposed in the completed Work, using cleaning agents and procedures recommended in writing by manufacturer of affected construction.

END OF SECTION 072713

THIS PAGE INTENTIONALLY LEFT BLANK

Bid Addendum 2/12/25

MODIFIED BITUMINOUS SHEET AIR BARRIERS 072713 - 10

PART 1 - GENERAL
1.1 SUMMARY
A. Section includes self-adhering, vapor-retarding, modified bituminous sheet air barriers.
1.2 DEFINITIONS
A. Air-Barrier Material: A primary element that provides a continuous barrier to the movement of air.
B. Air-Barrier Accessory: A transitional component of the air barrier that provides continuity.
C. Air-Barrier Assembly: The collection of air-barrier materials and accessories applied to an opaque wall, including joints and junctions to abutting construction, to control air movement through the wall.
D. ABAA: Air Barrier Association of America.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Sustainable Design Submittals:
C. Shop Drawings: For air-barrier assemblies.
D. Samples: Submit minimum 3-inch by 4-inch (75 mm by 100 mm) samples of each air barrier material, clearly labeled to indicate material and use in air barrier system.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For Installer. Include list of ABAA-certified installers and supervisors employed by Installer, who work on Project.
B. Product Certificates: From air-barrier manufacturer, certifying compatibility of air barriers and accessory materials with Project materials that connect to or that come in contact with air barrier.
C. Certifications
D. Field Quality-Control Reports: Submit test results from testing specified in Field Quality Control article in Part 3 of this Section.
E. ABAA QAP Report: Submit copy of ABAA Quality Assurance Program Report.
1.6 QUALITY ASSURANCE
A. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer.
1.7 PRECONSTRUCTION TESTING
A. Preconstruction Testing Service: Owner will engage a qualified testing agency to perform preconstruction testing on field mockups.
B. Mockup Testing: Air-barrier assemblies shall comply with performance requirements indicated, as evidenced by reports based on mockup testing by a qualified testing agency.
1.8 DELIVERY, STORAGE, AND HANDLING
A. Remove and replace liquid materials that cannot be applied within their stated shelf life.
B. Protect stored materials from direct sunlight.
1.9 FIELD CONDITIONS
A. Environmental Limitations: Apply air barrier within the range of ambient and substrate temperatures recommended in writing by air-barrier manufacturer.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Source Limitations: Obtain primary air-barrier materials and air-barrier accessories from single source from single manufacturer.
2.2 PERFORMANCE REQUIREMENTS
A. Air-Barrier Performance: Air-barrier assembly and seals with adjacent construction shall be capable of performing as a continuous air barrier and as a liquid-water drainage plane flashed to discharge to the exterior incidental condensation or water penetration. Air-barrier assemblies shall be capable of accommodating substrate movement and of sealing substrate expansion and control joints, construction material changes, penetrations, tie-ins to installed waterproofing, and transitions at perimeter conditions without deterioration and air leakage exceeding specified limits.
B. Air-Barrier Assembly Air Leakage: Maximum 0.04 cfm/sq. ft. of surface area at 1.57 lbf/sq. ft. (0.2 L/s x sq. m of surface area at 75 Pa), when tested according to ASTM E 2357.
2.3 SELF-ADHERING SHEET AIR BARRIER
A. Modified Bituminous Sheet: 40-mil- (1.0-mm-) thick, self-adhering sheet consisting of 36 mils (0.9 mm) of rubberized asphalt laminated to a 4-mil- (0.1-mm-) thick, cross-laminated polyethylene film with release liner on adhesive side.
2.4 ACCESSORY MATERIALS
A. Requirement: Provide primers, transition strips, termination strips, joint sealants, counterflashing strips, flashing sheets and metal termination bars, termination mastic, substrate patching materials, adhesives, tapes, foam sealants, lap sealants, and other accessory materials that are recommended in writing by air-barrier manufacturer to produce a complete air-barrier assembly and that are compatible with primary air-barrier material and adjacent construction to which they may seal.
B. Primer: Liquid solvent-borne primer recommended for substrate by air-barrier material manufacturer.
C. Stainless-Steel Sheet: ASTM A 240/A 240M, Type 304, 0.0187 inch (0.5 mm) thick, and Series 300 stainless-steel fasteners.
D. Membrane Strips: Manufacturer standard peel/stick strips for sealing of fasteners at exterior wall.
E. Preformed Silicone Extrusion: Manufacturer's standard system consisting of cured low-modulus silicone extrusion, sized to fit opening widths, with a single-component, neutral-curing, Class 100/50 (low-modulus) silicone sealant for bonding extrusions to substrates.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 SURFACE PREPARATION
A. Clean, prepare, treat, fill, and seal substrate and joints and cracks in substrate according to manufacturer's written instructions and details. Provide clean, dust-free, and dry substrate for air-barrier application.
B. Mask off adjoining surfaces not covered by air barrier to prevent spillage and overspray affecting other construction.
C. Remove grease, oil, bitumen, form-release agents, paints, curing compounds, and other penetrating contaminants or film-forming coatings from concrete.
D. Remove fins, ridges, mortar, and other projections and fill honeycomb, aggregate pockets, holes, and other voids in concrete with substrate-patching membrane.
E. Remove excess mortar from masonry ties, shelf angles, and other obstructions.
F. At changes in substrate plane, apply sealant or termination mastic beads at sharp corners and edges to form a smooth transition from one plane to another.
G. Cover gaps in substrate plane and form a smooth transition from one substrate plane to another with stainless-steel sheet mechanically fastened to structural framing to provide continuous support for air barrier.
H. Bridge expansion joints and discontinuous wall-to-wall, deck-to-wall, and deck-to-deck joints with air-barrier accessory material that accommodates joint movement according to manufacturer's written instructions and details.
3.3 INSTALLATION
A. Install materials according to air-barrier manufacturer's written instructions and details and according to recommendations in ASTM D 6135 to form a seal with adjacent construction and ensure continuity of air and water barrier.
B. Prepare, treat, and seal inside and outside corners and vertical and horizontal surfaces at terminations and penetrations with termination mastic and according to ASTM D 6135.
C. Apply primer to substrates at required rate and allow it to dry. Limit priming to areas that will be covered by air-barrier sheet on same day. Reprime areas exposed for more than 24 hours.
D. Apply and firmly adhere air-barrier sheets over area to receive air barrier. Accurately align sheets and maintain uniform 2-1/2-inch- (64-mm-) minimum lap widths and end laps. Overlap and seal seams, and stagger end laps to ensure airtight installation.
E. Apply continuous air-barrier sheets over accessory strips bridging substrate cracks, construction, and contraction joints.
F. CMU: Install air-barrier sheet horizontally against the CMU beginning at base of wall. Align top edge of air-barrier sheet immediately below protruding masonry ties or joint reinforcement or ties, and firmly adhere in place.
G. Seal top of through-wall flashings to air-barrier sheet with an additional 6-inch- (150-mm-) wide, transition strip.
H. Seal exposed edges of sheet at seams, cuts, penetrations, and terminations not concealed by metal counterflashings or ending in reglets with termination mastic.
I. Install air-barrier sheet and accessory materials to form a seal with adjacent construction and to maintain a continuous air barrier.
J. Connect and seal exterior wall air-barrier sheet continuously to roofing-membrane air barrier, concrete below-grade structures, floor-to-floor construction, exterior glazing and window systems, glazed curtain-wall systems, storefront systems, exterior louvers, exterior door framing, and other construction used in exterior wall openings, using accessory materials.
K. At end of each working day, seal top edge of air-barrier material to substrate with termination mastic.
L. Apply joint sealants forming part of air-barrier assembly within manufacturer's recommended application temperature ranges. Consult manufacturer when sealant cannot be applied within these temperature ranges.
M. Wall Openings: Prime concealed, perimeter frame surfaces of windows and doors. Apply transition strip so that a minimum of 3 inches (75 mm) of coverage is achieved over each substrate. Maintain 3 inches (75 mm) of contact over firm bearing to perimeter frames, with not less than 1 inch (25 mm) of full contact.
N. Fill gaps in perimeter frame surfaces of windows doors, and miscellaneous penetrations of air-barrier material with foam sealant.
O. Repair punctures, voids, and deficient lapped seams in air barrier. Slit and flatten fishmouths and blisters. Patch with air-barrier sheet extending 6 inches (150 mm) beyond repaired areas in all directions.
P. Do not cover air barrier until it has been tested and inspected by testing agency.
Q. Correct deficiencies in or remove air barrier that does not comply with requirements; repair substrates and reapply air-barrier components.
3.4 FIELD QUALITY CONTROL
A. ABAA Quality Assurance Program: Perform examinations, preparation, installation, testing, and inspections under ABAA's Quality Assurance Program.
B. Testing Agency: Owner will engage a qualified testing agency to perform tests and inspections.
C. ABAA Installer Testing and Audits: Cooperate with ABAA testing agency, allowing ABAA testing agency access to work areas and staging and notifying ABAA testing agency in writing of schedule for Work of this Section to allow sufficient time for testing and inspection by ABAA testing agency. Do not cover Work of this section until testing and inspection by ABAA testing agency has been completed and accepted.
D. Inspections: Air-barrier materials, accessories, and installation are subject to inspection for compliance with requirements. Inspections may include the following:
E. Tests: As determined by testing agency from among the following tests:
F. Air barriers will be considered defective if they do not pass tests and inspections.
G. Repair damage to air barriers caused by testing; follow manufacturer's written instructions.
H. Prepare test and inspection reports.
3.5 CLEANING AND PROTECTION
A. Protect air-barrier system from damage during application and remainder of construction period, according to manufacturer's written instructions.
B. Clean spills, stains, and soiling from construction that would be exposed in the completed Work, using cleaning agents and procedures recommended in writing by manufacturer of affected construction.