41-Sec 01 55 26 - TRAFFIC REGULATION.pdf

PDF 138 KB Posted

Attached to
Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 State and local contract opportunity
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Traffic Regulation specification document for Upper Makefield Township's 2026 Road Program, establishing the contractor's obligations for maintaining safe and efficient traffic flow during road construction activities. The contractor must furnish, erect, and maintain traffic control infrastructure including cones, drums, barricades, flashing lights, directional signs, and trained flagpersons as required by state and local permit requirements. The specification encompasses traffic control planning, advance notification procedures, construction parking controls, flagperson deployment, flares and lights, haul route coordination, and traffic sign and signal installation. The contractor is responsible for notifying the local Police Department at least ten days in advance of traffic restrictions, and must notify the Police, Fire Company, School District, Ambulance Service, and affected residents at least three days before restricting traffic. At least one traffic lane must remain open during non-working periods, and emergency vehicles must be allowed passage at all times.

The specification requires the contractor to provide notification to property owners and residents three days prior to milling and paving operations, specifying dates and times for parking restrictions, with the contractor bearing full responsibility for towing costs if proper notice is not provided. The contractor must maintain access to adjacent property driveways and entrances during non-working periods and to the maximum extent feasible during work hours, potentially requiring the use of steel plates or decking across trenches. Additionally, the contractor must install safe decking over open trenches during non-work periods and is prohibited from allowing traffic on milled surfaces for more than six calendar days, requiring installation of the bituminous wearing course within seven calendar days of milling operations. All traffic control equipment and devices must be removed upon completion, with post settings removed to a depth of two feet, and any installation damage must be repaired.

View the file

Other files for this state and local contract opportunity

Other files attached to Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11, newest first.
File Type Posted
2-6715-11 CONTRACT DRAWINGS.pdf PDF
1-6715-11 CONTRACT DOCUMENTS.pdf PDF
52-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
13-Doc 00 62 16-CERTIFICATE OF INSURANCE.pdf PDF
44-Sec 32 01 17.61 - ASPHALT JOINT SEALING.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
43-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
12-Doc 00 52 00 - AGREEMENT.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
3-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
19-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
42-Sec 31 23 16.26 - ROCK REMOVAL.pdf PDF
17-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
39-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
25-Sec 01 22 00 - 03 - MP PAVEMENT MARKING QUANTITIES.pdf PDF
34-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
51-Sec 01 57 13 - EROSION SEDIMENT CONTROL.pdf PDF
45-Sec 32 01 16.71 - MILLING OF BITUMINOUS PAVEMENT SURFACE.pdf PDF
2-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Sec 01 22 00 - 01 - MP BASE BID QUANTITIES.pdf PDF
54-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
21-Doc 00 91 13 - ADDENDA.pdf PDF
4-Doc 00 43 13 - BID BOND.pdf PDF
55-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
5-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
18-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Sec 31 20 00 - EARTHWORK.pdf PDF
27-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
14-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
26-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
47-Sec 01 50 00 - CONSTRUCTION FACILITIES.pdf PDF
9-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
8-Doc 00 41 00 - BID FORM - EBID.pdf PDF
36-Sec 01 26 73 - BITUMINOUS MATERIAL PRICE ADJUSTMENT.pdf PDF
10-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
22-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
56-2026 UMT Paving Map.pdf PDF
33-Sec 01 22 00 - 00 - MEASUREMENT AND PAYMENT.pdf PDF
53-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
1-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
20-Doc 00 73 00 - 01 - APPENDIX A PREVAILING WAGE RATES.pdf PDF
6-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
15-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
24-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
7-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
31-Sec 01 22 00 - 02 - MP ALTERNATE BID QUANTITIES.pdf PDF
37-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
Show all 50

Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRAFFIC REGULATION

01 55 26-1

SECTION 01 55 26

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. This Section involves the Contractor’s obligations relative to maintaining the safe and efficient movement of traffic in the vicinity of construction.

B. Contractor will be required to furnish, erect, and maintain traffic cones, drums, barricades, flashing danger signal lights, directional signs and provide trained and equipped flagmen as required by the State and local permit requirements to restrict the movement of traffic within the construction areas and to clearly indicate the restrictions well in advance to vehicular traffic.

1.02 SECTION INCLUDES

A. Traffic Control Plan B. Notification C. Construction parking controls.

D. Flag persons.

E. Flares and lights.

F. Haul routes.

G. Traffic signs and signals.

H. Other Requirements I. Removal.

1.03 RELATED SECTIONS

A. Section 01 11 13 - Summary of Work.

B. Section 01 31 00 - Coordination and Meetings: Coordination and Project conditions.

PART 2 - PRODUCTS

2.01 SIGNS, SIGNALS, AND DEVICES

A. Post Mounted and Wall Mounted Traffic Control and Informational Signs: As approved by the authority having jurisdiction.

B. Traffic Control Signals: As approved by the authority having jurisdiction.

C. Traffic Cones and Drums, Flares and Lights: As approved by the authority having jurisdiction.

D. Flagperson Equipment: As required by the authority having jurisdiction.

PART 3 - EXECUTION

3.01 TRAFFIC CONTROL PLAN

A. Contractor shall implement Traffic Control Plan requirements imposed by the Road Opening Permit issued by Upper Makefield Township relative to Work.

3.02 NOTIFICATIONS

A. Contractor shall provide advance notification to any parties so noted in the local municipal Road Opening Permit in accordance with the required time schedule. In any event, the local municipal Police Department shall be notified at least ten (10) days prior to the date Contractor desires to restrict traffic in or along any highways or roads.

B. Contractor shall obtain advance approval from the authority having jurisdiction should it be necessary to restrict traffic in or along any highways or roads, including temporary closure of a road. The following parties shall be notified at least three (3) days in advance:

1. Local Municipal Police

2. Local Fire Company

3. Local School District

01 55 26-2

4. Local Ambulance Service

5. All affected residents

C. At least one lane must be open for traffic during non-working periods and Contractor must be prepared to allow passage of emergency vehicles at any time.

D. The Contractor is responsible for notifying all property owners and residents that on-street parking will not be permitted during work hours. Notifications must be distributed 3 days prior to the milling and paving of each road and should include the specific the dates and times. If proper notice is not given, the Contractor will be responsible for the towing costs necessary to complete the work.

3.03 CONSTRUCTION PARKING CONTROLS

A. Control vehicular parking to prevent interference with public traffic and parking, access by emergency vehicles, and Owner's operations.

B. Monitor parking of construction personnel's vehicles in existing facilities. Maintain vehicular access to and through parking areas.

C. Prevent parking on or adjacent to access roads or in non-designated areas.

3.04 FLAG PERSONS

A. Provide trained and equipped flag persons to regulate traffic when construction operations or traffic encroach on public traffic lanes.

3.05 FLARES AND LIGHTS

A. Use flares and lights during hours of low visibility to delineate traffic lanes and to guide traffic.

3.06 HAUL ROUTES

A. Consult with authority having jurisdiction, establish public thoroughfares to be used for haul routes and site access.

3.07 TRAFFIC SIGNS AND SIGNALS

A. At approaches to site and on site, install at crossroads, detours, parking areas, and elsewhere as needed to direct construction and affected public traffic.

B. Install and operate [automatic] traffic control signals to direct and maintain orderly flow of traffic in areas under Contractor’s control, and areas affected by Contractor’s operations.

C. Relocate as Work progresses, to maintain effective traffic control.

3.08 OTHER REQUIREMENTS

A. Maintain access at all times during non-working periods and to the maximum extent feasible during working periods to all driveways and entrances of adjacent properties. In this regard, use and maintenance of steel plates or other decking across the trench may be necessary to reduce to a minimum interference with access to the adjacent properties.

B. Provide safe decking over open trenches in or along highways or roads during non-work periods by the use and maintenance of steel plates or other decking, which shall have sufficient strength to safely support all traffic including truck loads.

C. Do not allow traffic to drive on any milled surface for more than 6 calendar days. The 1-1/2”-inch bituminous wearing course must be installed within 7 calendar days from the start of the milling operation.

3.09 REMOVAL

A. Remove equipment and devices when no longer required.

B. Repair damage caused by installation.

C. Remove post settings to a depth of 2 feet.

END OF SECTION