About this file
This is a Summary of Work document for Upper Makefield Township's 2026 Road Program in Pennsylvania, outlining the scope of construction activities for a base bid and multiple alternate bids. The contract encompasses milling, base repair, leveling course, manhole rim adjustments, and wearing course along various roads within Upper Makefield Township. Specific roadway locations and associated quantities are detailed in Exhibits A, B, and C of Section 01 22 00 Measurement and Payment. The contractor is responsible for obtaining and providing third-party testing results performed on-site in accordance with PennDOT publication 408, section 702 standards. Construction work must be performed while existing roadways and utilities remain in active use, requiring the contractor to implement precautions to protect all water, gas, electric, communications, sanitary sewer, storm sewer, and other facilities. The contractor must notify property owners and residents at least three days prior to milling, paving, and joint sealant operations regarding on-street parking restrictions and is responsible for towing costs if proper notice is not provided. All work must comply strictly with OSHA Construction Workplace Safety Standards, and the contractor must provide biweekly schedule updates documenting completed work and anticipated completion timelines.
The contractor must determine utility locations in accordance with Pennsylvania Act 287, as amended by Act 121, prior to beginning work and is responsible for identifying and reporting potential drainage or ponding issues to G&A for remediation planning. Construction hours are restricted to 7:30 A.M. through 5:30 P.M., including equipment movement. The owner will occupy the site throughout the entire construction period, and the contractor may propose an alternate sequence of construction subject to engineer approval. No products will be supplied by the owner, and no concurrent work is planned by other parties at the specified locations. Coordination with the resident project representative and Upper Makefield Township is required for scheduling and placement of "No Parking" signage.
View the file
Other files for this state and local contract opportunity
Show all 50
Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF WORK
01 11 13-1
SECTION 01 11 13
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Description of Work.
2. Work by Owner.
3. Work by other parties.
4. Owner supplied Products.
5. Contractor use of site [and premises].
6. Future work.
7. Work sequence of construction.
8. Owner occupancy.
1.02 DESCRIPTION OF WORK
A. This contract consists of a base bid and alternate bids. Both the base and alternate bids involve milling, base repair, leveling course, manhole rim adjustments, and wearing course along various roads within Upper Makefield Township. The roadway and quantities associated with the base bid and each alternate are more fully defined in Exhibits A and B of Section 01 22 00 Measurement and Payment.
B. Contractor will be responsible for providing results of third-party testing performed on site as required by the Contract Documents and in accordance with PennDOT publication 408, section 702 standards.
1.03 WORK BY OWNER
A. No other work is being planned by Owner at the specified locations during construction of the Work under this contract.
1.04 WORK BY OTHER PARTIES
A. No other work is being planned by Other Parties at the specified locations during construction of the Work under this contract
1.05 OWNER SUPPLIED PRODUCTS
A. No Products are to be supplied and paid for by Owner.
1.06 CONTRACTOR USE OF SITE AND PREMISES
A. The Work under this contract must be accomplished while the existing roadway and utilities are in use. The work that is involved with the existing roadway and utilities must be done so that system operations will not be jeopardized.
B. Contractor shall take all necessary precautions to protect all existing water, gas, electric, communications, sanitary sewer, storm sewer, or other facilities encountered during the course of his operations, to guard against disruption of service. Before beginning Work, Contractor shall determine the location of each facility which is questionable. The location of utilities are not shown on the Drawings and it is the responsibility of Contractor to establish the exact location in accordance with the requirements of Pennsylvania Act 287 (1974) as last amended by Act 121 (2008).
C. Contractor is responsible for notifying all property owners and residents a minimum of 3 days prior to milling, paving and/or joint sealant operations that on-street parking will not be permitted during work hours. Notifications must include specific the dates and times for each roadway. If proper notice is not given, the Contractor will be responsible for the towing costs necessary to complete the work. Upon request, Upper Makefield Township can post ‘No
01 11 13-2
Parking’ signage during Contractor’s milling and paving operations. Contractor shall coordinate the schedule and placement of signage with resident project representative and Upper Makefield Township.
D. Contractor shall conduct all Work in strict compliance with OSHA Construction Workplace Safety Standards.
E. Contractor will be responsible for notifying G&A immediately if they observe/identify any locations of potential drainage/ponding issues while completing the required preconstruction video/photographs or during construction so a plan of action can be created to remediate the issue.
F. Contractor will be responsible for providing schedule updates on a biweekly basis detailing completed work and timeline for anticipated completion of remaining work.
1.07 FUTURE WORK
A. No future work is planned.
1.08 WORK SEQUENCE OF CONSTRUCTION
A. Contractor may propose an alternate sequence of construction subject to approval by Engineer.
1.09 OWNER OCCUPANCY
A. Owner will occupy the site during the entire period of construction of construction.
1.10 MUNICIPALITY SPECIFIC REQUIREMENTS
A. Time of Work
Construction at the job site may not begin before 7:30 A.M and must be terminated by 5:30 P.M. This work limitation also includes the moving of equipment.
END OF SECTION