This is a Clearing and Grubbing specification document (Section 31 11 00) for the Upper Makefield Township 2026 Road Program in Pennsylvania. The specification defines work requirements for clearing, grubbing, stripping and stockpiling topsoil, and debris disposal as part of roadway construction activities. The clearing work includes removal of trees, brush, vegetation, fences, walls, signs, and other obstructions within permanent and temporary construction easements and the limit of disturbance on the Owner's property. Grubbing operations require removal of stumps, roots, brush, and organic materials to a minimum depth of eight inches below the natural ground surface. The contractor must notify the Engineer at least 48 hours prior to beginning clearing work and must coordinate tree removal with the Resident Project Representative. Topsoil stripping must be staged to limit exposure and potential erosion, with staging limited to the length of trench that can be installed and backfilled in one day for utility construction. All stockpiled topsoil must be retained on-site for use in finish grading and cannot be removed or used as backfill.
The specification establishes that trees, logs, branches, brush, stumps, and debris resulting from clearing and grubbing become the property of the contractor and must be disposed of legally at locations outside the Owner's property, easements, and public right-of-ways. The contractor must obtain written agreements with property owners where debris will be deposited and submit two copies of these agreements to release the Owner from responsibility. Open burning of debris is prohibited. The contractor must protect designated trees and landscape features with temporary fencing, repair any injuries to retained plants using approved arboricultural practices, and replace any trees designated to be saved that are permanently injured or die during construction with like species acceptable to the property owner. Related work is specified in Sections 01 57 13 (Soil Erosion and Sediment Control), 31 23 33 (Excavation, Backfill and Compaction), and 32 92 00 (Finish Grading, Seeding and Sodding), with compliance required for Pennsylvania Act 287 (1974) as amended by PA Act 121 (2008) regarding utility relocations.
View the file
Other files for this state and local contract opportunity
Show all 50
Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLEARING AND GRUBBING
31 11 00-1
SECTION 31 11 00
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Clearing
2. Grubbing
3. Stripping and stockpiling topsoil
4. Debris disposal
B. Definitions:
1. Clearing is defined as the removal of trees, brush, down timber, rotten wood, rubbish, any other vegetation, and objectionable material at or above original ground elevation not designated to be saved. Clearing also includes removal of fences, walls, guard posts, guard rail, signs, and other obstructions interfering with the proposed work.
2. Grubbing is defined as the removal from below the surface of the natural ground of stumps, roots and stubs, brush, organic materials and debris.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 57 13: Soil Erosion and Sediment Control
2. Section 31 23 33: Excavation, Backfill and Compaction
3. Section 32 92 00: Finish Grading, Seeding and Sodding
1.03 JOB CONDITIONS
A. Contractor may clear all obstructions within the permanent and temporary construction easements and within the limit of disturbance of Owner's property as absolutely necessary to perform the construction work. Contractor shall leave as many trees as possible within the temporary construction easements and shall not disturb portions of Owner's property beyond the limit of disturbance. Removal of trees shall be coordinated with the Resident Project Representative.
1.04 SUBMITTALS
A. Agreements for Disposal of Debris:
1. Arrange for disposal of debris resulting from clearing and grubbing to locations outside Owner's property, easements and public right-of-ways and obtain a written agreement with the owners of each property where the debris will be deposited.
2. Submit two (2) copies of the agreement with each property owner releasing Owner from responsibility in connection with the disposal of the debris.
PART 2 - PRODUCTS
2.01 MATERIALS
31 11 00-2
A. Temporary Fencing:
1. Undamaged picket snow fence, 4' high, formed of wooden slats, tightly woven with wire cable or orange, open mesh plastic construction fencing, 4' high, or other acceptable, highly visible, weather resistant, easily maintained fencing that provides a substantial barrier.
2. Soil-set fence posts, studded "T" type, 6' high.
B. Tree Wound Dressing:
1. Antiseptic and waterproof, asphalt base.
PART 3 - EXECUTION
3.01 PREPARATION
A. Notify Engineer at least 48 hours prior to beginning any clearing work.
B. Protect benchmarks, utilities, existing trees, shrubs and other landscape features designated for preservation with temporary fencing or barricades satisfactory to the Resident Project Representative. No material shall be stored or construction operation carried on within four
(4) feet of any tree to be saved or within the tree protection fence.
3.02 UTILITY RELOCATIONS
A. Inform all companies, individuals and others owning or controlling facilities or structures within the limits of the work which have to be relocated, adjusted or reconstructed in sufficient time for the utility to organize and perform such work in conjunction with or in advance of Contractor's operations.
B. Comply with the provisions of PA Act 287 (1974) as last amended by PA Act 121 (2008).
3.03 CLEARING
A. Confine clearing as required to within the limits of the public right-of-ways,easements and Owner's property. Attention is called to Paragraph 1.03 of this Section.
B. Fell trees in a manner that will avoid damage to trees, shrubs, and other installations which are to be retained.
C. Where stumps are not required to be grubbed, flushcut with ground elevation.
3.04 GRUBBING
A. Turf clearing and grubbing shall be staged to limit exposure and potential erosion. [For utility construction, stages shall be limited to that length of trench which may be installed and backfilled in one (1)day.]
B. Grub areas within the construction limits to remove roots and other objectionable material to a minimum depth of 8".
C. Remove all stumps within the cleared areas unless otherwise authorized by the Resident
Project Representative.
31 11 00-3
3.05 STRIPPING AND STOCKPILING TOPSOIL
A. Stripping of topsoil shall be staged to limit exposure and potential erosion. [For utility construction, stages shall be limited to that length of trench which may be installed and backfilled in one (1) day.]
B. Strip topsoil to whatever depth it may occur from areas to be excavated, filled, or graded and stockpile at a location approved by the Resident Project Representative for use in finish grading.
C. Topsoil shall not be used as backfill or removed from the site.
3.06 DEBRIS DISPOSAL
A. Trees, logs, branches, brush, stumps, and other debris resulting from clearing and grubbing operations associated with the Work on the Project site and/or within off-site easements/public right-of-ways shall become the property of Contractor and shall be disposed of legally.
B. Debris resulting from the clearing and grubbing work shall not be deposited or buried on the
Project site, easements or public right-of-ways.
C. Open burning of debris is prohibited.
3.07 RESTORATION
A. Repair all injuries to bark, trunk, limbs, and roots of remaining plants by properly dressing, cutting, tracing and painting, using approved arboricultural practices and materials.
B. Replace trees, shrubs and plants designated to be saved which are permanently injured or die during the Contract or the maintenance period as a result of construction operations with like species acceptable to the property owner.
C. Remove protective fences, enclosures and guards upon the completion of the project.
D. Restore guard posts, guard rail, signs and other interferences to the condition equal to that existing before construction operations.
END OF SECTION