50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf

PDF 109 KB Posted

Attached to
Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 State and local contract opportunity
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Coordination and Meetings specification section for the Upper Makefield Township 2026 Road Program in Pennsylvania. The specification establishes requirements for project coordination, field engineering, and various meetings throughout the construction process. The work includes milling, base repair, leveling course, manhole rim adjustments, and wearing course along various roads within Upper Makefield Township, with quantities and scope defined in Exhibits A, B, and C of Section 01 22 00. The contract requires a preconstruction meeting to be scheduled by the Engineer after the Effective Date and prior to commencement of work, with attendance from the Owner, Engineer, Resident Project Representative, Contractor, Contractor's Superintendent, and major Subcontractors. Meeting minutes must be recorded and distributed within five working days. Progress meetings are scheduled on an as-needed basis throughout construction, and pre-installation meetings are required for specific sections as designated in individual specification sections.

The specification establishes comprehensive coordination requirements to ensure construction work does not interfere with Owner operations and public access. The Contractor is responsible for all construction-related damage to property on site and must maintain access to private driveways at all times. The Contractor must provide weekly milling and paving schedule updates to the Resident Project Representative. The specification acknowledges that other contracts may be under construction simultaneously and requires the Contractor to schedule work to avoid conflicts, promptly repair any damage caused to other contractors' work at the Contractor's expense, and suspend or modify work as directed by the Engineer to facilitate other contractors' operations. The Contractor cannot claim extra compensation or damages for delays caused by other contractors' work unless specifically permitted in the Contract Documents.

View the file

Other files for this state and local contract opportunity

Other files attached to Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11, newest first.
File Type Posted
2-6715-11 CONTRACT DRAWINGS.pdf PDF
1-6715-11 CONTRACT DOCUMENTS.pdf PDF
52-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
13-Doc 00 62 16-CERTIFICATE OF INSURANCE.pdf PDF
44-Sec 32 01 17.61 - ASPHALT JOINT SEALING.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
43-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
12-Doc 00 52 00 - AGREEMENT.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
3-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
19-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
42-Sec 31 23 16.26 - ROCK REMOVAL.pdf PDF
17-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
39-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
25-Sec 01 22 00 - 03 - MP PAVEMENT MARKING QUANTITIES.pdf PDF
10-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
22-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
56-2026 UMT Paving Map.pdf PDF
33-Sec 01 22 00 - 00 - MEASUREMENT AND PAYMENT.pdf PDF
53-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
1-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
20-Doc 00 73 00 - 01 - APPENDIX A PREVAILING WAGE RATES.pdf PDF
6-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
15-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
24-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
7-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
31-Sec 01 22 00 - 02 - MP ALTERNATE BID QUANTITIES.pdf PDF
37-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
49-Sec 32 12 23-RESTORATION OF PAVED SURFACES.pdf PDF
28-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Doc 00 73 00 - 03 - APPENDIX B COVER.pdf PDF
16-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
29-Doc 00 73 00 - 04 - APPENDIX B PUBLIC WORKS EMPLOYMENT VERIFICATION FORM.pdf PDF
35-Sec 31 11 00-CLEARING AND GRUBBING.pdf PDF
41-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
34-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
51-Sec 01 57 13 - EROSION SEDIMENT CONTROL.pdf PDF
45-Sec 32 01 16.71 - MILLING OF BITUMINOUS PAVEMENT SURFACE.pdf PDF
2-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Sec 01 22 00 - 01 - MP BASE BID QUANTITIES.pdf PDF
54-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
21-Doc 00 91 13 - ADDENDA.pdf PDF
4-Doc 00 43 13 - BID BOND.pdf PDF
55-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
5-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
18-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Sec 31 20 00 - EARTHWORK.pdf PDF
Show all 50

Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COORDINATION AND MEETINGS

01 31 00-1

SECTION 01 31 00

COORDINATION AND MEETINGS

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work of this Section Includes:

1. Coordination and Project conditions.

2. Field engineering.

3. Preconstruction meeting.

4. Progress meetings.

5. Pre-installation meetings.

6. Construction coordination requirements.

1.02 RELATED SECTIONS

A. Section not used.

1.03 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements, supports, and installation of mechanical and electrical Work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion and for portions of Work designated for Owner’s partial occupancy.

F. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s activities.

1.04 FIELD ENGINEERING

A. Contractor shall locate survey control and reference points and provide stakeout as required for construction activities. Contractor is responsible for the protection of survey control and reference points and will compensate Owner for re-establishment of survey control and reference points.

B. Verify set-backs and easements; confirm drawing dimensions and elevations.

C. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.

D. Construct Work based on elevations, lines and locations as established, utilizing recognized survey control points and stakeout.

1.05 PRECONSTRUCTION MEETING

A. Engineer will schedule a meeting at the Project site after the Effective Date of the Agreement and prior to commencement of Work and Contractor occupancy, prepare an agenda with copies for participants, and preside at the meeting.

B. Attendance Required: Owner, Engineer, Resident Project Representative, Contractor, Contractor’s Superintendent and major Subcontractors.

C. Agenda:

01 31 00-2

1. Distribution of Contract Documents.

2. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

3. Designation of personnel representing the parties in Contract, and the Engineer.

4. Procedures and processing of field decisions, submittals, substitutions, applications for payments, Change Orders, and Contract closeout procedures.

5. Scheduling.

6. Use of premises by Owner and Contractor.

7. Owner's requirements and occupancy.

8. Construction facilities and controls provided by Owner.

9. Security and housekeeping procedures.

10. Procedures for testing.

11. Procedures for maintaining record documents.

12. Inspection and acceptance of work.

D. Engineer shall record minutes and distribute copies within five (5) working days after meeting to Owner and all other participants.

1.06 PROGRESS MEETINGS

A. Meetings shall be scheduled throughout progress of the Work on an as-needed basis.

B. Resident Project Representative will make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Contractor's superintendent, major Subcontractors and suppliers, Engineer as appropriate to agenda topics for each meeting.

D. Resident Project Representative shall record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.

1.07 PRE-INSTALLATION MEETINGS

A. When required in individual specification sections, convene a pre-installation meeting at the site prior to commencing work of the section.

B. Require attendance of parties directly affecting, or affected by, work of the specific section.

C. Notify Resident Project Representative five (5) working days in advance of meeting date.

D. Prepare agenda and preside at meeting:

1. Review conditions of installation, preparation and installation procedures.

2. Review coordination with related work.

E. Record minutes and distribute copies within five (5) working days after meeting to Owner, Engineer and all other participants.

PART 2 – PRODUCTS

2.01 Not Used.

PART 3 – EXECUTION

3.01 CONSTRUCTION COORDINATION REQUIREMENTS

A. General

1. Construction work under this contract shall not interfere with the operations of the Owner and the general public. Contractor shall be responsible for any construction related damage to private/leased or Owner owned property on the site. Access to private driveways must be maintained at all times during the course of the Work and Contractor shall accommodate periodic needs of the Owner and residents for access to site.

2. Contractor shall provide the Resident Project Representative with weekly milling and paving schedule updates.

01 31 00-3

B. Coordination of Contractor’s, other contractor’s and Owner’s Workmen

1. Contractor is advised that construction of other contracts may be in progress at the same time that this Contract is under construction. Contractor shall schedule his work so as not to conflict or interfere with these other contracts.

2. Contractor shall conduct his operations so as not to interfere with or injure the work of other contractors or workmen performing work for Owner. Contractor shall promptly repair, at his own expense, any injury or damage which may be done to such work by him or his employees, agents, or subcontractors.

3. Contractor shall suspend such part of the Work, or shall carry on the same in such a manner as may be ordered by Engineer when necessary to facilitate the work of such other contractors and workmen of Owner.

4. Any difference which may arise between Contractor and any other contractors or workmen of Owner in regard to their Work shall be determined and adjusted by Owner insofar as Owner has authority.

5. Contractor shall not claim any extra compensation or damages as a result of delays or hindrances which may be caused by the work of such contractors or workmen of Owner, unless specifically permitted elsewhere in the Contract documents.

END OF SECTION

File details come from the government source that posted it. Updated .