This is a Submittals specification document (Section 01 33 00) for the Upper Makefield Township 2026 Road Program in Pennsylvania. The specification establishes comprehensive submittal procedures and requirements for the construction project, which includes milling, base repair, leveling course, manhole rim adjustments, and wearing course work along various township roads. The document outlines mandatory submission protocols for construction progress schedules, product data, shop drawings, samples, design data, test reports, and certificates. Contractors must submit preliminary progress schedules within 10 days after the effective date of agreement and final schedules within 10 days of the preconstruction conference. All submittals require sequential numbering with alphabetic suffixes for revisions, contractor certification and stamps, and identification of project, contractor, subcontractor, supplier information, and relevant specification sections. The Engineer allows 15 days for review of each submittal excluding delivery time, and contractors must provide three copies of product data and shop drawings for Engineer retention, plus copies for field distribution and record documentation purposes.
The specification establishes detailed requirements for various submittal categories, including construction progress schedules presented as horizontal bar charts identifying work sequences, activity durations, start and finish dates, float dates, and estimated completion percentages. Product data, shop drawings, and samples must indicate utility and electrical characteristics, connection requirements, and outlet locations for functional equipment. Samples must illustrate both functional and aesthetic characteristics with integral parts and attachment devices, and reviewed samples may be used in the work as specified in individual specification sections. Certificates of conformance from manufacturers, installation subcontractors, or contractors must indicate that products meet or exceed specified requirements and may reference recent or previous test results acceptable to the Engineer. The specification requires that submittals not previously requested will not be recognized or processed, and all parties must promptly report any inability to comply with established requirements.
View the file
Other files for this state and local contract opportunity
Show all 50
Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUBMITTALS
01 33 00-1
SECTION 01 33 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Submittal procedures.
2. Construction progress schedules.
3. Product data.
4. Shop Drawings.
5. Samples.
6. Design data.
7. Test reports.
8. Certificates.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 40 00: Quality Control: Manufacturers' field services.
2. Section 01 70 00: Contract Closeout: Contract closeout submittals including maintenance bond, manufacturers’ warranties, and record drawings.
1.03 REFERENCES
A. AGC (Associated General Contractors of America) publication “The Use of CPM in Construction - A Manual for General Contractors and the Construction Industry”.
1.04 SUBMITTAL PROCEDURES
A. Transmit each submittal to Engineer.
B. Sequentially number the transmittal forms. Revise submittals with original number and a sequential alphabetic suffix.
C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.
D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.
E. Schedule submittals to expedite the Project and to coordinate submission of related items.
F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.
G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.
H. Provide space for Contractor and Engineer review stamps.
I. When revised for resubmission, identify all changes made since previous submission.
J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.
K. Submittals not requested will not be recognized or processed.
1.05 CONSTRUCTION PROGRESS SCHEDULES
A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of Agreement for review by Engineer.
B. Revise and resubmit as required.
01 33 00-2
C. Submit final progress schedule within 10 days of preconstruction conference or within 10 days upon request of Engineer if no preconstruction conference is to be held.
D. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version.
E. Submit a horizontal bar chart with separate line for each section of Work, identifying first work day of each week.
F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.
G. Indicate estimated percentage of completion for each item of Work at each submission.
H. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by Owner.
1.06 PRODUCT DATA
A. Product Data For Review:
1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
B. Product Data For Information:
1. Submitted for the Engineer’s knowledge as contract administrator or for OWNER.
C. Product Data For Project Closeout:
1. Submitted for Owner’s benefit during and after project completion.
D. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.
E. Mark each copy to identify applicable Products, models, options, and other data. Supplement manufacturers’ standard data to provide information specific to this Project.
F. Indicate Product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
1.07 SHOP DRAWINGS
A. Shop Drawings For Review:
1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, produce copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
B. Shop Drawings For Information:
1. Submitted for Engineer’s knowledge as contract administrator or for Owner.
C. Shop Drawings For Project Closeout:
1. Submitted for Owner’s benefit during and after project completion.
D. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
E. Submit the number of opaque reproductions which Contractor requires, plus three copies which will be retained by Engineer.
01 33 00-3
1.08 SAMPLES
A. Samples For Review:
1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, produce duplicates and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
B. Samples For Information:
1. Submitted for Engineer’s knowledge as contract administrator or for Owner.
D. Submit samples to illustrate functional and aesthetic characteristics of the Product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.
E. Include identification on each sample, with full Project information.
F. Submit the number of samples specified in individual specification sections; one of which will be retained by Engineer.
G. Reviewed samples which may be used in the Work are indicated in individual specification sections.
H. Samples will not be used for testing purposes unless specifically stated in the specification section.
1.09 DESIGN DATA
A. Submit for Engineer’s knowledge as contract administrator or for Owner.
B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
1.10 TEST REPORTS
A. Submit for Engineer’s knowledge as contract administrator or for Owner.
B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
1.11 CERTIFICATES
A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.
B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION