Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Consent of Surety to Final Payment document associated with Upper Makefield Township's 2026 Road Paving Program (CN #26-00060) located in Newtown, Pennsylvania. The document serves as formal approval from a surety company for final payment to the contractor upon completion of work. The project involves milling, base repair, leveling course, manhole rim adjustments, and wearing course improvements along various roads within Upper Makefield Township, with specific roadways and quantities defined in Exhibits A, B, and C of the contract documents. The contract structure includes a base bid and three alternate bids for road improvements.

The surety company, upon examination of the contractor's books and records or receipt of an affidavit confirming settlement of all labor and materials claims, approves final payment to the contractor. The surety company's bond obligations to Upper Makefield Township remain in full force and effect notwithstanding the final payment authorization. This document requires execution by the Surety Company with corporate seal and signature of an authorized officer (President, Vice President, or other authorized representative with proper certification of authority). The consent form must be completed with the specific effective date prior to final payment release to the contractor.

View the file

Other files

File Type Posted
2-6715-11 CONTRACT DRAWINGS.pdf PDF
1-6715-11 CONTRACT DOCUMENTS.pdf PDF
51-Sec 01 57 13 - EROSION SEDIMENT CONTROL.pdf PDF
3-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
37-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
15-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
49-Sec 32 12 23-RESTORATION OF PAVED SURFACES.pdf PDF
20-Doc 00 73 00 - 01 - APPENDIX A PREVAILING WAGE RATES.pdf PDF
1-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
9-Doc 00 01 15 - LIST OF DRAWINGS.pdf PDF
42-Sec 31 23 16.26 - ROCK REMOVAL.pdf PDF
12-Doc 00 52 00 - AGREEMENT.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
25-Sec 01 22 00 - 03 - MP PAVEMENT MARKING QUANTITIES.pdf PDF
27-Sec 01 32 16 - NARRATIVE CONSTRUCTION SCHEDULE.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
33-Sec 01 22 00 - 00 - MEASUREMENT AND PAYMENT.pdf PDF
24-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
28-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
7-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
19-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
23-Doc 00 73 00 - 03 - APPENDIX B COVER.pdf PDF
31-Sec 01 22 00 - 02 - MP ALTERNATE BID QUANTITIES.pdf PDF
35-Sec 31 11 00-CLEARING AND GRUBBING.pdf PDF
16-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
36-Sec 01 26 73 - BITUMINOUS MATERIAL PRICE ADJUSTMENT.pdf PDF
5-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
40-Sec 31 20 00 - EARTHWORK.pdf PDF
44-Sec 32 01 17.61 - ASPHALT JOINT SEALING.pdf PDF
55-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
14-Doc 00 65 19.13 - CONTRACTORS AFFIDAVIT.pdf PDF
22-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
43-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
13-Doc 00 62 16-CERTIFICATE OF INSURANCE.pdf PDF
17-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
6-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
53-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
39-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
47-Sec 01 50 00 - CONSTRUCTION FACILITIES.pdf PDF
10-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
52-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
29-Doc 00 73 00 - 04 - APPENDIX B PUBLIC WORKS EMPLOYMENT VERIFICATION FORM.pdf PDF
8-Doc 00 41 00 - BID FORM - EBID.pdf PDF
26-Doc 00 73 00 - 01 - APPENDIX A COVER.pdf PDF
4-Doc 00 43 13 - BID BOND.pdf PDF
56-2026 UMT Paving Map.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
Show 40 more

Latest 50 of 57 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSENT OF SURETY TO FINAL PAYMENT

00 65 19.19-1

DOCUMENT 00 65 19.19

CONSENT OF SURETY TO FINAL PAYMENT

In accordance with the provisions of an Agreement for the Work associated with

CN #26-00060: 2026 ROAD PAVING PROGRAM, between

Upper Makefield Township, 1076 Eagle Road, Newtown PA 18940 and

(Owner, Name and Address)

(Contractor, Name and Address) the ___________________________________________________________________, surety on the bond(s) of (Surety Company)

___________________________________________________________after a careful examination of the books and (Contractor) records of Contractor or after receipt of an affidavit from Contractor, which examination or affidavit satisfies this company that all claims for labor and materials have been satisfactorily settled, hereby approves of the final payment to ____________________________________________________________________, and by these presents (Contractor) witnesseth that payment to Contractor of the final estimate shall not relieve the Surety Company of any of its obligations to Upper Makefield Township as set forth in the Surety Company’s Bond.

(Owner)

IN WITNESS WHEREOF, the Surety Company has hereunto set its hand and seal this ______day of

___________________________, 20______.

SURETY

Company:

(Corp. Seal) Signature:

Name and Title:

NOTE: This statement, if executed by any person other than the President or Vice President of the

Surety Company, must be accompanied by a current and effective certificate showing authority conferred upon the person so signing to execute such instruments on behalf of the Surety Company represented.

END OF DOCUMENT

File details come from the government source that posted it. Updated .