This is a Narrative Construction Schedule specification section for the Upper Makefield Township 2026 Road Program in Pennsylvania. The specification outlines requirements for contractors to prepare, maintain, and revise a detailed construction project schedule to monitor progress and duration of roadway operations. The contractor must submit an initial schedule prior to construction start, based on the anticipated Notice to Proceed Date, that outlines the start date of milling and paving operations for each base bid and alternate bid roadway. The schedule submission is required before the owner will release progress payments. The engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. The work involves milling, base repair, leveling course, manhole rim adjustments, and wearing course along various roads within Upper Makefield Township, with specific roadway information and quantities defined in Exhibits A, B, and C of Section 01 22 00.
The contractor must provide a schedule that includes activity descriptions and locations, duration of activities in working days, start and finish calendar dates, and activity interdependencies. Additionally, the contractor must submit a workday calendar identifying work days and non-work days, number of shifts per day, and hours per shift. If the schedule is not received prior to construction start, the contractor will be required to attend a scheduling meeting to prepare an acceptable schedule, and the owner may withhold progress payments until scheduling is completed. Related coordination and meeting requirements are specified in Section 01 31 00.
View the file
Other files for this state and local contract opportunity
Show all 50
Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NARRATIVE CONSTRUCTION SCHEDULE
01 32 16-1
SECTION 01 32 16
NARRATIVE CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.01 SECTION DESCRIPTION
A. The Work Of This Section Includes:
1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 31 00 - Coordination and Meetings
PART 2 – PRODUCTS
2.01 Not Used
PART 3 - EXECUTION
3.01 CONSTRUCTION SCHEDULE
A. Base the initial schedule on the anticipated Notice to Proceed Date in the proposal. Submit an initial schedule outlining the anticipated start date of milling and paving operations for each base bid and alternate bid roadway prior to the start of construction. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.
B. Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:
Activity description & location;
Duration of activity, in working days; and Start and finish calendar dates of activities.
D. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.
E. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.
F. If the schedule is not received prior to the start of construction, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.
END OF SECTION