This is a Narrative Construction Schedule specification section for the Upper Makefield Township 2026 Road Program in Pennsylvania. The specification outlines requirements for contractors to prepare, maintain, and revise a detailed construction project schedule to monitor progress and duration of roadway operations. The contractor must submit an initial schedule prior to construction start, based on the anticipated Notice to Proceed Date, that outlines the start date of milling and paving operations for each base bid and alternate bid roadway. The schedule submission is required before the owner will release progress payments. The engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. The work involves milling, base repair, leveling course, manhole rim adjustments, and wearing course along various roads within Upper Makefield Township, with specific roadway information and quantities defined in Exhibits A, B, and C of Section 01 22 00.

The contractor must provide a schedule that includes activity descriptions and locations, duration of activities in working days, start and finish calendar dates, and activity interdependencies. Additionally, the contractor must submit a workday calendar identifying work days and non-work days, number of shifts per day, and hours per shift. If the schedule is not received prior to construction start, the contractor will be required to attend a scheduling meeting to prepare an acceptable schedule, and the owner may withhold progress payments until scheduling is completed. Related coordination and meeting requirements are specified in Section 01 31 00.

View the file

Other files for this state and local contract opportunity

Other files attached to Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11, newest first.
File Type Posted
1-6715-11 CONTRACT DOCUMENTS.pdf PDF
2-6715-11 CONTRACT DRAWINGS.pdf PDF
10-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
22-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
56-2026 UMT Paving Map.pdf PDF
33-Sec 01 22 00 - 00 - MEASUREMENT AND PAYMENT.pdf PDF
53-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
1-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
20-Doc 00 73 00 - 01 - APPENDIX A PREVAILING WAGE RATES.pdf PDF
6-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
15-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
24-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
7-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
31-Sec 01 22 00 - 02 - MP ALTERNATE BID QUANTITIES.pdf PDF
37-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
49-Sec 32 12 23-RESTORATION OF PAVED SURFACES.pdf PDF
28-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Doc 00 73 00 - 03 - APPENDIX B COVER.pdf PDF
16-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
29-Doc 00 73 00 - 04 - APPENDIX B PUBLIC WORKS EMPLOYMENT VERIFICATION FORM.pdf PDF
50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
35-Sec 31 11 00-CLEARING AND GRUBBING.pdf PDF
41-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
34-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
51-Sec 01 57 13 - EROSION SEDIMENT CONTROL.pdf PDF
45-Sec 32 01 16.71 - MILLING OF BITUMINOUS PAVEMENT SURFACE.pdf PDF
2-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Sec 01 22 00 - 01 - MP BASE BID QUANTITIES.pdf PDF
54-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
21-Doc 00 91 13 - ADDENDA.pdf PDF
52-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
13-Doc 00 62 16-CERTIFICATE OF INSURANCE.pdf PDF
44-Sec 32 01 17.61 - ASPHALT JOINT SEALING.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
43-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
12-Doc 00 52 00 - AGREEMENT.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
3-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
19-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
42-Sec 31 23 16.26 - ROCK REMOVAL.pdf PDF
17-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
39-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
25-Sec 01 22 00 - 03 - MP PAVEMENT MARKING QUANTITIES.pdf PDF
4-Doc 00 43 13 - BID BOND.pdf PDF
55-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
5-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
18-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
Show all 50

Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NARRATIVE CONSTRUCTION SCHEDULE

01 32 16-1

SECTION 01 32 16

NARRATIVE CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.01 SECTION DESCRIPTION

A. The Work Of This Section Includes:

1. The preparation, maintenance, and revision of the construction project schedule to monitor progress of project operations and duration.

1.02 RELATED SECTIONS

A. Related Work Specified Elsewhere:

1. Section 01 31 00 - Coordination and Meetings

PART 2 – PRODUCTS

2.01 Not Used

PART 3 - EXECUTION

3.01 CONSTRUCTION SCHEDULE

A. Base the initial schedule on the anticipated Notice to Proceed Date in the proposal. Submit an initial schedule outlining the anticipated start date of milling and paving operations for each base bid and alternate bid roadway prior to the start of construction. Owner, after consultation with Contractor, may elect not to release progress payments until the schedule is submitted and accepted.

B. Engineer will review and respond to the detailed schedule and supporting documentation within 10 calendar days of receipt. Include, as a minimum, the following in the initial schedule and in all schedule revisions:

Activity description & location;

Duration of activity, in working days; and Start and finish calendar dates of activities.

D. In addition, submit a workday calendar showing work days and non-work days, number of shifts per day, and number of hours per shift.

E. Provide enough activities to demonstrate the necessary interdependencies. Use the above information to complete a narrative description of the construction schedule.

F. If the schedule is not received prior to the start of construction, Contractor will be required to attend a scheduling meeting in order to prepare an acceptable schedule. Owner may elect not to release progress payments until the scheduling has been completed.

END OF SECTION