55-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf

PDF 100 KB Posted

Attached to
Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 State and local contract opportunity
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a Contract Closeout specification document (Section 01 70 00) prepared for Upper Makefield Township's 2026 Road Program in Pennsylvania, outlining the procedures and requirements for project completion and final acceptance. The specification covers comprehensive closeout procedures including final cleaning of interior and exterior surfaces, equipment adjustment and sanitization, site debris removal, and submission of final applications for payment. The contractor must maintain on-site project record documents including marked-up drawings, specifications, addenda, change orders, shop drawings, and manufacturer's instructions, with all actual revisions and product substitutions documented concurrent with construction progress. Prior to final payment, the contractor must submit various documentation including payroll certification forms (for contracts exceeding $25,000), waivers of liens from all subcontractors and suppliers, maintenance bonds, Material Form CS-4171 for asphalt paving to satisfy Liquid Fuels funding requirements, equipment warranties, and CD/DVD copies of preconstruction documentation.

The specification does not address specific pricing terms, set-asides, or incumbent contractor information, as it functions as a standard closeout procedure applicable to the project's base bid and three alternate bids involving milling, base repair, leveling course, manhole rim adjustments, and wearing course work across various roads in Upper Makefield Township. Final payment is contingent upon completion of all punchlist items within contract time, successful final inspection by the Engineer, and submission of all required documentation. The Liquid Fuels funding requirement identified in the specification indicates that asphalt paving materials are funded through Pennsylvania's Liquid Fuels program, requiring specific material documentation for closeout compliance.

View the file

Other files for this state and local contract opportunity

Other files attached to Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11, newest first.
File Type Posted
2-6715-11 CONTRACT DRAWINGS.pdf PDF
1-6715-11 CONTRACT DOCUMENTS.pdf PDF
52-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
13-Doc 00 62 16-CERTIFICATE OF INSURANCE.pdf PDF
44-Sec 32 01 17.61 - ASPHALT JOINT SEALING.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
43-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
12-Doc 00 52 00 - AGREEMENT.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
3-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
19-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
42-Sec 31 23 16.26 - ROCK REMOVAL.pdf PDF
17-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
39-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
25-Sec 01 22 00 - 03 - MP PAVEMENT MARKING QUANTITIES.pdf PDF
41-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
34-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
51-Sec 01 57 13 - EROSION SEDIMENT CONTROL.pdf PDF
45-Sec 32 01 16.71 - MILLING OF BITUMINOUS PAVEMENT SURFACE.pdf PDF
2-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Sec 01 22 00 - 01 - MP BASE BID QUANTITIES.pdf PDF
54-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
21-Doc 00 91 13 - ADDENDA.pdf PDF
10-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
22-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
56-2026 UMT Paving Map.pdf PDF
33-Sec 01 22 00 - 00 - MEASUREMENT AND PAYMENT.pdf PDF
53-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
1-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
20-Doc 00 73 00 - 01 - APPENDIX A PREVAILING WAGE RATES.pdf PDF
6-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
15-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
24-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
7-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
31-Sec 01 22 00 - 02 - MP ALTERNATE BID QUANTITIES.pdf PDF
37-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
49-Sec 32 12 23-RESTORATION OF PAVED SURFACES.pdf PDF
28-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Doc 00 73 00 - 03 - APPENDIX B COVER.pdf PDF
16-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
29-Doc 00 73 00 - 04 - APPENDIX B PUBLIC WORKS EMPLOYMENT VERIFICATION FORM.pdf PDF
50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
35-Sec 31 11 00-CLEARING AND GRUBBING.pdf PDF
4-Doc 00 43 13 - BID BOND.pdf PDF
5-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
18-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
40-Sec 31 20 00 - EARTHWORK.pdf PDF
Show all 50

Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT CLOSEOUT

01 70 00-1

SECTION 01 70 00

PART 1 GENERAL

1.01 SECTION DESCRIPTION

A. The Work of This Section Includes:

1. Closeout procedures.

2. Final cleaning.

3. Adjusting.

4. Project record documents.

5. Operation and maintenance manual.

6. Spare parts and maintenance Products.

7. Other documentation.

1.02 RELATED SECTIONS

A. Section not used.

1.03 CLOSEOUT PROCEDURES

A. Submit written certification that Contract Documents have been reviewed, Work has been inspected, and that Work is complete in accordance with Contract Documents and ready for Engineer's review.

B. Engineer shall make a final inspection and prepare a punchlist of items remaining to be completed or corrected prior to final acceptance in accordance with Article 14, paragraph 14.06 of the General Conditions.

C. Complete all items on the punchlist, plus any new items that may be subsequently added, as soon as possible and within the Contract Time.

D. Provide submittals to Engineer that are required by governing or other authorities.

E. Submit final Application for Payment identifying total adjusted Contract Price, previous payments, and remaining amount due.

F. Final Payment will not be made until final completion and acceptance of the Work.

G. Owner will occupy all portions of the Project upon Substantial Completion upon completion and acceptance as specified in Section 01 11 13.

1.04 FINAL CLEANING

A. Execute final cleaning prior to final Project inspection.

B. Clean interior and exterior glass and surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.

C. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

D. Clean or replace filters of operating equipment.

E. Clean debris from roofs, gutters, downspouts, and drainage systems.

F. Clean site; sweep paved areas, rake clean landscaped surfaces.

G. Remove waste and surplus materials, rubbish, and construction facilities from the site.

1.05 ADJUSTING

A. Adjust operating Products and equipment to ensure smooth and unhindered operation.

1.06 PROJECT RECORD DOCUMENTS

A. Maintain on-site one set of the following record documents; record actual revisions to the Work:

1. Drawings.

01 70 00-2

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, Product data, and samples.

6. Manufacturer’s instructions for assembly, installation and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress.

E. Specifications: Legibly mark and record at each Product section description of actual Products installed, including the following:

1. Manufacturer's name and product model and number.

2. Product substitutions or alternates utilized.

3. Changes made by Addenda and modifications.

F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including:

1. Measured depth of foundations in relation to finish main floor datum.

2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

4. Field changes of dimension and detail.

5. Details not on original Contract Drawings.

G. Delete Engineer's title block and seal from all documents.

H. Submit documents to Engineer with claim for final Application for Payment.

1.07 OTHER DOCUMENTATION

A. Provide data and documentation properly completed and executed prior to final Application for Payment as Engineer may reasonably require including:

1. Payroll Certification forms by Contractor and all Subcontractors (if price exceeds $25,000).

2. Waiver of Liens by all Subcontractors and Suppliers or Contractor's Affidavit, Contractor's

Release of Liens and Consent of Surety to Final Payment.

3. Maintenance Bond.

4. CS-4171 Material Form from Suppliers for asphalt used during paving to closeout

Liquid Fuels funding requirements.

5. Any Change Orders with supporting documentation which remain to be submitted.

6. Test and/or sample results.

7. Equipment warranties.

8. CD/DVD copies of preconstruction documentation.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION